DOI QR코드

DOI QR Code

Performance Analysis for Proposing Proper Construction Method for Joints of Polyurea Waterproofing Membrane Coating

폴리우레아 도막방수재의 이음부 적정 시공안 제안을 위한 성능 분석

  • Lee, Jung-Hun (BK Waterproofing Technology Institute) ;
  • Kim, Byoungil (School of Architecture, Seoul National University of Science & Technology)
  • Received : 2023.09.08
  • Accepted : 2023.12.23
  • Published : 2024.02.20

Abstract

In this study, an evaluation was conducted for a total of 16 conditions to suggest an appropriate construction method for the construction joint of polyurea waterproofing membrane coating. It was analyzed that the longer the construction time difference, the higher the rate of water leaks through joints, and it was confirmed that water leaks could be prevented through primer construction. In addition, since the surface of polyurea exposed outdoors for a long period of time is deteriorated and weakened, it was analyzed that polishing the area increases surface damage and affects the formation of the interface. During maintenance construction, it would be desirable to apply a primer before construction, and it is believed that using the same urea-based material will ensure waterproofing stability.

본 연구에서는 폴리우레아 도막방수재의 시공 시차별 분석과 열화면에 대한 유지관리 시공 타입별 분석을 통해 시공 이음부위의 적정 시공 방안을 제시하고자 전체 16가지 조건을 대상으로 시공 이음부위에 대한 평가를 진행하였다. 결과 분석을 통해 시공시차가 길어지면 길어질수록 이음부를 통한 누수발생률은 증가하는 것으로 분석되었고, 프라이머 시공을 통해 누수 예방이 가능한 것으로 확인되었다. 또한 장시간 옥외 노출된 폴리우레아는 표면이 열화되어 약해진 상태이기 때문에 해당 부위를 연마할 경우 표면손상이 확대되어 계면 형성에 영향을 미치는 것으로 분석되어, 유지관리 시공 시에는 프라이머를 도포하고 시공하는 것이 바람직하겠으며, 동일한 우레아 계열의 재료를 시공하는 것이 방수 안정성을 확보할 수 있을 것으로 판단된다.

Keywords

Acknowledgement

This study was financially supported by the Seoul National University of Science & Technology.

References

  1. Oh SK, Kim SR, Lee SI. A study on waterproofing performance evaluation of polyurea resin waterproofing membrane coating of velocity per second hardening. Journal of the Korea Institute of Building Construction. 2002 Feb;2(1):131-8. https://doi.org/10.5345/JKIC.2002.2.1.131 
  2. Lee JH, Choi EK, Song JY, Kim SY, Oh SK. Applicability of composite polyurea method considering the required performance in underground parking lot upper slab. Journal of the Korean Recycled Construction Resources Institute. 2019 Sep;7(3):243-54. https://doi.org/10.14190/JRCR.2019.7.3.243 
  3. Cho, CH. A study on waterproofing and anticorrosive performance evaluation of polyurea resin waterproofing membrane coating of velocity per second hardening [master's thesis]. Seoul(Korea): Seoul national University of Technology; 2004. 82 p. 
  4. Park WG, Park JS, Choi SY, Kim DB, Kim BI, Oh SK. A study on the thermal performance change due to amount of carbon fiber in poly-urea waterproofing material. Proceedings of The Korea Institute of Building Construction; 2017 Nov 09-10; Busan, Korea. Seoul (Korea): The Korea Institute of Building Construction; 2017. p. 126-7. 
  5. Oh SK, Kim SR, Choi EK, Choi SM, Kim YK. Analysis of chemically resistant characteristic to the liquid-applied membrane waterproofing materials of the rapidly hardening sprayed type applied on the concrete structure. Journal of the Architectural Institute of Korea Structure & Construction. 2013 Dec;29(12):113-20. https://doi.org/10.5659/JAIK_SC.2013.29.12.113 
  6. Doh KG, Song JY, Kim BI, Oh SK. An experimental study to improve durability of polyurea waterproofing anticorrosive materials applied to concrete water tank. Proceedings of The Korea Institute of Building Construction; 2020 Jun 12; Daejeon, Korea. Seoul (Korea): The Korea Institute of Building Construction; 2020. p. 12-3. 
  7. Kim SR, Kim, YG, Lee JD. A study on the improvement of construction defect of aftercuring polyurea coating film for waterproof and anti-corrosion. Journal of the Architectural Institute of Korea Structure & Construction. 2014 Nov;30(11):45-52. https://doi.org/10.5659/JAIK_SC.2014.30.11.45 
  8. Kim SD, Park WG, Park JS, Cho IK, Kim BI, Oh SK. A study on the reduction of scattering of polyurea coating for waterproofing and anti-corrosion by installing air jet nozzle. Proceedings of The Korea Institute of Building Construction; 2017 May 17-19; Kyungju, Korea. Seoul (Korea): The Korea Institute of Building Construction; 2017. p. 236-7. 
  9. Doh, KG. An experimental study to improve durability of polyurea waterproofing anticorrosive materials applied to concrete water tank [master's thesis]. Seoul (Korea): Seoul National University of Science and Technology; 2022. 92 p. 
  10. KS F 4922:2022. Polyurea resin waterproofing membrane coating. Korean Standards Association. Seoul(Korea): Korean Agency for Technology and Standards; 2022. 9 p. 
  11. KS F 2274. Standard test method for accelerated artificial exposure of plastic building materials. Korean Standards Association. Seoul(Korea): Korean Agency for Technology and Standards; 2018. 2-5 p. 
  12. KS L 5109. Practice for mechanical mixing of hydraulic cement pastes and mortars of plastic consistency. Korean Standards Association. Seoul(Korea): Korean Agency for Technology and Standards; 2017. 1-3 p.