Hossen, Muhammed Mufazzal;Kang, Sunkoo;Jung, JC;Kim, Jonghyun
Journal of the Korean Society of Systems Engineering
/
v.11
no.1
/
pp.9-24
/
2015
Construction industry faces a lot of inherent uncertainties and issues and the construction phase of nuclear power project is not free from this risk. This paper investigates promising methodologies to be used on nuclear power plant (NPP) construction schedule delay risk assessment by using entry level systems engineering approach. This study contains how the initial concept for the risk assessment methodology has been developed. In this point of view, this work structured on three main phases: needs analysis (NA), concept exploration (CE), and concept definition (CD) through systems engineering (SE) approach. Traditionally, the SE process is applied to technical development programs but this study opens up a new avenue that SE can also be successfully applied to the development and optimization of the risk assessment model. This study provides a rational and systematic process for developing and selecting the best risk assessment model. This paper selects analytic hierarchy process (AHP) method to assess NPP construction schedule delay risk for international project. As conclusion, the proposed concept and selected method can discriminate successfully and clearly among schedule delay risk assessment methods.
Journal of the Korea Institute of Military Science and Technology
/
v.14
no.5
/
pp.850-858
/
2011
The risk analysis plays an important role in weapon system acquisition project due to uncertainties in the acquisition process. But in domestic, studies on risk analysis are insufficient and risk cost is not included in acquisition budget in policy. Therefore, in this study, we suggest a method that measures risk or success probability of project using the stochastic model. In particular, in order to calculate the success probability, we apply the joint probability distribution model of cost and schedule that are critical factors influencing the project risk. And also we verify the applicability of this model in Korean defence industry environment through case studies.
Minhyuk Jung;Hyun-soo Lea;Moonseo Park;Bogyeong Lee
International conference on construction engineering and project management
/
2013.01a
/
pp.397-402
/
2013
In super-tall building construction projects, schedule risk factors which vertically change and are not found in the low and middle-rise building construction influence duration of a project by vertical attribute; and it makes hard to estimate activity or overall duration of a construction project. However, the existing duration estimating methods, that are based on quantity and productivity assuming activities of the same work item have the same risk and duration regardless of operation space, are not able to consider the schedule risk factors which change by the altitude of operation space. Therefore, in order to advance accuracy of duration estimation of super-tall building projects, the degree of changes of these risk factors according to altitude should be analyzed and incorporated into a duration estimating method. This research proposes a simulation model using Monte Carlo method for estimating activity duration incorporating schedule risk factors by weather conditions in a super-tall building. The research process is as follows. Firstly, the schedule risk factors in super-tall building are identified through literature and expert reviews, and occurrence of non-working days at high altitude by weather condition is identified as one of the critical schedule risk factors. Secondly, a calculating method of the vertical distributions of the weather factors such as temperature and wind speed is analyzed through literature reviews. Then, a probability distribution of the weather factors is developed using the weather database of the past decade. Thirdly, a simulation model and algorithms for estimating non-working days and duration of each activity is developed using Monte-Carlo method. Finally, sensitivity analysis and a case study are carried out for the validation of the proposed model.
Park, Jongho;Cho, Mingeon;Eom, Sae Ho;Park, Sun-Kyu
KSCE Journal of Civil and Environmental Engineering Research
/
v.43
no.1
/
pp.109-117
/
2023
Schedule delays present a major risk factor, as they can adversely affect construction projects, such as through increasing construction costs, claims from a client, and/or a decrease in construction quality due to trims to stages to catch up on lost time. Risk management has been conducted according to the importance and priority of schedule delay risk, but quantification of risk on the depth of schedule delay tends to be inadequate due to limitations in data collection. Therefore, this research used the BERT (Bidirectional Encoder Representations from Transformers) language model to convert the contents of aconstruction log, which comprised unstructured data, into WBS (Work Breakdown Structure)-based structured data, and to form a model of classification and quantification of risk. A process was applied to eight highway construction sites, and 75 cases of rain schedule delay risk were obtained from 8 out of 39 detailed work kinds. Through a K-S test, a significant probability distribution was derived for fourkinds of work, and the risk impact was compared. The process presented in this study can be used to derive various schedule delay risks in construction projects and to quantify their depth.
Journal of the Korean Operations Research and Management Science Society
/
v.35
no.4
/
pp.33-53
/
2010
When purchase prices of a raw material fluctuate over time, the total purchasing cost is mainly affected by reordering time. Existing researches focus on deciding the right time when the demand for each period is replenished at the lowest cost. However, the decision is based on expected future prices which usually turn out to include some error. This discrepancy between expected prices and actual prices deteriorates the performance of inventory models dealing with fluctuating purchase prices. In this paper, we propose a new inventory model which incorporates not only cost but also risk into making up a replenishment schedule to meet each period's demand. For each replenishment schedule, the risk is defined to be the variance of its total cost. By introducing the risk into the objective function, the variability of the total cost can be mitigated, and eventually more stable replenishment schedule will be obtained. According to experimental results from crude oil inventory management, the proposed model showed better performance over other models in respect of variability and cost.
