• Title/Summary/Keyword: Incremental Launching Method(ILM)

Search Result 16, Processing Time 0.024 seconds

Analysis of Two-Span Structures Constructed by Incremental Launching Method (ILM 공법에 의해 시공된 2경간 구조물의 해석)

  • Kim, Sung Hoon;Kim, Bu Kyu;Choi, Jun Hyeok
    • Journal of Korean Society of Steel Construction
    • /
    • v.28 no.1
    • /
    • pp.35-42
    • /
    • 2016
  • This paper presents the structural analysis of two-span structures constructed by incremental launching method to traverse the existing facilities. The structure with a relatively short launching span can not be secure the structural stability caused by excessive deflection and overturning prior to reaching the maximum strength, because the length of the other span is different or the rear structure is not continuous. In order to estimate the stability of the construction stages of deflection and the overturning, the structural analysis was carried out. The parameters of the analysis is launching span ratio of the launching nose and the upper structure, weight ratio and so on. From the analysis result, the effects of parameters were investigated and a deflection formula of the launching nose and the condition of the overturning of structure were proposed.

Development of the Approximate Cost Estimating Model Using Statistical Inference for PSC Box Girder Bridge Constructed by the Incremental Launching Method (통계적 기법을 활용한 ILM압출공법 교량 상부공사 개략공사비 산정모델 개발 연구)

  • Kim, Sang-Bum;Cho, Ji-Hoon
    • KSCE Journal of Civil and Environmental Engineering Research
    • /
    • v.33 no.2
    • /
    • pp.781-790
    • /
    • 2013
  • This research focuses on development of the conceptual cost estimation models for I.L.M box girder bridge. The current conceptual cost estimation for public construction projects is dependent on governmental average unit price references which has been regarded as inaccurate and unreliable by many experts. Therefore, there have been strong demands for developing a better way of conceptual cost estimating methods. This research has proposed three different conceptual cost estimating method for a P.S.C. girder bridge built with the I.L.M method. Model (I) attempts to seek the proper breakdown of standard works that are accountable for more than 95 percentage in total cost and calculates the amount of standard work's materials from the standard section and volume of I.L.M box girder bridge. Model (II) utilizes a correlation analysis (coefficient over 0.6 or more) between breakdown of standard works and input data that would be considered available information in preliminary design phase. Model(III) obtains conceptual estimating through multiple-regression analysis between the breakdown of standard works and all of input data related to them. In order to validate the clustering of coverage in the preliminary design phase, the variation of I.L.M cost coverage from multiple-regression analysis[model(III)] has been investigated which result in between -3.76% and 11.79%, comparing with AACE(Association for the Advancement of Cost Engineering) which informs its variation between -5% and +15% in the design phase. The model proposed from this research are envisioned to be improved to a great distinct if reliable cost date for P.S.C. girder bridges can be continually collected with reasonable accuracies.

The Continuously Underwater Tunnelling Methods by Incremental launching Methods (연속압출공법(ILM)을 이용한 수저(水底)터널공법에 관한 연구)

  • Jung, Byung-Ryul;Ryu, Dong-Hun;Kim, Joon-Mo
    • Proceedings of the KSR Conference
    • /
    • 2009.05a
    • /
    • pp.28-41
    • /
    • 2009
  • We know the several construction methods for underwater tunnel, but properly submerged concrete box type tunnel was mostly good structure stability and mostly shot length of tunnels. Submerged box type tunnel was buildup the unit segments in dry dock or ship yard by 10 to 20meters. The submerged box was composed with segments was join each together. It was installing the gate and waterproofing the coupling the front hull of a box. The complete submerged box rise up to the surface water, tow in the submerged box by tugboat, going to the destination of tunnel construction site. Beforehand dredge up soil at the bottom of a underwater, sinking the submerged box, connection together complete submerged box in underwater. The research and development ILM tunneling method is receiving careful study. Biggest weakness in submerged concrete box type tunnel was pressure waterproofing, box to box connecting, complete submerged boxes navigation and installation, after operation the submerged tunnel and management concrete box structure. It was positive evidence in submerged concrete box type tunnel. We make a practical application of the principle "the ILM tunneling method in underwater construction methods."

