Korea Mechanical Construction Contractors Association
월간 기계설비
/
no.11
s.208
/
pp.21-28
/
2007
내역입찰제도 개선, 적격심사항목 보완, 적격심사 이행관리계획 미준수 업체 제재사유 추가, 정정공고 근거규정 마련 등을 주요 골자로 하는 국가계약법 시행령 및 시행규칙이 제.개정되어 지난 10월 10부터 시행에 들어갔다. 개정된 시행규칙은 1억원 미만 소규모 공사는 물량내역서가 계약서에 포함되지 않아 발주기관의 물량산정 오류시 설계변경이 불가능해 소규모 공사에서 경제적 피해가 많이 발생되어 민원이 제기됨에 따라 우리협회는 재정경제부에 "1억원 미만 소규모 공사도 계약서에 물량내역서가 포함되도록" 건의한 결과 우리협회의 의견이 반영되었다.
Kim, Soon-Young;Han, Choong-Hee;Baek, Tae-Ryong;Kim, Kyoon-Tai;Lee, Jun-Bok
Korean Journal of Construction Engineering and Management
/
v.11
no.2
/
pp.35-44
/
2010
Currently, the unit price of public construction projects are not being evaluated appropriately for several reasons. First, the evaluation of the unit price differ per nature of the bidding process and its estimation process. In fact, pricing is determined to meet the total price in turnkey projects and to pass the low bid price deliberation process in unit price projects, and thus, such prices cannot be said to be reasonable prices per public project. After the contract is awarded, however, the prices determined without taking into consideration the characteristic of each bidding process and price estimate process are used for the valuation of progress payment, design changes, and escalation. Furthermore, this is also being applied to other low bid deliberation process as actual public project unit price, thereby affecting other processes as well. In effect, this system increases the risks for both the owner and the bidder who have determined the unit price. This research examines the risk factor and its extent in order to properly manage it in preparation for the future.
Korea Mechanical Construction Contractors Association
월간 기계설비
/
no.11
s.208
/
pp.29-40
/
2007
국가계약법 시행령이 개정됨에 따라 재정경제부는 공사계약 일반조건, 입찰조건, 입찰유의서 등 회계예규를 개정하고 지난 10월 12일부터 시행에 들어갔다. 개정된 시행규칙은 공사계약일반조건에서 설계서와 물량내역서 등의 범위에 대한 정의규정 보완/손해보험 관련 손해공제 포함/설계변경 관련 조문정리/설계변경 계약금액조정 제한대상 추가 및 입찰금액조정 규정 마련/특정규격의 자재별 가격변동에 따른 계약금액조정 관련 등이 개정되었고, 공사입찰유의서에는 입찰에 관한 서류의 열람 및 교부/입찰무효사유 보완/낙찰자가 부적격자로 판명된 경우 낙찰자 결정 방법 개선/조문정리 등이 개선되었다.
The amount of new apartment construction has been trending upward in 3~4% each year since 11% increase in 2002. Currently, in public apartment construction sites under separate delivery system for construction waste processing, the significant difference between estimated quantity for contract and actual amount frequently causes severe controversy among project participants. Many factors such as poor environmental management, inadequate contractual amount are assumed to influence the above problem, and the requirement to revise existing generation rates, the key criteria applied in estimating the quantities of waste, is increasing. Most of generation rates were established in early 2000's, and have difficulty in reflecting the changes from new materials and technologies accordingly. Therefore, this study aims to clarify the types of construction waste for each trade and the forecast method as preliminary work in order to develop more accurate generation rates for construction waste in new construction. To achieve this purpose, the architectural bills of quantities in ten apartment projects executed during 2010~2013 were collected, and the possible waste types and reasonable material loss ratio for each item from temporary works to owner-supplying material area were defined and compared through the workshops and interviews with the experts and on-site environmental managers. The results of this study will contribute to establishing the categories of construction waste for construction trades and proper generation rates by the indirect estimation method in new apartment construction in the follow-up study.
Korean Journal of Construction Engineering and Management
/
v.13
no.3
/
pp.99-108
/
2012
The rough design information is only available from BIM(Building Information Model) based schematic design. So, it is difficult to obtain sufficient information for generating BOQ. Like 2D design, there are some problems that the results are depend on what the choice of cost estimator. However, the most research of BIM based cost estimation are focus on quantity takeoff, the consideration of work item for generating BOQ is insufficient. Therefore, this paper present automatic inference process of work items in a BOQ using ontology. The proposed process and ontology is validated through applying tiling construction. If the proposed process is utilized, it is expected the basis of developing generation method for consistent BOQ by resolving intervention of cost estimator's arbitrary decision.