Proceedings of the Korean Institute Of Construction Engineering and Management
/
2004.11a
/
pp.384-387
/
2004
It is very important to manage the risk in building construction because construction process has too many internal risk compared with others. So construction managers need more developed risk management system than the Present. While the study for the solution and management of generated risk is comparatively enough, the effort to confirm the risk of construction phase on pre-construction phase haying an major effect on total duration, is insufficient. For supporting the schedule risk management of pre-construction, this study suggests the reclassified risk breakdown structure and the investigation form for advance preparations on pre-construction Phase, which help the Poorly experienced construction manager to make more correct decisions and efficiently to execute risk management.
International conference on construction engineering and project management
/
2005.10a
/
pp.929-934
/
2005
The complex and dynamic job nature and the ever-changing working environment of construction projects inevitably present uncertainties to construction operations. Identification, evaluation and control of uncertainties constitute main elements of risk management and critical tasks of project management in construction. This paper is focused on application of a simplified discrete-event simulation approach in management of schedule-overrun risks, each being the combination of the occurrence probability of an uncertain interruptive factor and its potential consequence in terms of time delay. A case study observed from a concreting operation in Hong Kong is converted into a simulation model and analyzed with an in-house-developed simulation package for demonstrating how the proposed approach can be implemented to manage multiple schedule-overrun risks on construction projects.
HOSSEN, MUHAMMED MUFAZZAL;KANG, SUNKOO;KIM, JONGHYUN
Nuclear Engineering and Technology
/
v.47
no.3
/
pp.362-379
/
2015
In this study, Nuclear Power Plant (NPP) construction schedule delay risk assessment methodology is developed and the construction delay risk is assessed for turnkey international NPP projects. Three levels of delay factors were selected through literature review and discussions with nuclear industry experts. A questionnaire survey was conducted on the basis of an analytic hierarchy process (AHP) and Relative Importance Index (RII) methods and the schedule delay risk is assessed qualitatively and quantitatively by severity and frequency of occurrence of delay factors. This study assigns four main delay factors to the first level: main contractor, utility, regulatory authority, and financial and country factor. The second and the third levels are designed with 12 sub-factors and 32 sub-sub-factors, respectively. This study finds the top five most important sub-sub-factors, which are as follows: policy changes, political instability and public intervention; uncompromising regulatory criteria and licensing documents conflicting with existing regulations; robust design document review procedures; redesign due to errors in design and design changes; and worldwide shortage of qualified and experienced nuclear specific equipment manufacturers. The proposed combined AHP-RII methodology is capable of assessing delay risk effectively and efficiently. Decision makers can apply risk informed decision making to avoid unexpected construction delays of NPPs.
Journal of Korean Society of Industrial and Systems Engineering
/
v.29
no.1
/
pp.94-100
/
2006
The risk management is an organized method for identifying and measuring risk and for selecting, developing, and implementing options for the handling of risk. The risk management covers all programatic and technical factors which affect the system development performance, cost, and schedule. While technical issues are primary concern for systems engineering, the three elements(performance, cost, and schedule) must be balanced for a successful risk management process. This paper proposes the risk management process for the KSLV-I(Korea Space Launch Vehicle-I) program using computer-aided systems engineering tool, Cradle. The risk management process of KSLV-I program is similar to the general risk management process, but it has its own specific features to manage large-scale complex characteristics of KSLV-I program.
Korean Journal of Construction Engineering and Management
/
v.10
no.5
/
pp.47-56
/
2009
As contemporary society becomes information-oriented, major construction companies have recently invested in information management, but small and medium ones have not. Though the small and medium companies recognize the information management is necessary and important, they don't have an ability to possess technical expertises. The purpose of this study is to develop a Schedule Risk Control System based on blogs using IT and web technologies for construction managers in small and medium construction companies. The system makes a chance to identify risk factors and prepare for responses to settle risks happened in preconstruction phases, and enables the managers and headquarters to predict and handle schedule risks by sharing information about risks on the blogs.
본 웹사이트에 게시된 이메일 주소가 전자우편 수집 프로그램이나
그 밖의 기술적 장치를 이용하여 무단으로 수집되는 것을 거부하며,
이를 위반시 정보통신망법에 의해 형사 처벌됨을 유념하시기 바랍니다.
