Improvement Plan of Post Construction Evaluation: Focus on Construction Performance

건설공사 사후평가 개선방안: 사업수행성과 중심으로

  • 박희성 (한밭대학교 건설환경공학과) ;
  • 김태영 (한밭대학교, 보령시청)
  • Received : 2024.03.04
  • Accepted : 2024.04.02
  • Published : 2024.06.01

Abstract

The size of the construction industry is increasing, and its impact on the entire national industry is also significant. However, construction cost increases, construction period delays, safety accidents, and quality problems occur during the construction process. This paper analyzed the construction cost, construction period, and change order performance for civil infrastructures for which post evaluation was performed. The analysis was conducted by dividing civil engineering facilities by type, construction nature, construction cost, contract nature, and delivery method. Planned and actual construction cost and period were compared during the planning, design, and construction process of civil engineering facilities. There is a possibility of input errors in project performance data, this paper proposes to the post-evaluation center should perform post-evaluation. Also, post-evaluation implementation guidelines for change orders should be revised. Additionally, further analysis of each facility was proposed through continuous data collection.

건설산업의 규모는 증가하고 있으며 국가 산업 전체에 미치는 영향도 크다. 그러나 건설사업 수행과정에서 공사비 증액, 공사 기간 지연, 안전사고 발생, 품질 문제 등이 발생하고 있다. 본 논문은 사후평가를 수행한 토목시설물 공사를 대상으로 공사 수행과정 중 공사비, 공사 기간, 설계변경 성과를 분석하였다. 토목시설물을 종류별, 공사 성격별, 공사 규모별, 계약 성질별, 입찰방식별로 구분하여 분석을 수행하였다. 이를 통해 공공사업으로 수행한 토목시설물 공사의 계획, 설계, 시공과정에서 공사비와 공사 기간 등의 예측과 그 결과를 비교하였다. 사업수행성과 데이터의 입력 오류 가능성이 있으므로 사후평가센터의 사후평가 직접 수행과 설계변경 시행지침의 변경을 제안하였다. 그리고 데이터의 지속적인 수집을 통해 시설물별 세부 분석을 제안하였다.

Keywords

Acknowledgement

This study was financially supported by Hanbat National University Financial Accounting Research Fund 2022 year.

References

  1. Ahn, J., Baek, S., Yun, S., Lee, K. and Han, S. (2023). "Analysis of major cases of road construction change order." Proceedings of KICEM Annual Conference, pp. 245-246 (in Korean).
  2. Ji, S., Park, M., Lee, H. and Yoon, Y. (2008). "Direction for improving cost estimation and management of construction projects: comparing to australian system." Korean Journal of Construction Engineering and Management, Vol. 9, No. 2, pp. 170-181 (in Korean).
  3. Jung, E., Yeom, D., Kim, J. and Kim, Y. (2021). "Development of construction cost estimation model for elementary, middle and high school facilities." Korean Journal of Construction Engineering and Management, Vol. 22, No. 3, pp. 69-78, https://doi.org/10.6106/KJCEM.2021.22.3.069 (in Korean).
  4. Kim, H. and Kim, H. (2023). "A study on the development of construction budget estimating model for public office buildings based on artificial neural network." Korean Journal of Construction Engineering and Management, Vol. 24, No. 5, pp. 22-34, https://dx.doi.org/10.6106/KJCEM.2023.24.5.022 (in Korean).
  5. Kim, K., Lee, D. and Kim, T. (2015). "A study for error analysis for post evaluation system on the construction projects." Korean Journal of Construction Engineering and Management, Vol. 16, No. 2, pp. 77-85, https://doi.org/10.6106/KJCEM.2015.16.2.077 (in Korean).
  6. Kim, J., Lee, J. and Lee, M. (2023). "A study on the improvement of long-term continuing construction contracts dispute using FGI." Korean Journal of Construction Engineering and Management, Vol. 24, No. 2, pp. 79-87, https://dx.doi.org/10.6106/KJCEM.2023.24.2.079 (in Korean).
  7. Koo, B., Yu, J. and Park, J. (2015). "Formal estimation method for optimal budget appropriation of highway construction projects under long-term construction contracts." Journal of the Korean Society of Civil Engineering, Vol. 35, No. 6, pp. 1405-1412, https://doi.org/10.12652/Ksce.2015.35.6.1405 (in Korean).
  8. KOSTAT (2003). Domestic value of construction orders received, https://kosis.kr/statHtml/statHtml.do?orgId=365&tblId=TX_365 05_A000&conn_path=I2 (Accessed: August 26, 2023). 
  9. Kwon, Y. and Kim, K. (2023). "A study on the problems and improvement plan of the post-evaluation system for construction work." Proceedongs of KICEM Annual Conference 2023, pp. 291-292 (in Korean).
  10. Lee, K. and Lee, H. (2011). "The study of analysis for costincreasing factors on public construction projects." Conference Proceedings of the Regional Association of Architectural Institute of Korea, pp. 105-108.
  11. Lee, K. and Park, H. (2018). "Development of the qualitative model for post construction evaluation." Journal of the Korean Society of Civil Engineers, Vol. 38, No. 5, pp. 733-739, https://doi.org/10.12652/Ksce.2018.38.5.0733 (in Korean).
  12. Lee, J., Tae, Y., Baek, S. and Kim, K. (2022). "A study of improvements in the standards of cost estimate for the new excellent technology in construction." Korean Journal of Construction Engineering and Management, Vol. 23, No. 5, pp. 65-76, https://dx.doi.org/10.6106/KJCEM.2022.23.5.065 (in Korean).
  13. Lee, J. and Yun, H. (2021). "Improvement plan through analysis of the current status of construction period calculation of public construction projects." Korean Journal of Construction Engineering and Management, Vol. 22, No. 3, pp. 12-20, https://doi.org/10.6106/KJCEM.2021.22.3.012 (in Korean).
  14. Mun, J. and Yun, S. (2023). "Analyzing planning performance of road construction projects using preliminary feasibility analysis data." Korean Journal of Construction Engineering and Management, Vol. 24, No. 1, pp. 3-11, https://dx.doi.org/10.6106/KJCEM.2023.24.1.003 (in Korean).
  15. Nam, S. and Park, H. (2020). "A study on the construction cost index for calculating conceptual estimation: 1970-1999." Journal of the Korean Society of Civil Engineering, Vol. 40, No. 5, pp. 527-534, https://doi.org/10.12652/Ksce.2020.40.5.0527 (in Korean).