Approximate Estimating of Plant Construction Duration Using a Standard Schedule Model  

Moon, Sung-Woo (부산대학교 토목공학과)
Park, Sang-Chun (부산대학교 토목공학과)
Kwon, Ki-Nam (부산대학교 토목공학과)
Publication Information
Korean Journal of Construction Engineering and Management / v.10, no.2, 2009 , pp. 26-33 More about this Journal
Abstract
The required level of detail in scheduling depends on the stages in the construction life-cycle. The objective of this study is to provide a Standardized Schedule Model (SSM) with an aim to facilitate the estimating of construction duration in the planning stage. The SSM modularizes work items; establishes relations between preceding and succeeding activities; and calculates approximate construction duration. The estimated duration of the SSM was compared with the detailed duration from the commercial scheduling tool using actual work activities. The difference showed to be ranged between -3.1% and +15%, which demonstrates that the SSM can be feasibly applied to the approximate estimation of construction duration.
Keywords
standard schedule model; preliminary estimating; activity duration; critical path; activity relation;
Citations & Related Records
연도 인용수 순위
  • Reference
1 EL-Rayes, K. (2001) 'Objective-Oriented Model for Repetitive Construction Scheduling', Journal of Construction Engineering and Management, ASCE, 127(3), pp. 199-205   DOI   ScienceOn
2 김정렬, 진경호, 김경주 (2001) '공공 도로건설사업 공정, 원가 통합관리 시스템 구축 연구' 대한토목학회논문집 21(5), 703-712
3 우성권, 이종수 (2002) '건설공사 공기 및 공정관리 현황과 문제점', 건설산업동향 2002(10), pp. 2-16
4 Shaked, O., Warszawski, A. (1992) 'CONSHED: Expert System for Scheduling of Modular Construction Projects', Journal of Construction Engineering and Management, ASCE, 118(3), pp. 488-506   DOI
5 Dzeng, R. J., Wang, W.C., Tsemg, H.P. (2004) 'Module-Based Construction Schedule Administration for Public Infrastructure Agencies', Journal of Construction Engineering and Management, ASCE, 130(1), pp. 5-14   DOI   ScienceOn
6 박찬정, 최인성(2000) '건설시공단계에서의일정-원가의통합방안' 대한건축학회논문집 16(9), pp. 83-90
7 김희정, 김수정, 김재준, 김경래(2001) '공공-공사비통합관리를 위한 현장공사관리체계 개선방안', 대한건축학회논문집 17(6), pp. 113-122
8 Project Management Institute (2000) Project Management Body of Knowledge, Newtown Square, PA, pp. 65-81
9 정순오 (2002) '건설프로젝트 공정관리 분야의 최근 연구동향', 경복논총 Vol.6, pp. 161-176
10 김양택, 현창택(2000) '국내건설산업의공정-공사비통합모델 비교분석' 대한건축학회논문집 16(12), pp. 145-153