공정거래위원회(위원장 정호열)는 지난 11월 6일 표준하도급계약서를 개정하고 이날부터 시행에 들어갔다. 개정된 표준하도급계약서는 발주자의 요청에 따라 설계변경이 이루어진 경우 증가된 물량 또는 신규비목의 단가는 설계변경 당시를 기준으로 산정한 단가와 이 단가에 낙찰률을 곱한 금액을 합한 금액의 100분의 50 이내에서 당사자간 협의해 정하도록 했다. 다만, 발주자의 요청 이외의 사유로 설계변경이 이뤄진 경우에는 종전과 같이 $\Delta$증감된 공사의 단가는 수급사업자가 작성한 산출내역서 상 단가를 적용하고 $\Delta$신규비목의 단가는 설계변경 당시 기준으로 작성한 단가에 낙찰률을 곱한 금액을 적용토록 했다.
Lee, Kee Sei;Choi, Jun Ho;Jiang, Meiling;Kang, Young Jong
한국방재학회:학술대회논문집
/
2011.02a
/
pp.164-164
/
2011
최근들어 교량 건설 프로젝트는 그 규모가 방대해 졌을 뿐만아니라, 건설에 사용되는 장비 및 자재, 인력의 종류 또한 다양해 지고 있다. 이에 따라 종래 구조적 안전만을 추구하던 건설현장은 이러한 제반 요소들을 효율적으로 관리하여 경제성뿐만 아니라 시공의 효율성 까지 고려할 수밖에 없게 되었다. 따라서 건설 현장의 진도 및 자재, 인력관리는 현대 건설 산업의 주요 과제라 할 수 있다. 이에 따라 본 연구에서는 현장의 시공정보를 무선으로 송신할 수 있는 단말기 및 RFID를 이용하여 종래에 시행되던 작업을 자동화함으로써 작업의 편리성을 도모하고 이를 통하여 시간과 인력의 낭비를 줄일 수 있는 시공관리 시스템에 대한 모듈을 제안 하였다. 제안된 시스템은 3D모델을 기반으로 하여 진도 및 공비를 한눈에 알아볼 수 있는 방안을 제시한다. 사용자는 현재 진행되고 있는 공정을 3차원 모델에서 확인할 수 있으며, 현재까지 사용된 비용 및 공정률을 손쉽게 확인할 수 있다. 3D모델은 공사 시작 전 공정에 맞추어 분절된 형태로 제작되어 현장에서 송신한 위치정보가 통합관리 시스템에서 수신되면 해당 새그가 화면에 나타나게 된다. 3D모델은 공정시각화의 역할을 할 뿐만 아니라 각 새그에는 사용된 자재의 종류나 수량등이 DB화 되어 있어, 실시간으로 공사에 사용된 물량을 산출 할수 있도록 한다. 시공정보의 수신은 각 자재에 부착한 RFID태그를 직접 읽어서 송신하거나, 작업자가 시공상황을 단말기를 통하여 직점 송신함으로써 이루어지게 된다. 수집된 시공정보는 3D모델과 연계됨과 동시에 통합관리 시스템에 내장된 DB와 연결되어 사용 자재 및 물량에 대한 비용산출에 중요한 역할을 하게 된다. 현재 우리나라의 교량 시공 현장에서는 기성청구시 내역서를 기준으로 비용을 산정하게 되는데, 시공관리 통합 프로그램에서는 각 공정이 DB화된 내역서와 연계되어 3D모델에서 얻어진 물량으로 공비를 산출하는 과정이 자동으로 이루어지게 된다. 이러한 과정은 단일 현장뿐만 아니라, 공구 내의 여러 교량 현장에 대하여도 적용이 가능하므로, 방대한 현장의 공사관리에 소요되던 시간과 노력을 절감 할 수 있다. 본 연구를 통하여 현장에서 이루어지는 공사관리 작업에 대해 IT기술을 접목하여 자동화 할 수 있는 방법에 대한 알고리즘을 제시하였다. 이는 모바일 오피스 및 단말기를 이용하여 현 공정까지 사용된 물량, 인력, 장비 정보를 관리하는 한편, 현재까지 진행된 공사 내용을 3D모델을 통하여 한눈에 알아볼수 있는 교량 건설현장 통합관리 시스템의 모듈을 제공한다. 이에따라 공무 작업에 소모되는 인력 및 시간을 크게 절약 할 수 있을 것이라 판단된다.
