• Title/Summary/Keyword: Change of the Uncertainty

Search Result 618, Processing Time 0.032 seconds

Long Term Stability of Uncertainty Analysis of Light Oil Elow Standard System (장기 안정성을 고려한 경질유 유량표준장치 불확도 평가)

  • Lim, Ki-Won;Choi, Jong-Oh
    • Transactions of the Korean Society of Mechanical Engineers B
    • /
    • v.29 no.10 s.241
    • /
    • pp.1130-1138
    • /
    • 2005
  • A national standard system for the petroleum field has been developed to calibrate and test the oil flow meters in Korea. The operating system and the uncertainty of the system were evaluated by the peer reviewers of foreign national metrology institutes in 2002. Since the characteristics of the system might be changed by time, the uncertainty of the system is reevaluated with the consideration of the long term stability of the system. It is found that the system has a relative expanded uncertainty of 0.048 $\%$ in the range of $15\~120\;m^3/h$. According to the uncertainty budget, the uncertainties of the fluid density and the final mass measurement, which are temperature dependent, contribute about $94\%$ of the total uncertainty in the oil flow standard system

A Study on the Uncertainty of Additional Generating Capacity in Long Term Electricity Plan (전력수급기본계획에서 발전소 준공 불확실성에 대한 고찰)

  • Kim, C.S.;Rhee, C.H.
    • Proceedings of the KIEE Conference
    • /
    • 2005.07a
    • /
    • pp.843-845
    • /
    • 2005
  • The uncertainty of long term electricity plan consists of the uncertainty of demand forecast and additional generating capacity. Demand forecast is clearly improved the accuracy than the past through improving forecasting methods. However, the uncertainty of additional generating capacity is increased due to the change of market environment. In an operation by a sole utility, additional generating capacity would be possible by the regulation of government. Currently the generation companies have spined off from KEPCO and some IPPs participate the electricity market. It increases the uncertainty due to weakened regulation. Also the environment movement by NGOs and occurrence of civil affairs cause the increase of uncertainty. This research would analyze the current situation on the uncertainty of additional generating capacity and construction delays. Furthermore this research would present the plan to reflecting it in long term electricity plan.

  • PDF

Prediction Model of Final Project Cost using Multivariate Probabilistic Analysis (MPA) and Bayes' Theorem

  • Yoo, Wi Sung;Hadipriono, FAbian C.
    • Korean Journal of Construction Engineering and Management
    • /
    • v.8 no.5
    • /
    • pp.191-200
    • /
    • 2007
  • This paper introduces a tool for predicting potential cost overrun during project execution and for quantifying the uncertainty on the expected project cost, which is occasionally changed by the unknown effects resulted from project's complications and unforeseen environments. The model proposed in this stuff is useful in diagnosing cost performance as a project progresses and in monitoring the changes of the uncertainty as indicators for a warning signal. This model is intended for the use by project managers who forecast the change of the uncertainty and its magnitude. The paper presents a mathematical approach for modifying the costs of incomplete work packages and project cost, and quantifying reduced uncertainties at a consistent confidence level as actual cost information of an ongoing project is obtained. Furthermore, this approach addresses the effects of actual informed data of completed work packages on the re-estimates of incomplete work packages and describes the impacts on the variation of the uncertainty for the expected project cost incorporating Multivariate Probabilistic Analysis (MPA) and Bayes' Theorem. For the illustration purpose, the Introduced model has employed an example construction project. The results are analyzed to demonstrate the use of the model and illustrate its capabilities.

