Causes of Construction Delays of Apartment Construction Projects: Comparative Analysis between Vietnam and Korea  

Kim, Young-Mok (부경대학교 건설관리공학협동과정)
Kim, Soo-Yong (부경대학교 건설공학부)
Luu, Truong-Van (부경대학교 건설관리공학협동과정)
Publication Information
Korean Journal of Construction Engineering and Management / v.9, no.5, 2008 , pp. 214-226 More about this Journal
Abstract
Construction delay caused considerable losses to project parties. Avoiding construction delays is important to save costs for project stakeholders. The main objective of this paper is to identify major causes of construction delays of apartment construction projects in Vietnam. Sixteen causes of delay were identified through a questionnaire survey of 166 professionals. Factor analysis was employed to categorize these causes. The results of the survey revealed the main causes of delay of apartment projects in Vietnam are: (1) owner's and contractor'S financial difficulties; (2) lack of experienced contractors; (3) late delivery of materials; (4) late construction site handover; (5) owner's late payments for completed works; (6) low bid prices; (7) inappropriate construction method; and (8) defective works and unnecessary reworks. Factor analysis uncovered that causes of delay can be grouped under five categories labeled the five INs: incompetence, ineffectiveness, inadequateness, inapplicableness and inconceivableness. Comparative analysis between the Vietnam construction industry (VCI) and the Korea construction industry (KCI) has been performed to infer valuable lessons for researchers and practitioners in the VCI and the KCI. Comparative analysis indicated that main causes of delay in the VCI somewhat differ from main causes of delay in the KCI. However, "contractor'S financial difficulties", "late construction site handover", "unnecessary rework", "incapable designers", "site clearance difficulties" are common causes of delay in the VCI as well as the KCI. The findings of this research can be used as a guideline to overcome problems in the VCI as well as in other construction industries. Since Korea has emerged as the first largest foreign investor in Vietnam, the results of this study may be useful not only to practitioners and researchers in Vietnam but also to participants in Korea.
Keywords
apartment projects; causes of delay; comparative analysis; empirical study; factor analysis; Korea; time overruns; Vietnam;
Citations & Related Records
Times Cited By KSCI : 1  (Citation Analysis)
연도 인용수 순위
1 Acharya, N.K, Lee, Y.D., and Im, H.M. (2006). 'investigating delay factors in construction industry: a Korean perspective. 'Korean Journal of Constuction Engineering and Management, 10, pp.177-190   과학기술학회마을
2 Bradsher, K. (2006), 'Vietnam'S roaring economy is set for world stage.'The New York Times, (2006.10.25)
3 Burleson, R.C., Haas, C.T., Tucker, R.L., and Stanley, A. (1998). 'Multi-skilled labor utilization strategies in construction. Journal of Construction Engineering and Management, ASCE, 124(6), pp.480-489   DOI
4 Hair, J.F., Anderson, R.E., Tatham, R.L., and Black, W.C. (1998). Multivariate Data Analysis, 5th Ed., Prentice Hall
5 Kaiser, H.F., and Rice, J. (1974). 'Little Jiffy Mark IV. 'Educational and psychological measurement, 34 (spring), pp.111-117   DOI
6 Mansfield, N.R., Ugwu, O.O., and Doran, T. (1994). 'Causes of delays and cost overruns in Nigeria construction projects.' International Journal of Project Management, 12 (4), pp.254-260   DOI   ScienceOn
7 Ogunlana, S.O., Promkuntong, K., and Jearkjirm, V. (1996). 'Construction delays in a fast-growing economy: comparing Thailand with other economies.' International Journal of Project Management, 14 (1), pp.37-45.   DOI   ScienceOn
8 Sanvido, V., Grobler, F., Parfitt, K., Guvenis, M., and Coyle, M. (1992). 'Critical success factors for construction projects.' Journal of Construction Engineering and Management, ASCE, 118(1), pp.94- 111   DOI
9 Thomas, R.T., Riley, D.R., and Sanvido, V.E. (1999). 'Loss of labor productivity due to delivery methods and weather.' Journal of Construction Engineering and Management, ASCE, 125(1), pp.39-46   DOI   ScienceOn
10 Assaf, S.A., Al-Khalid, M. and Al-Hazmi, M. (1995). 'Causes of delay in large building construction projects.' Journal of Construction Engineering and Management, ASCE, 11 (2), pp.45-50
11 Koushki, P.A., Al-Rashid, K., and Kartam, N. (2005). ' Delays and cost increases in the construction of private residential projects in Kuwait. Construction Management and Economics, 23(3), pp.285-294   DOI   ScienceOn
