• Title/Summary/Keyword: ROCK1

Search Result 3,394, Processing Time 0.029 seconds

Comparative Study on the Stability Analysis Methods for Underground Pumped Powerhouse Caverns in Korea (국내 양수발전소 지하공동 안정성 해석방법의 비교)

  • 임한욱;김치환
    • Tunnel and Underground Space
    • /
    • v.12 no.4
    • /
    • pp.248-258
    • /
    • 2002
  • The sixth underground pumped powerhouse cavern is now under construction in Korea. For the stability analysis for the caverns of the five underground powerhouses, finite element method was used. For the analysis, in-situ rock stress were measured by overcoring method. The stress measurement showed that initial horizontal to vertical stress ratio was 1.07-1.32 in low powerhouse sites. Rock mass strength and elasticity were assumed from rock core properties through engineering processes. So the ratio of input elasticity fur the analysis were about 0.16-0.55 to rock core elasticity. In most of the analysis, elasto-plastic condition with Mohr-Coulomb failure criteria were applied. But in one case, viscoelastic condition was applied, too. The input cohesion and internal friction angle were approximately 0.12-0.22, 0.6-0.87 to rock core strength parameters, respectively.

Stability Analysis of Rock Slope (암반절취사면의 안정해석)

  • Cho, Seong Seop;Kim, Yong Seong;Chee, In Taeg;Lee, Dal Won
    • Korean Journal of Agricultural Science
    • /
    • v.23 no.1
    • /
    • pp.1-12
    • /
    • 1996
  • To design the safe and rational rock slope, several rock slopes of roads in Kang-won area were analyzed, and the following results were obtained ; 1. The results were analyzed by stereographic projection at the rock slope that the joint was developed. All of the sloped which were designed by standard slope of rock was not considered that the joints were unstable. 2. The relation of rainfall and slope failure, as well as the danger of failure, was very high when the maximum hourly rainfall was larger than 20mm and when there was a 2-day cumulative rainfall that was larger than 200mm. 3. In the design of rock slope, operated by the stereographic projection considering discontinuity. If turn out unstable, it should be analyzed carefully using the limit equilibrium method. 4. In the design of rock slope, it is desirable to consider the discontinuity of rock(joint, bedding, fault).

  • PDF

Effect of utilizing pressurized ring beam system in modern rock TBM: I. Numerical study (현대식 Rock TBM에서 가압형 링빔의 효과 연구: I. 수치해석적 연구)

  • Kwak, Yun-Suk;Kang, Gi-Don;Kim, Do-Hoon;Lee, In-Mo
    • Journal of Korean Tunnelling and Underground Space Association
    • /
    • v.14 no.1
    • /
    • pp.55-77
    • /
    • 2012
  • A Modern Rock TBM is a tunnel excavation method combining the conventional tunnelling method with the mechanized tunnelling method. It is a hybrid system that excavates a tunnel with TBM and supports the ground by ring beam, wire mesh, rock bolt, shotcrete, i.e., conventional tunnelling method. In the Modern Rock TBM, a ring beam is similar to a steel rib in NATM in the way that uses H-beam. But using a ring beam is more effective than a steel rib because it is installed in a closed-circle. Therefore, improving the performance of the ring beam is a key factor for achieving tunnel stability. In this respect, this study introduces a pressurized ring beam that might be functioning more effectively by confining convergence during tunnel excavation. In order to verify the effect of the pressurized ring beam, a three-dimensional numerical analysis was conducted. The numerical analysis confirms an increase in the minimum principal stress and reduction in the plastic strain that triggers excessive displacement. The analysis result also indicates a decrease in the relative displacement occurring after installing the ring beam, and expansion in spacing between the ring beams.

A Study on Setup for Preliminary Decision Criterion of Continuum Rock Mass Slope with Fair to Good Rating (양호한 연속체 암반사면의 예비 판정기준 설정 연구)

  • Kim, Hyung-Min;Lee, Su-gon;Lee, Byok-Kyu;Woo, Jae-Gyung
    • The Journal of Engineering Geology
    • /
    • v.29 no.2
    • /
    • pp.85-97
    • /
    • 2019
  • It can be observed that steep slopes ($65^{\circ}$ to $80^{\circ}$) consist of rock masses were kept stable for a long time. In rock-mass slopes with similar ground condition, steeper slopes than 1 : 0.5 ($63^{\circ}$) may be applied if the discontinuities of rock-mass slope are distributed in a direction favorable to the stability of the slope. In making a decision the angle of the slope, if the preliminary rock mass conditions applicable to steep slope are quantitatively setup, they may be used as guidance in design practice. In this study, the above rock mass was defined as a good continuum rock mass and the quantitative setup criterion range was proposed using RMR, SMR and GSI classifications for the purpose of providing engineering standard for good continuum rock mass conditions. The methods of study are as follows. The stable slope at steep slopes ($65^{\circ}$ to $80^{\circ}$) for each rock type was selected as the study area, and RMR, SMR and GSI were classified to reflect the face mapping results. The results were reviewed by applying the calculated shear strength to the stable analysis of the current state of rock mass slope using the Hoek-Brown failure criterion. It is intended to verify the validity of the preliminary criterion as a rock mass condition that remains stable on a steep slope. Based on the analysis and review by the above research method, it was analyzed that a good continuum rock mass slope can be set to Basic RMR ${\geq}50$ (45 in sedimentary rock), GSI and SMR ${\geq}45$. The safety factor of the LEM is between Fs = 14.08 and 67.50 (average 32.9), and the displacement of the FEM is 0.13 to 0.64 mm (average 0.27 mm). This can be seen as a result of quantitative representation and verification of the stability of a good continuum rock mass slope that has been maintained stable for a long period of time with steep slopes ($65^{\circ}$ to $80^{\circ}$). The setup guideline for a good continuum rock mass slope will be able to establish a more detailed setup standard when the data are accumulated, and it is also a further study project. If stable even on steep slopes of 1 : 0.1 to 0.3, the upper limit of steep slopes is 1 : 0.3 with reference to the overseas design standards and report, thus giving the benefit of ensuring economic and eco-friendlyness. Also, the development of excavation technology and plantation technology and various eco-friendly slope design techniques will help overcome psychological anxiety and rapid weathering and relaxation due to steep slope construction.

