Analysis of the Crew Productivity and Influence Factor for Special-Plant Reinforce Concrete
특수 플랜트 철근콘크리트 공종의 작업조 생산성 및 영향요인 분석
- Published : 2014.05.29
Abstract
Few studies on crew productivity has been conducted, although the data is significant for time and cost estimation. Crew productivity data was collected for over 9 months from a nuclear power plant and analysed in order to identify factors driving the productivity. It was revealed that the crew productivity of form work, rebar work and concrete pouring work was 45.64(㎡/crew·day), 2.93(t/crew·day), 110.25(㎡/crew·day) on average respectively. Moreover, 'nightwork', 'No. of workers per crew' and 'total work amount' were identified as drivers.