KO AC/DC Converter System Installation Status and Commissioning Plan at ITER Site

이터 초전도자석 전원공급장치 현장 설치현황 및 시운전 계획

  • Song, Inho (Power Supply Technology Team, Korea Institute of Fusion Energy) ;
  • Oh, Jong-Seok (Power Supply Technology Team, Korea Institute of Fusion Energy)
  • Received : 2022.01.27
  • Accepted : 2022.03.14
  • Published : 2022.10.20

Abstract

The construction of the ITER tokamak machine is ongoing at a 77% process rate to achieve the first plasma in 2025. The 18 sets of power supply systems comprising 400 MVA thyristor AC/DC converters for the superconducting magnets supplied by Korea (KO) are being installed with other systems, such as PF converters (China), DC busbars (Russia), and cooling water systems (India), in two buildings (Europe). The system interfaces have been defined during the design stage, and the systems have been manufactured. However, during the on-site installation work, several installation and integration issues emerged due to the manufacturing tolerance and design mistakes. To continue the installation and testing, the engineers of each system resolved the interface issues, planned the commissioning, and integrated the test plan. This paper describes the on-site installation status and issues and the commissioning plan of KO AC/DC converters.

Keywords

Acknowledgement

이 논문은 2021년도 정부(과학기술정보통신부)의 재원으로 한국연구재단의 지원을 받아 수행된 국책연구사업임(No. 2007-2006995, 초전도자석 전원 공급장치 개발·제작)

References

  1. R. Aymar, "The ITER design," Plasma Phy. Control. Fusion, Vol. 44, No. 5, pp.519-565, Apr. 2002. https://doi.org/10.1088/0741-3335/44/5/304
  2. J. Oh and J. Choi, "Final design of the korean AC/DC converters for the ITER coil power supply system," Fusion Engineering and Design, Vol. 98-99, pp. 1127-1130, Oct. 2015. https://doi.org/10.1016/j.fusengdes.2015.06.147
  3. H. Tan and F. Fortunato, "ITER magnet power conversion building construction and AC/DC converter installation," Fusion Engineering and Design, Vol. 146, Part B, pp. 1891-1894, Sep. 2019. https://doi.org/10.1016/j.fusengdes.2019.03.058
  4. ITER document, Working Instruction for Completion Dossier Preparation(ITER_D_UYUSEE), Sep. 2017.