12 VNAb. (2007), 'New waves in Viet Nam-Republic of Korea relations.'Vietnam News Agency, (2008.01.12)
13 Wikipedia. (2007). 'Geography of Vietnam.' Wikipedia - the free encyclopedia, http://en.wikipedia.org/wiki/Geography_of_Vietnam> (2008.01.16)
14 Othman, A.A., Torrance, J.V., and Hamid, M.A. (2006). 'Factors influencing the construction time of civil engineering projects in Malaysia.' Engineering Construction and Architectural Management, 13 (5), pp.481-501   DOI   ScienceOn
15 mirkhanian, S.N., and Baker, N.J. (1992). 'Expert system for equipment selection for earth-moving operations.' Journal of Construction Engineering and Management, ASCE, 118(2), pp.318-331   DOI
16 Long, N.D., Ogunlana, S., Quang, T., and Lam, K.C. (2004). 'Large construction projects in developing country: a case study from Vietnam.' International Journal of Project Management, 22(7), pp.553-561   DOI   ScienceOn
17 Yates, J.K. (1993). 'Construction decision support system for delay analysis.' Journal of Construction Engineering and Management, ASCE, 119(2), pp.226-244   DOI   ScienceOn
18 Arditi, R.D., Akan, G.T., and Gurdamar, S. (1985). 'Reasons for delays in public projects in Turkey.' Construction Management and Economics, 3, pp.171-181   DOI
19 Odeh, A.M., and Battaineh, H.T. (2002). 'Causes of construction delay: traditional contracts.' International Journal of Project Management, 20(1), pp.67-73
20 Assaf, S.A, and Al-Hejji, S. (2006). 'Causes of delay in large construction projects.'International Journal of Project Management, 24(4), pp.349-357   DOI   ScienceOn
21 Arditi, R.D., and Gunaydin, H.M. (1998). Factors that effect process quality in the life cycle of building projects.' Journal of Construction Engineering and Management, ASCE, 124(3), pp.194-203   DOI   ScienceOn
22 Thomas, H.R., and Napolitan, C.L. (1995). 'Quantitative effects of construction changes on labor productivity.' Journal of Construction Engineering and Management, ASCE, 121(3), pp.290-296
23 Russell, A.D. (1993). 'Computerized daily site reporting.' Journal of Construction Engineering and Management, ASCE, 119(2), pp.385-402   DOI
24 Fisher, D.J., and Rajan, N. (1986). 'Automated constructability analysis of work-zone trafficcontrol planning.' Journal of Construction Engineering and Management, ASCE, 122(1), pp.36-43   DOI
25 Sambasivan, M., and Soon, Y.W. (2007). 'Causes and effects of delays in Malaysian construction industry.' International journal of Project Management, 25, pp.517-526   DOI   ScienceOn
26 VNAa. (2007), 'Republic of Korea is still a first foreign investor in Vietnam.'Vietnam News Agency, (2008.01.12)
27 Frimpong, Y., Oluwoye, J., and Crawford, L. (2003). 'Causes of delay and cost overruns in construction of groundwater projects in a developing countries; Ghana as a case study.' International Journal of Project Management, 21(5), pp.321-326   DOI   ScienceOn
28 Kaming, P.F., Olomolaiye, P.O., Holt, G.D., and Harris, F.C. (1997). 'Factors influencing construction time and cost overruns on high-rise projects in Indonesia.' Construction Management and Economic, 15, pp.83-94   DOI
29 Sharma, S. (1996). Applied Multivariate Techniques, John Willey & Sons
30 Ng, W.M., Khor, E.L., Tiong, L.K., and Lee, J. (1998). 'Simulation modeling and management of large basement construction.' Journal of Computing Civil Engineering, ASCE, 12(2), pp.101-110   DOI   ScienceOn
31 Dozzi, P., Hartman, F., Tidsbury, N., and Ashrafi, R. (1996), 'More-stable owner-contractor relationship.' Journal of Construction Engineering and Management, ASCE, 122(1), pp.30-35   DOI
32 Sullivan, A., and Harris, F.C. (1986). 'Delays on large construction projects.' International Journal of Operation Production Management, 6(1), pp.25-33   DOI
33 Maloney, W.F., and McFillen, J.M. (1986). 'Motivational implications of construction work.' Journal of Construction Engineering and Management, ASCE, 2(1), pp.137-151
34 Mulholland, B., and Christian, J. (1999). 'Risk assessment in construction schedules. 'Journal of Construction Engineering and Management, 125(1), pp.8-15   DOI   ScienceOn
35 Sweis, G., Sweis, R., Hammad, A.A., and Shboul, A. (2007). 'Delays in construction projects: the case of Jordan. ' International Journal of Project Management, (2008.01.14)
36 Daoud, O.E.K. (1997). 'The architect/engineer's role rehabilitation work.' Journal of Construction Engineering and Management, ASCE, 123(1), pp.1-5   DOI   ScienceOn
37 Songer, A.D., and Molenaar, K.R. (1997). 'Project characteristics for successful public-sector deignbuild.' Journal of Construction Engineering and Management, ASCE, 123(1), pp.34-40   DOI   ScienceOn