Uncertainty assessment caused by GCMs selection on hydrologic studies

  • Ghafouri-Azar, Mona;Bae, Deg-Hyo
    • Proceedings of the Korea Water Resources Association Conference
    • /
    • 2018.05a
    • /
    • pp.151-151
    • /
    • 2018
  • The present study is aimed to quantifying the uncertainty in the general circulation model (GCM) selection and its impacts on hydrology studies in the basins. For this reason, 13 GCMs was selected among the 26 GCM models of the Fifth Assessment Report (AR5) scenarios. Then, the climate data and hydrologic data with two Representative Concentration Pathways (RCPs) of the best model (INMCM4) and worst model (HadGEM2-AO) were compared to understand the uncertainty associated with GCM models. In order to project the runoff, the Precipitation-Runoff Modelling System (PRMS) was driven to simulate daily river discharge by using daily precipitation, maximum and minimum temperature as inputs of this model. For simulating the discharge, the model has been calibrated and validated for daily data. Root mean square error (RMSE) and Nash-Sutcliffe Efficiency (NSE) were applied as evaluation criteria. Then parameters of the model were applied for the periods 2011-2040, and 2070-2099 to project the future discharge the five large basins of South Korea. Then, uncertainty caused by projected temperature, precipitation and runoff changes were compared in seasonal and annual time scale for two future periods and RCPs compared to the reference period (1976-2005). The findings of this study indicated that more caution will be needed for selecting the GCMs and using the results of the climate change analysis.

  • PDF

Spatial prioritization of climate change vulnerability using uncertainty analysis of multi-criteria decision making method (다기준 의사결정기법의 불확실성 분석기법을 이용한 기후변화 취약성에 대한 지역별 우선순위 결정)

  • Song, Jae Yeol;Chung, Eun-Sung
    • Journal of Korea Water Resources Association
    • /
    • v.50 no.2
    • /
    • pp.121-128
    • /
    • 2017
  • In this study, robustness index and uncertainty analysis were proposed to quantify the risk inherent in the process of climate change vulnerability assessment. The water supply vulnerability for six metropolitan cities (Busan, Daegu, Incheon, Gwangju, Daejeon, and Ulsan), except for Seoul, were prioritized using TOPSIS, a kind of multi-criteria decision making method. The robustness index was used to analyze the possibility of rank reversal and the uncertainty analysis was introduced to derive the minimum changed weights of the criteria that determine the rank reversal between any paired cities. As a result, Incheon and Daegu were found to be very vulnerable and Daegu and Busan were derived to be very sensitive. Although Daegu was relatively vulnerable against the other cities, it can be largely improved by developing and performing various climate change adaptation measures because it is more sensitive. This study can be used as a preliminary assessment for establishing and planning climate change adaptation measure.

Design of Adaptive Observer for Power System with Structured Uncertainty (구조화된 불확실성을 갖는 전력 계통의 적응 관측기 설계)

  • Hwang, Jung-Rok;Kim, Do-Woo;Kim, Hong-Pil;Yang, Hai-Won
    • Proceedings of the KIEE Conference
    • /
    • 1999.07c
    • /
    • pp.1211-1214
    • /
    • 1999
  • Power system operating conditions vary with system configuration and loading conditions. Coefficients in nominal system model change in a complex manner with different operating point and so does system dynamic behavior. With the aid of unstructured and structured uncertainty descriptions the worst system variations can be estimated and formulated into two different uncertainty models multiplicative unstructured uncertainty in the form of transfer function and structured uncertainty with the parametric uncertainty description. in frequency domain

  • PDF

Determination of Weighted Value to Estimate Each Emission Factor of Landfill (폐기물 매립부문 배출계수 평가항목의 가중치 결정)

  • Lee, Seung Hoon;Kim, Jae Young;Yi, Seung Muk;Choi, Eun Hwa;Kim, Young Soo
    • Journal of Climate Change Research
    • /
    • v.5 no.3
    • /
    • pp.199-208
    • /
    • 2014
  • According to "IPCC guide line for national greenhouse gas inventories" each country should develop the 'Country-specific emission factor' and apply it to estimate greenhouse gases emissions from landfill. It could reflect properties of country and make estimation more accurate. For that accuracy, developed country-specific emission factor should be assessed and be verified consistently. Developed emission factors should be assessed in terms of Representative, Emission Property, Accuracy and Uncertainty, but there is no study about weighted assessment factors under each emission variable. This study do survey targeting public officials, professors and other experts for Analytical Hierarchy Process(AHP), mostly use to make decisions, to weight assessment factors. We investigated the weighted values per Emission factor for Representative, Emission property, Accuracy and Uncertainty on AHP survey, and Representative factor was the highest, and then in the order of Emission property (0.26), Accuracy(0.22), Uncertainty (0.15).

