• Title/Summary/Keyword: concrete tunnel

Search Result 594, Processing Time 0.025 seconds

A Case Study of Collapse and Reinforcement for Large Span Waterway Tunnel at Thrust Fault Zone (스러스트 단층대에서의 대단면 수로터널 낙반 및 보강 사례)

  • Kim, Young-Geun;Han, Byeong-Hyun;Lee, Seung-Bok;Kim, Eung-Tae
    • Tunnel and Underground Space
    • /
    • v.21 no.4
    • /
    • pp.251-263
    • /
    • 2011
  • The geomechanical characteristics of rock and the structural geological feature of the fault should be studied and examined for the successful construction of large-span tunnel. In this case study, that is a important case for the tunnel collapse and reinforcement during the construction for the waterway tunnel at large thrust fault zone in schist, we carried out geological and geotechnical survey for make the cause and mechanism of tunnel collapse. Also, we have designed the reinforcement and re-excavation for the safe construction for collapse zone and have carried out successfully the re-excavation and finished the final concrete lining.

The Blasting Pollution Effects Estimation & The Excavation Construction Case Study Of Personal Museum On Tunnel (산악터널에 인접한 개인 박물관의 발파공해 영향평가 및 굴착 시공사례)

  • Kwon, Soon-Sub;Lee, Myong-Choul;Park, Tae-Soon;Jeong, In-Choul;Lee, Hyun-Gu
    • Proceedings of the KSR Conference
    • /
    • 2004.10a
    • /
    • pp.127-132
    • /
    • 2004
  • The third double-track construction part of work, called Chung Ang Railroad line(Deok-So$\∼$Won-Ju) is in progress and the personal museum located 330m from the starting point of Pal-Dang Tunnel(length=4,470m) line in the canyon is to be effected by rock blasting during the tunnel excavation work, especially museum articles and building itself. This paper is the example of application suitable tunnel rock blasting pattern for excavation after the case study about the investigation and analysis of rock blasting noise pollution during tunnel excavation work. The museum is a three-story building, RC concrete structure and is located 17m from the top of the tunnel, in the center of the double-track line. Comparing estimate vibration frequency with site vibration one, it can be verified the reasonable rock blasting noise pollution as improving the application of tunnel excavation rock blasting pattern. The above pattern has been selected economically and effectively and applied to our construction field.

  • PDF

Investigation of the Lining Load Induced by Backfill and Consolidation Grouting (배면 및 압밀그라우팅에 의한 터널 라이닝 하중 연구)

  • 박동순;김학준;김완영
    • The Journal of Engineering Geology
    • /
    • v.13 no.4
    • /
    • pp.445-456
    • /
    • 2003
  • Backfill grouting and consolidation grouting are major reinforcing methods that enhance the stability of tunnel by filling the gap between the tunnel lining and the ground and increasing the stiffness of the ground. However, the effect of the grouting on the tunnel lining is not well established. Field measurements such as pressuremeter test, Lugeon test, and lining instruments were peformed to analyze the grouting effect on the tunnel lining for a waterway tunnel. The elastic modulus was increased up to 5 times than that of original rock mass due to consolidation grouting. This study shows that only 10% of grout pressure was acting on the back face of the tunnel lining. The final results are expected to be used for the design of the concrete lining.

A Study on the Closure Ratio for Tunnel Face Stabilization during Tunnel Excavation in Sand Soil (사질토지반에서 터널굴착시 막장안정을 위한 폐합비에 관한 연구)

  • Kim, Sang-Hwan;Kim, Ji-Tae;Lim, Chae-Ho;Lee, In-Keun
    • Journal of the Korean Geotechnical Society
    • /
    • v.28 no.4
    • /
    • pp.79-89
    • /
    • 2012
  • This paper presents experimental and numerical studies on the closure ratio of tunnel face to reduce pressure and displacement occurring at tunnel face during tunnel excavation. In experimental study, model tests are carried out according to the closure ratio of tunnel face and tunnel depth. Model test results are analyzed and interpreted by numerical calculation in order to verify results obtained from experimental and numerical studies. It is clearly found that tunnel face stability increases with the increase of the closure ratio of tunnel face. The results also show that tunnel face is stable when the closure ratio of tunnel face is larger than 80%. This research will be very useful to develop the economical tunnel face closing system.

Literature study on the improvement of lightweight concrete in perspective of foaming agent (기포제 관점에서 경량기포 콘크리트의 개선방향에 관한 문헌적 연구)

  • Choi, Myeong-In;Lee, Han-seung
    • Proceedings of the Korean Institute of Building Construction Conference
    • /
    • 2015.11a
    • /
    • pp.141-142
    • /
    • 2015
  • This literature study is focused on the improvement of lightweight concrete in perspective of foaming agent. Lightweight concrete is the cured concrete as putting required amount of foaming agent to slurry which is a mixture of a certain amount of cement, sand, and water. It has lower density than general concrete, because foaming agent disintegrates numerous bubbles evenly and independently. Thus, it is capable of lightening the weight and great for sound absorption and insulation, In foreign countries, studies for structural lightweight concrete mainly of tunnel grouting and weight lightening of heavy structures are going along actively. Domestically, exterior panel and ALC blocks are alternatively used for flooring. Therefore, this research consider improvement of lightweight concrete in perspective of foaming agent with foundation study.