Korean Journal of Construction Engineering and Management
/
v.20
no.6
/
pp.89-97
/
2019
Recently, BIM has been actively introduced in construction projects. In particular, the introduction of BIM in cost estimating process is expected to improve the accuracy and efficiency of the cost estimate. However, the quantity calculation and BoQ documents preparation process still require manual work. Although the BIM model may support quantification process, it is still problematic that the level of detail of the model must be very detailed to meet the items in BoQ. To address this, it is necessary to analyse the LOD criteria and to analyze the extent to which quantity can be computed according to the level of detail in the BIM model. For the analysis of LOD-based work items, the work item grades were divided into A,B, and C. In this study, the ratio and cost of each item that can be calculated at the LOD level in the detailed design phase are reviewed for each type of work, and the method for improving the quantity calculation using BIM is proposed. In the LOD 300 stage(Detailed design stage), the largest number of items in the class B, the major improvement class, are window and glass work. In addition, the most expensive type of work was analyzed by reinforced concrete work. In the future, it is necessary to suggest appropriate improvement way for items with high item ratios and items with high cost ratios. The results of this study are expected to be used as a BIM-based cost estimation or as basic data for improving the current BoQ system.
It is very important to estimate accurate construction total cost needed early in the project. In the initial phase of the design, the project cost estimates are determined by total quantity from design documents and the variables that affect the calculation of the total cost of the project. In order to determine accurate total construction cost, the contractor has to produce detailed quantity information based on the drawings and specifications. The process of preparing quantification and cost estimation documents is still being worked out manually, and a lot of errors have been occurred in many cases. Recent advances in information technology have led to the BIM based quantity takeoff and cost estimation. However, there are some limits to the extent to which the current specifications for BoQ documents are computed from BIM model. This research analyze the current BoQ cases and analyze how to make quantity takeoff possible through BIM. The study defined five levels of quantity category that could be produced by BIM. Only about 40% or indirectly usable items can be used when information is extracted to BIM modelling. This is very insufficient to fill out the BoQ. The BoQ document structure quantity takeoff specifications should be simplified in order to BIM based cost estimation more efficiently.
Kim, Soon-Young;Han, Choong-Hee;Baek, Tae-Ryong;Kim, Kyoon-Tai;Lee, Jun-Bok
Korean Journal of Construction Engineering and Management
/
v.10
no.6
/
pp.107-116
/
2009
As the Fundamentals of Construction Business Act was revised in December 2004 and its implementing ordinances and enforcement regulations were adjusted in June 2005, the screening system of low price subcontracting has been an obligation to the public owners, having brought about arguments for and against since it enacted in 1983. The statutes for low price subcontracting have been reinforced from this year; for example, it underlines to submit to a project and builds an information network of subcontracting works. The system's original intention was that prevents shoddy and fraudulent constructions caused by low price subcontracting and precludes disturbances of fair trade by screening that whether it satisfies the conditions or not in advance. But, the criterion for the existing low price subcontracting has several issues having held up a true mirror to the real situation. It is arguable to discharge an important task with the primary purpose. This dissertation have researched the problem with a deposit of subcontract and the low price subcontracting basic rate are being used by the criteria for deciding whether it is a low price subcontracting or not, so showing the plan of reformation based on the findings, it wishes to contribute toward making the most of the system's essential intent.
본 웹사이트에 게시된 이메일 주소가 전자우편 수집 프로그램이나
그 밖의 기술적 장치를 이용하여 무단으로 수집되는 것을 거부하며,
이를 위반시 정보통신망법에 의해 형사 처벌됨을 유념하시기 바랍니다.
[게시일 2004년 10월 1일]
이용약관
제 1 장 총칙
제 1 조 (목적)
이 이용약관은 KoreaScience 홈페이지(이하 “당 사이트”)에서 제공하는 인터넷 서비스(이하 '서비스')의 가입조건 및 이용에 관한 제반 사항과 기타 필요한 사항을 구체적으로 규정함을 목적으로 합니다.
제 2 조 (용어의 정의)
① "이용자"라 함은 당 사이트에 접속하여 이 약관에 따라 당 사이트가 제공하는 서비스를 받는 회원 및 비회원을
말합니다.