Evaluation of Uncertainty Importance Measure by Experimental Method in Fault Tree Analysis (결점나무 분석에서 실험적 방법을 이용한 불확실성 중요도 측도의 평가)

  • Cho, Jae-Gyeun
    • Journal of Korea Society of Industrial Information Systems
    • /
    • v.14 no.5
    • /
    • pp.187-195
    • /
    • 2009
  • In a fault tree analysis, an uncertainty importance measure is often used to assess how much uncertainty of the top event probability (Q) is attributable to the uncertainty of a basic event probability ($q_i$), and thus, to identify those basic events whose uncertainties need to be reduced to effectively reduce the uncertainty of Q. For evaluating the measures suggested by many authors which assess a percentage change in the variance V of Q with respect to unit percentage change in the variance $\upsilon_i$ of $q_i$, V and ${\partial}V/{\partial}{\upsilon}_i$ need to be estimated analytically or by Monte Carlo simulation. However, it is very complicated to analytically compute V and ${\partial}V/{\partial}{\upsilon}_i$ for large-sized fault trees, and difficult to estimate them in a robust manner by Monte Carlo simulation. In this paper, we propose a method for experimentally evaluating the measure using a Taguchi orthogonal array. The proposed method is very computationally efficient compared to the method based on Monte Carlo simulation, and provides a stable uncertainty importance of each basic event.

Uncertainty Characteristics in Future Prediction of Agrometeorological Indicators using a Climatic Water Budget Approach (기후학적 물수지를 적용한 기후변화에 따른 농업기상지표 변동예측의 불확실성)

  • Nam, Won-Ho;Hong, Eun-Mi;Choi, Jin-Yong;Cho, Jaepil;Hayes, Michael J.
    • Journal of The Korean Society of Agricultural Engineers
    • /
    • v.57 no.2
    • /
    • pp.1-13
    • /
    • 2015
  • The Coupled Model Intercomparison Project Phase 5 (CMIP5), coordinated by the World Climate Research Programme in support of the Intergovernmental Panel on Climate Change (IPCC) AR5, is the most recent, provides projections of future climate change using various global climate models under four major greenhouse gas emission scenarios. There is a wide selection of climate models available to provide projections of future climate change. These provide for a wide range of possible outcomes when trying to inform managers about possible climate changes. Hence, future agrometeorological indicators estimation will be much impacted by which global climate model and climate change scenarios are used. Decision makers are increasingly expected to use climate information, but the uncertainties associated with global climate models pose substantial hurdles for agricultural resources planning. Although it is the most reasonable that quantifying of the future uncertainty using climate change scenarios, preliminary analysis using reasonable factors for selecting a subset for decision making are needed. In order to narrow the projections to a handful of models that could be used in a climate change impact study, we could provide effective information for selecting climate model and scenarios for climate change impact assessment using maximum/minimum temperature, precipitation, reference evapotranspiration, and moisture index of nine Representative Concentration Pathways (RCP) scenarios.

A Progress-based Expert System for Quantitative Assessments of Project Delay

  • Yoo, Wi Sung
    • Architectural research
    • /
    • v.10 no.1
    • /
    • pp.41-48
    • /
    • 2008
  • Construction projects have frequently exceeded their schedule despite reliable estimates at the start of a project. This problem was attributed to unpredictable causes at the beginning and to shortage of proper tools to accurately predict project completion date. To supplement this difficulty, project managers need a comprehensive system that can be employed to monitor the progress of an ongoing project and to evaluate potential delay for achieving the goal on time. This paper proposed a progressive-based expert system for quantitative assessments of project delay at the early stages of the execution. Furthermore, the system is used to inspect the change of the uncertainty on completion date and its magnitude. The proposed expert system is helpful for furnishing project managers a warning signal as a project is going behind schedule and for tracking the changed uncertainty at a desired confidence level. The main objectives of this paper are to offer a new system to overcome the difficulties of conventional forecasting tools and to apply a construction project into the system to illustrate its effectiveness. This paper focuses on construction phase of project development and is intended for the use by project managers.