THE ROOT CAUSE ANALYSIS PROCESS FOR SCHEDULE DELAY IN CONSTRUCTION  

Ji, Kun-Chang (광운대학교 건축공학과)
Kim, Chang-Duk (광운대학교 건축공학과)
Yu, Jung-Ho (광운대학교 건축공학과)
Publication Information
Korean Journal of Construction Engineering and Management / v.7, no.5, 2006 , pp. 138-148 More about this Journal
Abstract
In constructing projects, there exist various kinds of work interferences, which cause a delay of the outset and completion of planned schedule because of some attributions, such as variability, uncertainty and complexity, and so schedule delay has been treated as a natural phenomenon. To reduce or prevent the schedule delay, a constant confirmation of schedule delay and a preparation of counter plans for finding out the cause structure of schedule delay should have been done. However, all this time the research has been mostly done on the calculation method or claim cases of schedule delay, and the range of analysis method of the cause structure of schedule delay has been multifarious from industrial views to views of specific work. Moreover, the classifying system and analysis method did not consider the trait, which cause the schedule delay, in constructing projects. For this reason, it is difficult to compare the cause of delay factors of the projects and to understand the effect of schedule delay by each factor. This paper restricts the range of the cause analysis of schedule delay to the field of site management in the projects and divides the cause structure of schedule delay into the cause objects and cause attributes of schedule delay according to the input elements. The system of classifying causes of schedule delay is examined by interviews with experts and questionnaire. Additionally, this paper analyzes the attributes of cause attributes and cause subjects and presents the analysis method and procedure of schedule delay with the application of VSM.
Keywords
Schedule Delay; Root cause analysis method; schema of Schedule delay analysis;
Citations & Related Records
Times Cited By KSCI : 3  (Citation Analysis)
연도 인용수 순위
1 류한국, 유정호, 이현수 (2002). '손실생산성을 고려한 공기지연일수 산정방법' 건축, 제18권 10호, 대한건축학회, pp. 117-124
2 표영민, 배수용, 유형한, 이상범 (2005). 'AHP기법을 이용한 건설노동생산성 저하요인 분석에 관한 연구' 한국건축시공학회 학술.기술논문발표회 논문집, 제5권 1호, 한국건축시공학회, pp. 141-148
3 Department of Energy. et. al (1992). 'Root cause analysis guidance document' Washington, D.C., U.S., 69 pp
4 H. Glenn Ballard (2000). 'The last planner system of production control' Ph.D, Univ. of Birmingham, 192 pp
5 Jimmie Hinze, Caroline Pedersen, John Fredley (1998). 'Identifying root causes of construction injuries' ASCE, J. of Constr. Engrg. and Mgmt., 124(1), pp. 67-71   DOI   ScienceOn
6 Johan s. carlson, Rikard S?derberg (2003). 'Assembly root cause analysis: A way to reduce dimensional variation in assembled products' The international journal of flexible manufacturing systems, Netherlands, pp. 113-150
7 Office of Safety and Mission Assurance, Chief Engineers Office (2003), 'Root cause analysis overview' NASA report, (2006. 3. 25)
8 Saied Kartam (1999). 'Generic Methodology for Analyzing Delay Claims' ASCE, J. of Constr. Engrg. and Mgmt., 125(6), pp. 409-419   DOI
9 Said A. Assaf, Mohammed Al-Khalil, Muhammad Al-Hazmi (1995) 'Cause of delay in Large Building Construction Projects' ASCE, J. of Mgnt. in Engrg., 11(2), pp. 45-50   DOI   ScienceOn
10 한종관, 진상윤, 김예상 (2003) '시공자 중심의 주요 공종별 공기지연 원인분석에 관한 연구-공동주택을 중심으로' 건축, 제19권 3호, 대한건축학회, pp. 163-170
11 Chris J. Eagle, Jan M. Davies, J. Reason (1992). 'Accident analysis of large-scale technological disasters applied to an anaesthetic complication' Canadian journal of anaesthesia, 39(2), pp. 118-122   DOI
12 김선국, 송용식, 이종국 (2006). ' 潛在的클레임이 公共아파트 工事管理에 미치는 영향요인분석' 대한건축학회 논문집(구조계), 제22권 4호, 대한건축학회, pp. 187-195
13 Alkass, S., Mazerolle, M., Tribaldos, E., and Harris, F. (1995). 'Computer aided construction delay analysis and claims preparation' ASCE, J. of Constr. Engrg. and Mgmt., 13(4), pp. 335-352
14 Augustine U. Elinwa, Mangvwat Joshua (2001). 'Timeoverrun factors in nigerian construction industry' ASCE, J. of Constr. Engrg. and Mgmt., 127(5), pp. 419-425   DOI   ScienceOn
15 M.Z. Abd. Majid (1998). 'Factors of Non Excusable Delays That Influence Contractors 'Performance' J. of Mgmt in Engrg., 14(3), pp. 42-49   DOI   ScienceOn
16 Iamara Rossi Bulh.oes1, Flavio Augusto Picchi2 and Ariovaldo Denis Granja(2000), 'Combining value stream and process levels analysis for continuous flow implementation in construction', Proceeding of the 14th annual conference of the international group for lean construction(IGLC-14), Sydney, Australia, July, pp. 99-107
17 Paulo Andery, Antonio N. Carvalho Jr., and Horacio Helman (1998). 'Looking for what could be wrong: an approach to lean thinking' Proceeding of the 6th annual conference of the international group for lean construction(IGLC-6), (2006. 3. 28)
18 H. Randolph Thomas, Ahmet S. Sakarcan (1994). 'Forecasting Labor Productivity Using Factor Model' ASCE, J. of Constr. Engrg. and Mgmt., 120(1), pp. 228-239   DOI   ScienceOn
19 문정문 (2002). '가치흐름분석을 통한 건설 프로세스의 낭비제거 방법-철근공사를 중심으로' 광운대학교 대학원 건축공학과, 석사논문, 108 pp
20 홍영탁, 유정호, 임경호, 이현수 (2005).'FMEA를 이용한 초고층 건축시공의 공기영향요인 평가' 대우건설기술, 제27호, pp. 149-163
21 Tariq S. Abdelhamid, John G. Everett (2000). 'Identifying Root Causes of Construction Accidents' ASCE, J. of Constr. Engrg. and Mgmt., 126(1), pp. 52-60   DOI   ScienceOn
22 Daud Nasir, Brenda McCabe, Loesie Hartono (2003) 'Evaluating Risk in Construction-Schedule Model (ERIC-S): Construction Schedule Risk Model' ASCE, J. of Constr. Engrg. and Mgmt.,, 129(5), pp. 518-527   DOI   ScienceOn
23 Gary R. Smith, Caryn M. Bohn (1999). 'Small to Medium Contractor Contingency and Assumption of Risk' ASCE, J. of Constr. Engrg. and Mgmt., 125(2), pp. 101-108   DOI   ScienceOn