Behavior of shallow 2-Arch tunnel due to excavation under horizontal discontinuity plane

수평 불연속변 하부에 굴착한 얄은 심도의 2-Arch 터널의 거동

  • 전은숙 ((주)건화엔지니어링) ;
  • 김홍문 (아주대학교 건설교통공학과) ;
  • 이상덕 (아주대학교 환경건설교통공학부)
  • Published : 2005.09.01

Abstract

In this study, the behavior of shallow 2-Arch tunnel due to excavation under horizontal discontinuity plane was verified experimentally. The model tests were carried out by varying the overburden height and the location of the discontinuity plane. The model tests followed exactly the real 2-Arch tunnel construction stages. As a result, it is discovered that stress-transfer mechanism and loosening area around the 2-Arch tunnel depends on the overburden heights and the location of the discontinuity plane. And central pillar load is also dependent on overburden height, location of discontinuity plane and construction stages.

본 연구에서는 수평 불연속면 하부에 굴착한 얄은 섬도의 2-Arch 터널의 거동을 실험적으로 규명하고자 하였다. 이를 위하여 토피고와 불연속면의 위치를 변화시켜가며 모형실험을 수행하였다. 모형실험은 실제 2-Arch 터널의 Pilot 터널굴착에서 본선터널불착에 이르는 시공단계가 반영된 실험순서에 따라 진행되었다. 연구결과로 부터 토피고에 따른 2-Arch 터널 주변지반의 하중전이 메커니즘의 변화와 불연속면 위치에 따른 이완영역의 분포 및 범위의 변화를 확인하였다. 또한 시공단계에 따른 중앙필러의 역학적 거동을 규명하였으며 불연속면 위치가 터널에 근접할수록 중앙필러 작용하중이 증가하는 것을 확인하였다.

Keywords