On the Evaluation of Construction Standards Based on Seismic Velocities Obtained In-Situ and through Laboratory Rock Tests (현장 및 실내 측정 탄성파 속도에 근거한 암반평가 기준에 대한 고찰)

  • Lee, Kang Nyeong;Park, Yeon Jun
    • Tunnel and Underground Space
    • /
    • v.27 no.4
    • /
    • pp.230-242
    • /
    • 2017
  • Seismic velocities measured from in-situ tests (n=177) and through rock core samples (n=1,035) are reviewed in light of construction standards, widely used standards as a first-hand approximation of rock classification solely based on seismic velocities. In-situ down hole tests and refraction survey for soft rocks showed seismic velocities of 1,400~2,900 m/s which is faster than those specified in construction standards. For moderate~ hard rocks, in-situ down hole tests and refraction survey showed 2,300~3,800 m/s which roughly corresponds with the range specified in the construction standards. A similar trend is also observed for seismic velocities measured from rock core samples. The observed differences between construction standards and seismic velocities can be explained in two ways. If construction standards are correct the observed differences may be explained with seismic velocities affected by underlying fast velocities and also possibly with selection of intact cores for velocity measurement. Alternatively, construction standards may have intrinsic problems, namely artificial discrete boundaries between soft rocks and moderate rocks, application of foreign standards without consideration of geologic setting and lack of independent verification steps. Therefore, we suggest a carefully designed verification studies from a test site. We also suggest that care must be exercised when applying construction standards for the interpretation and accessment of rock mass properties.

Development of Hydraulic Rock Splitting Technique for Rock Excavation (암반 굴착을 위한 수압암반절개 기술 개발)

  • Park, Jongoh;Lee, Dal-Heui
    • The Journal of Engineering Geology
    • /
    • v.26 no.3
    • /
    • pp.353-360
    • /
    • 2016
  • Tests of hydraulic rock splitting were conducted using double packer at the 1, 2 free surface in the limestone mining and granodiorite Suksan area, respectively. The method of hydraulic rock splitting was applying hydraulic power in the interval layer using double packer. As a result of tests, a crack occurred. At about 6.5 MPa and 13 MPa, a crack occurred in 2 free surface. Any crack did not occur in the 1 free surface. Rather, used 1 double packer was broken in the 1 free surface. Also, it was confirmed that the water pressure of the interval increased through the existing crack and the new crack in the test areas.

Control of Blast Vibration, Air Blast, and Fly Rock in Rock Excavation (암반굴착에 의한 발파진동, 소음 및 비석의 조절)

  • Ryu, Chang-Ha
    • Tunnel and Underground Space
    • /
    • v.2 no.1
    • /
    • pp.102-115
    • /
    • 1992
  • Blasting operations associated with rock excavation work may have an environmental impact in nearby structures or human beings. With the increase of construction work in urban areas, vibration problems and complaints have also increased. In order to determine the optimum design parameters for safe blast, it is essential to understand blast mechanism, design variables involved in blast-induced damage, and their effects on the blasting results. This paper deals with the characteristics of ground vibrations, air blast and fly rock caused by blast, including the general method of establishing the vibration predictors, and damage criteria suggested by various investigators. The results of field measurements from open pit mine and tunnel construction work are discussed. Basic concepts of how to design blast parameters to control the generation of ground vibrations, air blast and fly rock are presented.

  • PDF

A Study on the Evaluation of Necessity for the Support in Case of Excavartion of the Transport Drift at Danyang Site (단양지역의 운방갱도 굴착시 갱도 지보의 필요성 판정에 관한 연구)

  • 이종욱;조만섭;김일중;김영석
    • Tunnel and Underground Space
    • /
    • v.3 no.1
    • /
    • pp.54-62
    • /
    • 1993
  • In order to evaluate the necessity for the support during the excavation of the transport drift and use the data for design applications, laboratory testings of mechanical properties of rock samples and engineering rock mass classifications on this study site were performed. The values of RMR and Q-system are 68 and 11.8, respectively. Since these results were evaluated as good, this rock mass were determined to be unsupported. Full face excavation method was determined to be suitable for excavating this drift. In case of excavation, smooth blasting techniques must be carried out at the wall rock and the crown. However, considering the blast vibration etc. that have an effect on the surrounding rock mass, approximately less than 9kg of explosive charges per blast should be maintained.

  • PDF