② "회원"이라 함은 서비스를 이용하기 위하여 당 사이트에 개인정보를 제공하여 아이디(ID)와 비밀번호를 부여
받은 자를 말합니다.
③ "회원 아이디(ID)"라 함은 회원의 식별 및 서비스 이용을 위하여 자신이 선정한 문자 및 숫자의 조합을
말합니다.
④ "비밀번호(패스워드)"라 함은 회원이 자신의 비밀보호를 위하여 선정한 문자 및 숫자의 조합을 말합니다.
제 3 조 (이용약관의 효력 및 변경)
① 이 약관은 당 사이트에 게시하거나 기타의 방법으로 회원에게 공지함으로써 효력이 발생합니다.
② 당 사이트는 이 약관을 개정할 경우에 적용일자 및 개정사유를 명시하여 현행 약관과 함께 당 사이트의
초기화면에 그 적용일자 7일 이전부터 적용일자 전일까지 공지합니다. 다만, 회원에게 불리하게 약관내용을
변경하는 경우에는 최소한 30일 이상의 사전 유예기간을 두고 공지합니다. 이 경우 당 사이트는 개정 전
내용과 개정 후 내용을 명확하게 비교하여 이용자가 알기 쉽도록 표시합니다.
제 4 조(약관 외 준칙)
① 이 약관은 당 사이트가 제공하는 서비스에 관한 이용안내와 함께 적용됩니다.
② 이 약관에 명시되지 아니한 사항은 관계법령의 규정이 적용됩니다.
제 2 장 이용계약의 체결
제 5 조 (이용계약의 성립 등)
① 이용계약은 이용고객이 당 사이트가 정한 약관에 「동의합니다」를 선택하고, 당 사이트가 정한
온라인신청양식을 작성하여 서비스 이용을 신청한 후, 당 사이트가 이를 승낙함으로써 성립합니다.
② 제1항의 승낙은 당 사이트가 제공하는 과학기술정보검색, 맞춤정보, 서지정보 등 다른 서비스의 이용승낙을
포함합니다.
제 6 조 (회원가입)
서비스를 이용하고자 하는 고객은 당 사이트에서 정한 회원가입양식에 개인정보를 기재하여 가입을 하여야 합니다.
제 7 조 (개인정보의 보호 및 사용)
당 사이트는 관계법령이 정하는 바에 따라 회원 등록정보를 포함한 회원의 개인정보를 보호하기 위해 노력합니다. 회원 개인정보의 보호 및 사용에 대해서는 관련법령 및 당 사이트의 개인정보 보호정책이 적용됩니다.
제 8 조 (이용 신청의 승낙과 제한)
① 당 사이트는 제6조의 규정에 의한 이용신청고객에 대하여 서비스 이용을 승낙합니다.
② 당 사이트는 아래사항에 해당하는 경우에 대해서 승낙하지 아니 합니다.
- 이용계약 신청서의 내용을 허위로 기재한 경우
- 기타 규정한 제반사항을 위반하며 신청하는 경우
제 9 조 (회원 ID 부여 및 변경 등)
① 당 사이트는 이용고객에 대하여 약관에 정하는 바에 따라 자신이 선정한 회원 ID를 부여합니다.
② 회원 ID는 원칙적으로 변경이 불가하며 부득이한 사유로 인하여 변경 하고자 하는 경우에는 해당 ID를
해지하고 재가입해야 합니다.
③ 기타 회원 개인정보 관리 및 변경 등에 관한 사항은 서비스별 안내에 정하는 바에 의합니다.
제 3 장 계약 당사자의 의무
제 10 조 (KISTI의 의무)
① 당 사이트는 이용고객이 희망한 서비스 제공 개시일에 특별한 사정이 없는 한 서비스를 이용할 수 있도록
하여야 합니다.
② 당 사이트는 개인정보 보호를 위해 보안시스템을 구축하며 개인정보 보호정책을 공시하고 준수합니다.
③ 당 사이트는 회원으로부터 제기되는 의견이나 불만이 정당하다고 객관적으로 인정될 경우에는 적절한 절차를
거쳐 즉시 처리하여야 합니다. 다만, 즉시 처리가 곤란한 경우는 회원에게 그 사유와 처리일정을 통보하여야
합니다.
