• 제목/요약/키워드: L.W grouting

검색결과 7건 처리시간 0.02초

한강 단층대를 통과하는 하저터널의 안정성 확보에 관한 연구 (Stability Evaluation for a riverbed tunnel in the Han River at the Fault Zone Crossing)

  • 우종태;이송
    • 한국구조물진단유지관리공학회 논문집
    • /
    • 제5권3호
    • /
    • pp.225-231
    • /
    • 2001
  • When building tunnels beneath riverbeds where very large quantities of groundwater inflow exist, added to high water head the soil supporting conditions are very poor because the soil consists of sand and silt, etc. It is necessary to have grouting and mini pipe roof installed in the region for ground reinforcement to decrease permeability. According to this result of horizontal boring and laboratory soil testing, ground reinforcement was achieved by L.W grouting for range of 3.0 times the tunnel radius, to increase stability of the tunnel we used the ling-cut method, 0.8m for one step excavation, shotcrete with 25cm thick, steel lib with H-$125{\times}125$. and a temporary shotcrete invert 20cm thick was installed to prevent deformation of the tunnel.

  • PDF

B.G.I 지반보강 공법에 관한 연구 (A Study on the Ground Reinforcement Method of B.G.I)

  • 유남재;서승오;김동건
    • 산업기술연구
    • /
    • 제29권B호
    • /
    • pp.73-80
    • /
    • 2009
  • This paper is to investigate effect of B.G.I (Best Grouting Innovation) method on reinforcing ground. In this thesis, extensive literature review was performed to summarize theoretical backgrounds of grouting and to compare the applicability of different grouting methods. Unconfined compression test with specimen prepared by injecting different grouts of B.G.I, S.G.R and L.W methods and by changing the curing time were carried out to figure out characteristics of initial unconfined compression strength mobilized in the early stage. As results of test, the compression strength increases with curing times and specimen prepared with grouts of B.G.I method show greater values than others. On the other hands, the measured values of pH are in the range of 7-10 during tests. In field, preliminary construction to main construction at several sites were performed to confirm the effect of reinforcing the ground by application of B.G.I method. From the results of permeability test in field, SPT test and phenol reaction test, it was found that N values after grouting are greater than those before grouting and values of permeability in grouted ground is reduced significantly.

  • PDF

친환경 비알칼리성 실리카졸 지반주입재의 개발과 특성에 관한 연구 (A Study on the Development and Characteristics of Eco-friendly None Alkaline Silica Sol Grouting Material)

  • 강현상;정대석
    • 한국재난정보학회 논문집
    • /
    • 제19권4호
    • /
    • pp.747-756
    • /
    • 2023
  • 연구목적: 본 연구에서는 기존 주입공법의 문제점을 개선하기 위한 친환경적인 주입재를 개발하고 시험을 통해 현장 적용성을 확인하기 위한 연구를 수행하였다. 연구방법: 친환경 주입재와 기존 주입재(L.W, S.G.R)의 호모겔 공시체를 각각 제작하고, 실내시험(일축압축강도, 투수계수, 수축성, 내화학성, 용출성, 어독성, 폐기물공정)을 실시하여 물리화학적 및 공학적 특성을 비교·검토하였다. 연구결과: 실내시험 결과 친환경 주입재가 기존 주입재에 비해 모든면에서 우수하였으며 주입재료로서 실제 현장에서 시공적합성을 실험하고 지반개량 효과를 확인할 수 있었다. 결론: 본 연구에서 사용된 주입재는 강도증가 및 투수성 감소 등의 기본적인 물성을 만족하면서 친환경적인 특성을 가지고 있어 지반의 조건과 적용에 관계없이 범용적으로 사용이 가능한 재료로 판단되었다.

제주도의 오염 방지 시공이 부실한 지하수 관정에 대한 구간 차폐 공법의 적용과 평가 (Application and Assesment of Regrouting Method for Improperly Constructed Wells in Jeju Island)

  • 김미진;강봉래;조희남;최성욱;양원석;박원배
    • 한국지하수토양환경학회지:지하수토양환경
    • /
    • 제25권3호
    • /
    • pp.43-51
    • /
    • 2020
  • About 90% of groundwater wells in Jeju Island are reported to be under the threat of contamination by infiltration of the surface pollutants. Most of those wells have improperly grouted annulus which is an empty space between the well and the inner casing. As a remedy to this problem, some of the wells were re-grouted by filling the annulus with cement without lifting an inner casing. In order to evaluate whether this method is appropriate for the geological structure of Jeju Island, two wells (W1 and W2) were selected and this method was applied. The water holding capacity did not decrease while the nitrate levels decreased from 16.8 and 20.2 to 6.8 and 13.8 mg/L in W1 and W2, respectively. The higher nitrate level in W2 is deemed to be influenced by the livestock farms located in the upper area of the well. In addition, transmissivity of the vedose zone was higher in W2 than W1, potentially facilitating the transport of nitrate to the groundwater. The overall result of this study suggests re-grouting of wells for the purpose of protecting water quality of goundwater should take into account geological structure of vadose zone as well as appropriate source control of the contaminants.