  • PDF

Development of an Activity-Based Conceptual Cost Estimating Model for P.S.CBox Girder Bridge (대표공종 기반의 P.S.C 박스 거더교 개략공사비 산정모델 개발 -상부공사 중심으로-)

  • Cho, Ji-Hoon;Kim, Sang-Bum
    • Proceedings of the Korean Institute Of Construction Engineering and Management
    • /
    • 2008.11a
    • /
    • pp.197-201
    • /
    • 2008
  • Conceptual cost estimates for domestic highway projects have generally been conducted using governmental unit-price references. Inaccuracies in governmental unit-price data has repeatedly addressed in the Korean construction industry which often lead to poor decision making and cost management practices. Thus, needs for developing a better way of conceptual cost estimating has been widely recognized. This research is considered as the first step in developing such model using real-world cost data based on actual construction activities. The data analyzed in this paper includes 41 P.S.C (Prestressed Concrete) Box bridges which broke into 4 categories based on construction methods such as I.L.M(Incremental Launching Method), M.S.S(Movable Scaffolding System), F.S.M(Full Staging Method), and F.C.M(Free Cantilever Method). Actual design documents; including actual cost estimating documents, drawings and specifications were carefully reviewed to effectively break down cost structures for PSC girder bridges. Among more than 40 cost categories for each P.S.C girder bridge type, 7 of them were identified which accounted for more than 95% of total construction cost (ILM: 99.47%, MSS: 99.22%, FSM: 98.18%, and FCM: 98.12%). In order to validate the clustering of cost categories, the variation of each cost category has been investigated which resulted in between -1.16 % and 0.59%.

  • PDF

Design and Safety Control in Construction Stage of Prestressed Concrete Box Girder Bridge with Corrugated Steel Web (파형강판 PSC 박스거더 교량의 설계 및 시공중 안전관리)

  • Kim, Kwang-Soo
    • Journal of the Korean Society of Safety
    • /
    • v.23 no.2
    • /
    • pp.87-97
    • /
    • 2008
  • The Ilsun Bridge is the world's longest box girder bridge(801m) with corrugated steel webs and has the widest width($21.2{\sim}30.9m$: tri-cellular cross section) among these kinds of composite girder bridges. It has fourteen spans(50m, 10 at 60m, 50m, 2 at 50.5m) where twelve spans are erected by the incremental launching method and two spans by full staging method. Special topics related to the structural safety of prestressed concrete box girder bridge with corrugated steel web in construction stage and service were reviewed. Investigations focus on the span-to-depth ratio, shear stress of corrugated steel webs and optimization of tile length of steel launching nose. The span-to-depth ratio of Ilsun bridge has been found to be well-planned while the corrugated steel web has been designed highly conservative and it has been observed that the conventional nose-deck interaction equation do not fit well with corrugated steel web bridges. As a result, detailed construction stage analysis was performed to check the stress levels and the safety of preceding design conditions. Finally, from the design review of Ilsun bridge, this study suggests optimal design issues which should be of interest in designing a prestressed concrete box girder bridge with corrugated steel webs.

Stress Distribution on Construction Joint of Prestressed Concrete bridge Members with Tendon Couplers (텐던커플러를 사용한 프리스트레스트 콘크리트 교량부재의 이음부 응력분포 특성)

  • 오병환;채성태;김병석;이만섭
    • Journal of the Korea Concrete Institute
    • /
    • v.13 no.1
    • /
    • pp.1-8
    • /
    • 2001
  • Recently, prestressed concrete(PSC) bridge structures with many repetitive spans have been widely constructed using the segmental construction method in many countries. In these segmentally constructed PSC bridges, there exist many construction joints which is required coupling of tendons or overlapping of tendons to introduce continuous prestress through several spans of bridges. The purpose of this paper is to investigate in detail the complicated stress distributions around the tendon coupled joints in prestressed concrete girders. To this end, a comprehensive experimental program has been set up and a series of specimens have been tested to identify the effects of tendon coupling. The present study indicates that the longitudinal and transverse stress distributions of PSC girders with tendon couplers are quite different from those of PSC girders without tendon couplers. It is seen that the longitudinal compressive stresses introduced by prestressing are greatly reduced around coupled joints according to tendon coupling ratios. The large reduction of compressive stresses around the coupled joints may cause deleterious cracking problems in PSC girder bridges due to tensile stresses arising from live loads, shrinkage and temperature effects. The analysis results by finite element method correlate very well with test results observed complex strain distributions of tendon coupled members. It is expected that the results of this paper will provide a good basis for realistic design guideline around tendon coupled joints in PSC girder bridges.