Developing a Project Management Information System for Construction Claims  

Wang, Hankyeom (School of Architectural Engineering, Korea University of Technology and Education (Koreatech))
Park, Junil (Strategic Planning Department, Hankook Construction Management Consultancy (HKCMC), Inc.)
Choi, Jaehyun (School of Design and Architectural Engineering, Korea University of Technology and Education (Koreatech))
Publication Information
Korean Journal of Construction Engineering and Management / v.19, no.4, 2018 , pp. 70-81 More about this Journal
Abstract
Claims in the construction industry can have a serious impact on the profitability of the project or can even result in project failure if it fails to take appropriate prevention. In order to properly prevent and respond to the potential claims and legal disputes throughout the project execution, it is necessary to continuously accumulate informations and clearly define the roles and responsibilities of the important activities systematically. Based on these needs, this study develops and verifies the project information management system(PMIS) that can prevent and respond possible claims for construction projects. Developed system includes such management modules as schedule, cost, PM/CM, design, collaboration, and claims. The system was validated by adopting it to the practical projects. The results showed that information systems tailored to the construction claim need to elevate users' familiarity to be more useful. Besides, the system can be more functional when used by both owners and contractors.
Keywords
Claim; Disputes; PMIS; Document Management; Collaborative Management;
Citations & Related Records
Times Cited By KSCI : 2  (Citation Analysis)
연도 인용수 순위
1 Choi, J. W. (2015). "An Analysis on Regional Differences of Major Delay Factors in Overseas Architectural Projects-Focused on the Southeast Asia and the Middle East." MS thesis, Hanyang Univ., Seoul.
2 Choi, S. K. (2016). "Legal Issues Relating to Acceleration in International Construction Contracts." Korean Forum on International Trade and Business Law, 25(1), pp. 205-243.
3 Chung, H. S. (2014). "Comparative Analysis on Concurrent Delay in International Construction Contract-Focusing on Common Law Approaches." The Korean Association of Comparative Private Law, 21(2), pp. 827-864.
4 Kim, W. T. and Lee, Y. H. (2012). "Overseas Construction Contracts and Claim Management Status and Countermeasures." Construction Economy Research Institute of Korea, CERIK, Construction Issue Focus, pp. 1-29.
5 Jeon, K. H. and Yoon, S. H. (2010). "A Study of Improvement Through Utilization of PMIS and Perceptions of Field Managers Research." Journal of The Regional Association of Architectural Institute of Korea, 2010(1), pp. 383-386.
6 Jeong, M. J. and Cho, Y. J. (2007). "A Study on the Improvement Contract System of to Prevent Domestic Public Construction Claims." Proceedings of KICEM Annual Conference, KICEM, 7, pp. 239-242.
7 Kang, L. S. and Kwon, J. H. (2008). "Estimating System for Responsible Days of Schedule Delay for Construction Projects through Time Impact Analysis." Journal of the Korean Society of Civil Engineers, KSCE, 28(5D), pp. 685-694.
8 Kim, Y., Hong, J., Kim, K., and Kim, J. (1999). "A Study on the Reasonable Analysis Method for Delay Claims-Based on Judical Precedents." Journal of the Architectural Institute of Korea Structure & Construction, 15(7), pp. 117-126.
9 Kim, Y. J., Kim, T. S., Jo, D. S. and Lee, H. G. (2015). " A Study on Substantiation Methodology for Extension of Time in International Mega-Project Claims." Korean Journal of Construction Engineering and Management, KICEM, 16(3), pp. 165-176.   DOI
10 Construction Economy Research Institute of Korea (CERIK) (2008). Analysis on the Trends in Construction Claims in Korea, CERIK Research Report, 1998-10.
11 Yoon, J. S. (2006). "A Study of Analyzing Claim Factor and Making Strategies to Prevent Claim in Early Stage for Architectural Turn-key Project." Journal of Korea Institute of Building Construction, 6(1), pp. 93-99.   DOI
12 Lee, J. H., Lee, H. S., Park, M. S. and Kim, I. H. (2007 ). "Claim Management during Construction Based on Key Claim Management Factors." Proceedings of KICEM Annual Conference, KICEM, 7, pp. 463-468.
13 Seo, J. H., Kim, Y. S. and Jin, S. Y. (2010). "Eliciting Management Factors of Claims types for Coping with The Construction Claim." Proceedings of KICEM Annual Conference, KICEM, 10, pp. 287-288.
14 Sung, N. W., Kim, Y. S., Lee, M. Y. and Lee, J. S. (2006). "The Development of a Web-based Decision Support System for Construction Claim Management." Journal of Korea Society of Civil Engineers. KSCE, 26(1D), pp. 115-123.