[게시일 2004년 10월 1일]
이용약관
제 1 장 총칙
제 1 조 (목적)
이 이용약관은 KoreaScience 홈페이지(이하 “당 사이트”)에서 제공하는 인터넷 서비스(이하 '서비스')의 가입조건 및 이용에 관한 제반 사항과 기타 필요한 사항을 구체적으로 규정함을 목적으로 합니다.
제 2 조 (용어의 정의)
① "이용자"라 함은 당 사이트에 접속하여 이 약관에 따라 당 사이트가 제공하는 서비스를 받는 회원 및 비회원을
말합니다.
② "회원"이라 함은 서비스를 이용하기 위하여 당 사이트에 개인정보를 제공하여 아이디(ID)와 비밀번호를 부여
받은 자를 말합니다.
③ "회원 아이디(ID)"라 함은 회원의 식별 및 서비스 이용을 위하여 자신이 선정한 문자 및 숫자의 조합을
말합니다.
④ "비밀번호(패스워드)"라 함은 회원이 자신의 비밀보호를 위하여 선정한 문자 및 숫자의 조합을 말합니다.
제 3 조 (이용약관의 효력 및 변경)
① 이 약관은 당 사이트에 게시하거나 기타의 방법으로 회원에게 공지함으로써 효력이 발생합니다.
② 당 사이트는 이 약관을 개정할 경우에 적용일자 및 개정사유를 명시하여 현행 약관과 함께 당 사이트의
초기화면에 그 적용일자 7일 이전부터 적용일자 전일까지 공지합니다. 다만, 회원에게 불리하게 약관내용을
변경하는 경우에는 최소한 30일 이상의 사전 유예기간을 두고 공지합니다. 이 경우 당 사이트는 개정 전
내용과 개정 후 내용을 명확하게 비교하여 이용자가 알기 쉽도록 표시합니다.
제 4 조(약관 외 준칙)
① 이 약관은 당 사이트가 제공하는 서비스에 관한 이용안내와 함께 적용됩니다.
② 이 약관에 명시되지 아니한 사항은 관계법령의 규정이 적용됩니다.
제 2 장 이용계약의 체결
제 5 조 (이용계약의 성립 등)
① 이용계약은 이용고객이 당 사이트가 정한 약관에 「동의합니다」를 선택하고, 당 사이트가 정한
온라인신청양식을 작성하여 서비스 이용을 신청한 후, 당 사이트가 이를 승낙함으로써 성립합니다.
② 제1항의 승낙은 당 사이트가 제공하는 과학기술정보검색, 맞춤정보, 서지정보 등 다른 서비스의 이용승낙을
포함합니다.
제 6 조 (회원가입)
서비스를 이용하고자 하는 고객은 당 사이트에서 정한 회원가입양식에 개인정보를 기재하여 가입을 하여야 합니다.
제 7 조 (개인정보의 보호 및 사용)
당 사이트는 관계법령이 정하는 바에 따라 회원 등록정보를 포함한 회원의 개인정보를 보호하기 위해 노력합니다. 회원 개인정보의 보호 및 사용에 대해서는 관련법령 및 당 사이트의 개인정보 보호정책이 적용됩니다.
제 8 조 (이용 신청의 승낙과 제한)
① 당 사이트는 제6조의 규정에 의한 이용신청고객에 대하여 서비스 이용을 승낙합니다.
② 당 사이트는 아래사항에 해당하는 경우에 대해서 승낙하지 아니 합니다.
- 이용계약 신청서의 내용을 허위로 기재한 경우
- 기타 규정한 제반사항을 위반하며 신청하는 경우
제 9 조 (회원 ID 부여 및 변경 등)
① 당 사이트는 이용고객에 대하여 약관에 정하는 바에 따라 자신이 선정한 회원 ID를 부여합니다.
② 회원 ID는 원칙적으로 변경이 불가하며 부득이한 사유로 인하여 변경 하고자 하는 경우에는 해당 ID를
해지하고 재가입해야 합니다.
③ 기타 회원 개인정보 관리 및 변경 등에 관한 사항은 서비스별 안내에 정하는 바에 의합니다.
제 3 장 계약 당사자의 의무
제 10 조 (KISTI의 의무)
① 당 사이트는 이용고객이 희망한 서비스 제공 개시일에 특별한 사정이 없는 한 서비스를 이용할 수 있도록
하여야 합니다.
② 당 사이트는 개인정보 보호를 위해 보안시스템을 구축하며 개인정보 보호정책을 공시하고 준수합니다.