금속 광미 처리를 위한 포틀랜드 시멘트와 MSG(micro silica grouting) 시멘트 고형화 실증 실험 연구 (Study of Solidification by Using Portland and MSG(micro silica grouting) Cements for Metal Mine Tailing Treatment)

  • 전지혜;김인수;이민희;장윤영
    • 자원환경지질
    • /
    • 제39권6호
    • /
    • pp.699-710
    • /
    • 2006
  • 폐금속광산 주변에 산재한 광미를 고화제를 이용하여 영구 매립하는 고형화 처리 공정의 타당성을 평가하기 위하여, 경상북도에 위치한 지시, 대량, 어전 금속 폐광산 주변 광미를 대상으로 3 종류의 시멘트 고화제를 이용하여 고화체를 양생하고, 고화체의 압축강도 및 중금속 용출을 측정하여 고화체의 고형화 효율을 규명하였다. 포틀랜드 시멘트와 MSG(micro silica grouting) 계열 시멘트를 고화제로 사용하여 광미와 1:1(w.t.) 혼합하여 양생한 고화체의 압축강도 실험 결과 양생 기간이 14일 인 모든 고화체의 일축압축강도는$1{\sim}2kgf/mm^2$를 나타내어, 현행 폐기물관리법(20 조 관련)에서 규정하고 있는 차단형 매립시설의 내부막의 압축강도 기준인 $0.21kgf/mm^2$ 보다 높은 것으로 나타났다. 광미와 혼합하여 성형한 고화체와 순수한 광미를 대상으로 토양공정시험법에서 제시한 약산 추출법으로 중금속 용출을 실시하여 광미와 광미로 성형한 고화체의 중금속 용출 농도 차이를 비교하였다. 고화제와 광미를 1:1(w.t.)로 혼합하여 성형한 고화체의 경우 As와 Pb의 용출농도가 약 $3{\sim}5$배 감소하는 것으로 나타나 약산 추출법에 의한 중금속용출은 고화체 성형 시 뚜렷한 감소 효과가 있었다. 다양한 pH를 갖는 수용액을 이용하여, 광미와 고화제를 혼합하여 양생한 고화체의 시간에 따른 수용액으로의 중금속 용출 농도를 측정하였다. 수용액의 pH가 1과 13인 강산/강염기 용액에서 일부 중금속의 용출 농도가 지하수 생활응수 기준치를 초과하였으나, pH가 $3{\sim}11$인 경우에는 중금속 용출이 급격히 감소하여 모두 지하수 생활용수 기준치 이하를 나타내었다. pH가 1과 13인 수용액의 경우에도 고화체와 반응하는 시간이 증가할수록 고화체의 완충(buffering) 효과에 의해 수용액의 pH가 변화하여 $9{\sim}10$을 나타내었다. 이러한 결과는, 현장에서 pH가 1과 13인 수계와 광미로 형성된 고화체가 접촉한다 하여도, 고화체의 완충 효과에 의해 시간이 지남에 따라 접촉수의 pH가 변하여 고화체로부터 지속적인 다량의 중금속 용출이 제한될 수 있음을 의미한다.

NATM터널 저토피 구간에서의 막장붕락 사례연구 (Case Study on the Tunnel Collapse at the Shallow Depth)

  • 백기현;노종륜;김용일;조상국;황낙연
    • 터널과지하공간
    • /
    • 제15권2호
    • /
    • pp.102-110
    • /
    • 2005
  • 익산-장수 고속도로 ○ ○ 공구에 위치한 ○ ○ 터널 저토피 계곡구간에서 시공 중 붕락이 발생하였다. 본 구간은 TSP 탐사 및 시추조사 등을 통해 불연속면이 예측되었으나, 굴착 중 실제 암질이 비교적 양호하고 막장이 안정되어 암반 등급을 상향 변경하여 시공하였다. 그러나 굴착 중 발파와 동시에 붕락이 발생하였으며, 터널 막장 상부 8 m 부분의 붕락과 함께 지상 구간의 침하에 따른 계곡수 및 지하수 유입으로 진행되었다. 붕락구간 복구를 위해 붕락원인 분석, 보강공법의 선정 및 3차원 터널 안정성 해석을 실시하였고, 막장 상부 공동부는 팽창성 경량 콘크리트로 충진 후, 강관다단 그라우팅 공법으로 안정화시키고, 터널 상부 지반 침하부에서는 계곡수로 이설 후, 시멘트밀크 그라우팅 공법에 혼용된 약액 그라우팅 공법으로 지반보강 및 차수를 실시하였다.

풍화대를 통과하는 도로 NATM 터널의 천단부 함몰에 대한 연구 (Analysis on Surface Collapse of the Road NATM Tunnel through the Weathered Rock)

  • 신은철;유재성
    • 한국지반신소재학회논문집
    • /
    • 제15권2호
    • /
    • pp.55-64
    • /
    • 2016
  • 산악지 풍화대를 관통하는 도로 NATM터널에서 록볼트+숏크리트 타설과 강관다단 그라우팅 보강작업 진행 중, 터널 천단부붕락(토피고 25m) 및 지표면 함몰($V=12m{\times}14m{\times}$높이 5m = $840m^3$)과 터널 내 과다한 변위가 발생하였다. 원활한 후속 공사를 위해 각종 조사 자료와 시험, 분석을 통해 함몰(땅꺼짐) 원인을 분석하고 수치해석을 통하여 적절한 갱내외 보강범위를 다양하게 검토한 후 대책공법을 제시하였다. 수치해석 결과 터널 종횡방향 0.5D, 터널 상단 1.0D에서 보강효율이 가장 좋은 것으로 분석되었다. 터널 지상부는 시멘트밀크그라우팅으로, 터널 내부는 대구경강관다단 3열 중첩으로 보강하였다. 라이닝에 철근을 보강하고 잔여 터널구간에 선진수평보링을 적용하여 사전에 막장 전방상태를 파악하고 필요시 적절한 보강을 하도록 하였다.