제 11 조 (회원의 의무)
① 이용자는 회원가입 신청 또는 회원정보 변경 시 실명으로 모든 사항을 사실에 근거하여 작성하여야 하며,
허위 또는 타인의 정보를 등록할 경우 일체의 권리를 주장할 수 없습니다.
② 당 사이트가 관계법령 및 개인정보 보호정책에 의거하여 그 책임을 지는 경우를 제외하고 회원에게 부여된
ID의 비밀번호 관리소홀, 부정사용에 의하여 발생하는 모든 결과에 대한 책임은 회원에게 있습니다.
③ 회원은 당 사이트 및 제 3자의 지적 재산권을 침해해서는 안 됩니다.
제 4 장 서비스의 이용
제 12 조 (서비스 이용 시간)
① 서비스 이용은 당 사이트의 업무상 또는 기술상 특별한 지장이 없는 한 연중무휴, 1일 24시간 운영을
원칙으로 합니다. 단, 당 사이트는 시스템 정기점검, 증설 및 교체를 위해 당 사이트가 정한 날이나 시간에
서비스를 일시 중단할 수 있으며, 예정되어 있는 작업으로 인한 서비스 일시중단은 당 사이트 홈페이지를
통해 사전에 공지합니다.
② 당 사이트는 서비스를 특정범위로 분할하여 각 범위별로 이용가능시간을 별도로 지정할 수 있습니다. 다만
이 경우 그 내용을 공지합니다.
제 13 조 (홈페이지 저작권)
① NDSL에서 제공하는 모든 저작물의 저작권은 원저작자에게 있으며, KISTI는 복제/배포/전송권을 확보하고
있습니다.
② NDSL에서 제공하는 콘텐츠를 상업적 및 기타 영리목적으로 복제/배포/전송할 경우 사전에 KISTI의 허락을
받아야 합니다.
③ NDSL에서 제공하는 콘텐츠를 보도, 비평, 교육, 연구 등을 위하여 정당한 범위 안에서 공정한 관행에
합치되게 인용할 수 있습니다.
④ NDSL에서 제공하는 콘텐츠를 무단 복제, 전송, 배포 기타 저작권법에 위반되는 방법으로 이용할 경우
저작권법 제136조에 따라 5년 이하의 징역 또는 5천만 원 이하의 벌금에 처해질 수 있습니다.
제 14 조 (유료서비스)
① 당 사이트 및 협력기관이 정한 유료서비스(원문복사 등)는 별도로 정해진 바에 따르며, 변경사항은 시행 전에
당 사이트 홈페이지를 통하여 회원에게 공지합니다.
② 유료서비스를 이용하려는 회원은 정해진 요금체계에 따라 요금을 납부해야 합니다.
제 5 장 계약 해지 및 이용 제한
제 15 조 (계약 해지)
회원이 이용계약을 해지하고자 하는 때에는 [가입해지] 메뉴를 이용해 직접 해지해야 합니다.
제 16 조 (서비스 이용제한)
① 당 사이트는 회원이 서비스 이용내용에 있어서 본 약관 제 11조 내용을 위반하거나, 다음 각 호에 해당하는
경우 서비스 이용을 제한할 수 있습니다.
- 2년 이상 서비스를 이용한 적이 없는 경우
- 기타 정상적인 서비스 운영에 방해가 될 경우
② 상기 이용제한 규정에 따라 서비스를 이용하는 회원에게 서비스 이용에 대하여 별도 공지 없이 서비스 이용의
일시정지, 이용계약 해지 할 수 있습니다.
제 17 조 (전자우편주소 수집 금지)
회원은 전자우편주소 추출기 등을 이용하여 전자우편주소를 수집 또는 제3자에게 제공할 수 없습니다.
제 6 장 손해배상 및 기타사항
제 18 조 (손해배상)
당 사이트는 무료로 제공되는 서비스와 관련하여 회원에게 어떠한 손해가 발생하더라도 당 사이트가 고의 또는 과실로 인한 손해발생을 제외하고는 이에 대하여 책임을 부담하지 아니합니다.
제 19 조 (관할 법원)
서비스 이용으로 발생한 분쟁에 대해 소송이 제기되는 경우 민사 소송법상의 관할 법원에 제기합니다.
[부 칙]
1. (시행일) 이 약관은 2016년 9월 5일부터 적용되며, 종전 약관은 본 약관으로 대체되며, 개정된 약관의 적용일 이전 가입자도 개정된 약관의 적용을 받습니다.