③ 당 사이트는 회원으로부터 제기되는 의견이나 불만이 정당하다고 객관적으로 인정될 경우에는 적절한 절차를
거쳐 즉시 처리하여야 합니다. 다만, 즉시 처리가 곤란한 경우는 회원에게 그 사유와 처리일정을 통보하여야
합니다.
제 11 조 (회원의 의무)
① 이용자는 회원가입 신청 또는 회원정보 변경 시 실명으로 모든 사항을 사실에 근거하여 작성하여야 하며,
허위 또는 타인의 정보를 등록할 경우 일체의 권리를 주장할 수 없습니다.
② 당 사이트가 관계법령 및 개인정보 보호정책에 의거하여 그 책임을 지는 경우를 제외하고 회원에게 부여된
ID의 비밀번호 관리소홀, 부정사용에 의하여 발생하는 모든 결과에 대한 책임은 회원에게 있습니다.
③ 회원은 당 사이트 및 제 3자의 지적 재산권을 침해해서는 안 됩니다.
제 4 장 서비스의 이용
제 12 조 (서비스 이용 시간)
① 서비스 이용은 당 사이트의 업무상 또는 기술상 특별한 지장이 없는 한 연중무휴, 1일 24시간 운영을
원칙으로 합니다. 단, 당 사이트는 시스템 정기점검, 증설 및 교체를 위해 당 사이트가 정한 날이나 시간에
서비스를 일시 중단할 수 있으며, 예정되어 있는 작업으로 인한 서비스 일시중단은 당 사이트 홈페이지를
통해 사전에 공지합니다.
② 당 사이트는 서비스를 특정범위로 분할하여 각 범위별로 이용가능시간을 별도로 지정할 수 있습니다. 다만
이 경우 그 내용을 공지합니다.
제 13 조 (홈페이지 저작권)
① NDSL에서 제공하는 모든 저작물의 저작권은 원저작자에게 있으며, KISTI는 복제/배포/전송권을 확보하고
있습니다.
② NDSL에서 제공하는 콘텐츠를 상업적 및 기타 영리목적으로 복제/배포/전송할 경우 사전에 KISTI의 허락을
받아야 합니다.
③ NDSL에서 제공하는 콘텐츠를 보도, 비평, 교육, 연구 등을 위하여 정당한 범위 안에서 공정한 관행에
합치되게 인용할 수 있습니다.
④ NDSL에서 제공하는 콘텐츠를 무단 복제, 전송, 배포 기타 저작권법에 위반되는 방법으로 이용할 경우
저작권법 제136조에 따라 5년 이하의 징역 또는 5천만 원 이하의 벌금에 처해질 수 있습니다.
제 14 조 (유료서비스)
① 당 사이트 및 협력기관이 정한 유료서비스(원문복사 등)는 별도로 정해진 바에 따르며, 변경사항은 시행 전에
당 사이트 홈페이지를 통하여 회원에게 공지합니다.
② 유료서비스를 이용하려는 회원은 정해진 요금체계에 따라 요금을 납부해야 합니다.
제 5 장 계약 해지 및 이용 제한
제 15 조 (계약 해지)
회원이 이용계약을 해지하고자 하는 때에는 [가입해지] 메뉴를 이용해 직접 해지해야 합니다.
제 16 조 (서비스 이용제한)
① 당 사이트는 회원이 서비스 이용내용에 있어서 본 약관 제 11조 내용을 위반하거나, 다음 각 호에 해당하는
경우 서비스 이용을 제한할 수 있습니다.
- 2년 이상 서비스를 이용한 적이 없는 경우
- 기타 정상적인 서비스 운영에 방해가 될 경우
② 상기 이용제한 규정에 따라 서비스를 이용하는 회원에게 서비스 이용에 대하여 별도 공지 없이 서비스 이용의
일시정지, 이용계약 해지 할 수 있습니다.
제 17 조 (전자우편주소 수집 금지)
회원은 전자우편주소 추출기 등을 이용하여 전자우편주소를 수집 또는 제3자에게 제공할 수 없습니다.
제 6 장 손해배상 및 기타사항
제 18 조 (손해배상)
당 사이트는 무료로 제공되는 서비스와 관련하여 회원에게 어떠한 손해가 발생하더라도 당 사이트가 고의 또는 과실로 인한 손해발생을 제외하고는 이에 대하여 책임을 부담하지 아니합니다.
제 19 조 (관할 법원)
서비스 이용으로 발생한 분쟁에 대해 소송이 제기되는 경우 민사 소송법상의 관할 법원에 제기합니다.
[부 칙]
1. (시행일) 이 약관은 2016년 9월 5일부터 적용되며, 종전 약관은 본 약관으로 대체되며, 개정된 약관의 적용일 이전 가입자도 개정된 약관의 적용을 받습니다.