Development of the Approximate Cost Estimating Model Using Statistical Inference for PSC Box Girder Bridge Constructed by the Incremental Launching Method  

Kim, Sang-Bum (Dongguk University, Civil and Environmental Engineering)
Cho, Ji-Hoon (Dongguk University, Civil and Environmental Engineering)
Publication Information
KSCE Journal of Civil and Environmental Engineering Research / v.33, no.2, 2013 , pp. 781-790 More about this Journal
Abstract
This research focuses on development of the conceptual cost estimation models for I.L.M box girder bridge. The current conceptual cost estimation for public construction projects is dependent on governmental average unit price references which has been regarded as inaccurate and unreliable by many experts. Therefore, there have been strong demands for developing a better way of conceptual cost estimating methods. This research has proposed three different conceptual cost estimating method for a P.S.C. girder bridge built with the I.L.M method. Model (I) attempts to seek the proper breakdown of standard works that are accountable for more than 95 percentage in total cost and calculates the amount of standard work's materials from the standard section and volume of I.L.M box girder bridge. Model (II) utilizes a correlation analysis (coefficient over 0.6 or more) between breakdown of standard works and input data that would be considered available information in preliminary design phase. Model(III) obtains conceptual estimating through multiple-regression analysis between the breakdown of standard works and all of input data related to them. In order to validate the clustering of coverage in the preliminary design phase, the variation of I.L.M cost coverage from multiple-regression analysis[model(III)] has been investigated which result in between -3.76% and 11.79%, comparing with AACE(Association for the Advancement of Cost Engineering) which informs its variation between -5% and +15% in the design phase. The model proposed from this research are envisioned to be improved to a great distinct if reliable cost date for P.S.C. girder bridges can be continually collected with reasonable accuracies.
Keywords
Cost Estimation Model; Incremental Launching Method(ILM); Breakdown of Standard Work; Correlation Analysis; Multiple-Regression Analysis;
Citations & Related Records
Times Cited By KSCI : 4  (Citation Analysis)
연도 인용수 순위
1 KICT(2011), "Development of Cost Estimating Model; Bridge and Tunnel," Research Report.
2 Bruce L. Bowerman et al.(2004), "Business Statistics".
3 MOCT. (2007a). "Guideline for investment evaluation," Ministry of Construction and Transportation (MOCT), Seoul (in Korean).
4 MOCT. (2007b). "Guide for road construction," Ministry of Construction and Transportation (MOCT), Seoul (in Korean).
5 KDI. (2004). "Guideline for preliminary feasibility study; Road and Railway-Ver. 4," Korea Development Institute, Seoul (in Korean).
6 Park, J. H. and Lee, T. S. (2003). "Methodology for a cost estimating on the project of a composite facility." Journal of the Korean Society of Civil Engineering," KSCE, Vol. 23, No. 1-D, pp. 69-78.   과학기술학회마을
7 Lee, Y. S. (2003). "Development of construction cost model through the analysis of critical work items." Journal of Construction Management," KICEM, Vol. 4, No. 4, pp. 212-219.   과학기술학회마을
8 Trost, S. M. and Oberlender, G. D. (2003). "Predicting accuracy of early cost estimates using factor analysis and multivariate regression," Journal of Construction Engineering and Management, ASCE, Vol. 129, No. 2, pp. 198-204.   DOI   ScienceOn
9 Kyong Ju Kim, Kyoungmin Kim, and Chan Sung Kang(2009) "Approximate Cost Estimating Model for PSC Beam Bridge Based on Quantity of Standard Work," Journal of Civil Engineering, Korean Society of Civil Engineers, 13(6), 2009. 11. pp. 377-388 (in Korean).   과학기술학회마을   DOI   ScienceOn
10 Kyong Ju Kim, Kyoungmin Kim(2010), "Preliminary Cost Estimation Model Using Case-Based Reasoning and Genetic Algorithms," Journal of Computing in Civil Engineering, American Society of Civil Engineers, 24(6), 2010. 11. pp. 499-505.   DOI   ScienceOn
11 Kang, C.S, Lim W.S., Kim K.M and Kim K.J(2007), "Approximate Estimating Model for PSC BEAM Bridge Using Influence Factors," KICEM (2007-11).
12 Kang, C.S, Lee G.H, Kim K.M and Kim K.J.(2008), "Approximate Estimating Model Using the Case Based Reasoning," KICEM (2008-11).
13 Park, J. H. and Lee, T. S. (2002). "Development of the cost analysis format for road construction project." Journal of Civil Engineering," KSCE, Vol. 22, No. 2-D, pp. 259-269.   과학기술학회마을
14 Hong T.H.(2008), "Cost prediction model of Public Multi-housing Projects in Schematic Design Phase," KICEM, Vol. 9, No. 3 pp. 65-74.
15 Ministry of Land. Transport and Marine Affairs(2004), "Volume reduction through the advancement of PSC box girder bridge design".
16 Park M.S.(2008), "Method of Quantity Data Analysis for Building Construction Cost Estimation : Focusing on Finish Work of Public Apartment Project," KICEM, Vol. 9, No. 6, pp. 235-243.
17 MOCT.(2007), "Civil Quantity Works calculated based on guidelines," Ministry of Construction and Transportation (MOCT), Seoul (in Korean).
18 Kim K. J.(2007), "Quantity - Theory and Practice," Gumi Books (in Korean).
19 Cho, J. H.(2008), "Development of an Activity-Based Conceptual Cost Estimating Model for P.S.C Box Girder Bridge," KICEM (2008-11).
20 Park S. H.(2008), "Object & Parameter based Schematic Estimation Model for Predicting Cost of Building Interior Finishings," KICEM, Vol. 9, No. 6, pp. 175-184.
21 Jung, Y. H.(2004), "Static Data Analysis".
22 Jang, S. K.(2006), "Basic Static Data Analysis".
23 Kim D. S.(2008), "Regression analysis Fundamentals and Applications" pp. 209-228.