Economical Analysis and Estimate Method of Possible Working Hours for Marine Rock Excavation Work Regarding the Tide Cycle  

Kwon, Soon-Boum (대한주택공사)
Ock, Jong-Ho (서울산업대학교 건축공학과)
Lee, Seung-Hyun (한국건설기술연구원)
Publication Information
Korean Journal of Construction Engineering and Management / v.8, no.5, 2007 , pp. 142-151 More about this Journal
Abstract
The rock excavation work on the sea is planned as underwater process if the elevation of the rock is lower than the M.S.L.(Mean Sea Level). However, in case of West and South sea which are largely different between the rise and fall of the tide, the earth work can be performed on the ground while the work surface is exposed above the sea according to the tide cycle. Thus, it may a good substitute to make up for shortcomings of underwater construction works such as safety problems of workers, loss of efficiency and increasement of construction costs. But the difference between the height of the rock excavation surface and the water surface changed by the tide makes the exposure time of work surface, that is the possible working hours be changed. Also, it may cause the changes of construction cost. Thus, this study analyzes the economical efficiency of the construction method using the difference between the rise and fall of the tide in comparison with the construction method which is performed under the sea, and it also suggests the way to analyze the economical working hours by estimating the possible working hours on the ground. We also try to find out the application possibility of the way like the rock excavation work on the sea using the difference between rise and fall of the tide.
Keywords
Marine Construction; Underwater Rock Excavation; Tide; possible working hours;
Citations & Related Records
연도 인용수 순위
  • Reference
1 서재화 외 1인, '인천국제공항 연육교(영종대교 가설공법 적용사례', 건설기술정보, 한진중공업, VOL. 26, 1999
2 해운항만청, '항만공사적산표준예', 1994
3 조덕인 외 3인, '복합 S.R.C 공법과 CAISSION 진수 및 거치사례', 건설기술정보, VOL. 39, 2005
4 육일동, '해상구간 장대 강교량의 가설공법에 관한 연구', 건설기술정보, 한진중공업, VOL. 32, 2002
5 손창백 외 1인, '건축공사의 생산성 저하요인 분석', 대한건축학회 논문집, 대한건축학회, 18권 12호, 2002
6 김정웅 외 3인, '영종대교 복층 Warren Truss 해상구간 가설공법', 학술발표대회 논문집, 한국건설관리학회, 제2회, 2001
7 정인수 외 3인, '군시설 공사의 순공사기간 예측모형에 관한 연구', 대한건축학회 논문집, 대한건축학회, 2000
8 한국물가협회, '월간 물가자료', 한국물가협회, 2006
9 한국물가정보, '종합물가정보', 한국물가정보, 2006
10 한국건설기술연구원, '2006 건설공사 표준품셈', 건설교통부, 2006
11 한진중공업, '플로트 매팅 방식에 의한 중량물 선적방법 및 장치', 건설기술정보, 한진중공업, VOL. 28, 2000
12 국립해양조사원 조석정보