Proceedings of the Korean Institute of Building Construction Conference (한국건축시공학회:학술대회논문집)
- 2009.05b
- /
- Pages.171-174
- /
- 2009
Analysis of Actual Labor and Productivity for Based Work Crew Standard of Cement Liquid Watertight Construction
시멘트 액체방수 공사의 작업조 기반 품셈을 위한 생산량 및 노무량 분석
Abstract
The standard estimation system, used to estimate the predetermined cost of construction work, is measured by the standard and typical construction methods and field conditions. And the standard estimation system is applied to basic data for the measuring of construction cost, such as the consumed quantity of material, labor hours, and machinery cost. However it does not reflect sufficiently for the diversity and reality of constructions work Therefore, this study is recognized the necessity of new cost estimation models for the rational construction cost estimation. To improve estimation technique and construction ability, it was analyzed labor hours, production volume based on the work crew in construction work.