  • PDF

Effects of Artificial Vibrations on Strength and Physical Properties of Curing Concrete (인공진동의 크기가 양생콘크리트의 강도와 물성에 미치는 영향)

  • 임한욱;정동호;이상은
    • Tunnel and Underground Space
    • /
    • v.4 no.1
    • /
    • pp.31-37
    • /
    • 1994
  • The effects of blasting and ground vibratons on curing concrete have not been well studied. As a results unrealistic and costly ground vibration constraints have been placed on blasting and piling when it occurs in the vicinity of curing concrete. To study the effects of ground vibrations, a shaking table was made to produce peak particle velocities in the nearly same frequency range as found in construction blasting. Concrete blocks of 33.3X27.7X16.2cm were molded and placed on the shaking table. Different sets of concrete blocks were subjected to peak vibrations of 0.25, 0.5, 1.0, 5.0 and 10cm/sec. The impulses were applied at two hour intervals for thirty seconds. Along with unvibrated concrete blocks, the vibrated concrete samples with 60.3mm in diameters were measured for elastic moduli, sonic velocity, tensile and uniaxial compressive strength. Test results showed that the vibrations in curing concrete generally have effects on the uniaxial compressive strength or physical properties of the concrete.

  • PDF

Prediction of ground-condition ahead of tunnel face using electromagnetic wave - analytical study (전자기파를 이용한 터널전방 예측 -해석기법 중심으로)

  • Choi, Jun-Su;Cho, Gye-Chun;Lee, Geun-Ha;Yoon, Ji-Nam
    • Journal of Korean Tunnelling and Underground Space Association
    • /
    • v.6 no.4
    • /
    • pp.327-343
    • /
    • 2004
  • During tunnel construction, ground failures often occur due to existence of weak zones, such as faults, joints, and cavities, ahead of tunnel face. It is hard to detect effectively weak zones, which can lead underground structure to fail after excavation and before supporting, by using conventional characterization methods. In this study, an enhanced analytical method of predicting weak zones ahead of tunnel face is developed to overcome some problems in the conventional geophysical exploration methods. The analytical method is based on Coulomb's and Gauss' laws with considering the characteristics of electric fields subjected to rock mass. Using the developed method, closed form solutions are obtained to detect a spherical shaped zone and an oriented fault ahead of tunnel face respectively. The analytical results suggest that the presence of weak zones and their sizes, location, and states can be accurately predicted by combining a proper inversion process with resistance measured from several electrodes on the tunnel face. It appears that the skin depth or resistivity in rock mass is affected by the diameter of tunnel face, natural electric potential and noises induced by experimental measurement and spatial distribution of uncertain properties. The developed analytical solution is verified through experimental tests. About 1800 concrete blocks of 5cm by 5cm by 5cm in size are prepared and used to model a joint rock mass around tunnel face. Weak zones are simulated ahead of tunnel face with a material which has relatively higher conductivity than concrete blocks. Experimental results on the model test show a good agreement with analytical results.

  • PDF

Study of Load Combination and Member Force of Cut and Cover Tunnel by Design Codes (도시철도 개착식 구조물의 설계기준별 하중조합 및 단면력 검토)

  • Hur, Jin-Ho;Kim, Jin-Ho
    • Proceedings of the KSR Conference
    • /
    • 2011.10a
    • /
    • pp.1185-1190
    • /
    • 2011
  • In designing cut and cover tunnels, load combination applied Korea seismic design code of urban transit and its sections applied Korea concrete code 2003. However, by revision of Korea concrete code in 2007, engineers have been experiencing difficulties in their work. In this study, application of Korea concrete code 2007 for designing is reviewed by comparing load combination of related codes and member force.

  • PDF

Unsupported Sleepers in Transition Zone between Concrete Slab Track and Ballasted Track : Phenomena and Its Countermeasures (고속철도 콘크리트궤도-자갈도상궤도 완충구간의 뜬침목 발생 현상과 대책)

  • Jang, Seung-Yup;Im, Oh-Jin;Yang, Sin-Chu
    • Proceedings of the KSR Conference
    • /
    • 2007.11a
    • /
    • pp.1126-1131
    • /
    • 2007
  • In 1st Phase Kyeong-Bu High-Speed Line, to lessen the impact in the transition zone between concrete slab track(in tunnel) and ballasted track(on embankment), the ballast bonding method has been adopted. However, in this area, in the beginning of the operation, unsupported sleepers are found, and the track deterioration and damage of concrete sleepers have occurred. In this paper, the status and causes of unsupported sleepers are discussed and several repair measures are proposed.

  • PDF

A Numerical study on the Moisture Transport of Concrete Tunnel Linings with the Sprayable Waterproofing Membrane (뿜칠 방수 멤브레인이 시공된 터널 라이닝의 수분이동에 관한 수치해석 연구)

  • Lee, Chulho;Choi, Soon-Wook;Kang, Tae-Ho;Chang, Soo-Ho
    • Tunnel and Underground Space
    • /
    • v.26 no.3
    • /
    • pp.212-219
    • /
    • 2016
  • The sprayable waterproofing membrane is installed between shotcrete to provide crack bridging and hence prevent flow of liquid water as a waterproofing system. Because of its material characteristics, the sprayable membrane can be constructed at more complex structure than sheet membrane. The main component of the sprayable waterproofing membrane is a polymer-based material, therefore, moisture can migrate through sprayable waterproofing membrane materials by capillary and vapor diffusion mechanisms. The moisture transport mechanisms can have an influence on the degree of saturation and may influence the pore pressure and risk of freeze-thaw damage on concrete linings and membrane. In this study, long-term hygrothermal behavior was simulated with considering moisture transport and long-term effects on saturation of tunnel linings. From the simulation, due to water absorption and vapor transport properties of sprayable membrane, change of relative humidity and water content in tunnel lining can be evaluated.