Analysis of Loss Costs and Risk Reserve due to Risk Events for Aircraft Runway Construction

활주로 건설공사의 위험사건에 따른 손실비용 및 위험예비비 분석

  • Kang, Hyun Wook (Department of Architectural Engineering, Gwangju University)
  • 강현욱 (광주대학교 건축학부 건축공학과)
  • Received : 2022.01.20
  • Accepted : 2022.03.21
  • Published : 2022.05.31

Abstract

The purpose of this study is to derive risk events that occurred during aircraft runway construction and analyze loss costs for project participants. For this purpose, design change data, contracted statement and completed statement were investigated. The results of this study are as follows: There were 12 risk events in the process of construction, 5 design errors and 7 construction errors. The increased construction costs due to such risk events were calculated as KRW 726 million. Of the KRW 726 million that was increased due to risk events, about 52.57% was spent by the ordering agency, and about 47.43% contractors. The increased construction costs due to such risk events are about 4.86% of the direct construction costs of KRW 14.9 billion. Based on the results derived from these case studies, a method for estimating reserve costs and construction costs considering risk events is presented.

본 연구의 목적은 활주로 건설공사에서 수집된 공사비 내역서, 설계변경 자료 등을 근거로 발생된 위험사건(위험항목)으로 인하여 변동된 공사금액을 산정하고 위험사건이 발생하게 된 원인에 따라 사업참여기관별로 손실비용을 분석하는 것이다. 본 연구를 수행한 결과, 위험사건은 12건이며, 증액된 총 공사금액은 726백만원으로 발주기관이 부담하여야 하는 금액은 약 52.57%, 건설사는 약 47.43%로 산정되었다. 또한, 계약금액의 직접공사비 149억원 대비 증액된 공사금액은 약 4.86%이며, 토공사로 분류된 위험사건에 따라 증액된 공사금액은 토공사의 직접공사비 대비 약 5.29% 그리고 건축공사로 분류된 위험사건에 따라 증액된 공사금액은 건축공사의 직접공사비 대비 약 4.04%에 해당하는 것으로 도출되었다.

Keywords

Acknowledgement

본 연구는 2022년도 광주대학교 대학 연구비의 지원을 받아 수행되었음.

References

  1. Ahn, S. (2015). "A Case Study of the Risk Identification in Construction Project." Korean Journal of Construction Engineering and Management, KICEM, 16(1), pp. 15-23. https://doi.org/10.6106/KJCEM.2015.16.1.015
  2. California (2012). Project Risk Management Handbook, California Department of Transportation.
  3. Cha, H.S., and Shin, K.Y. (2011). "Predicting Project Cost Performance Level by Assessing Risk Factors of Building Construction in South Korea." Journal of Asian Architecture and Building Engineering, 10(2), pp. 437-444. https://doi.org/10.3130/jaabe.10.437
  4. Han, S.H., Park, H.K., Yeom, S.M., Chae, M.J., and Kim, U.Y. (2014). "Risk-Integrated Cash Forecasting for Overseas Construction Projects." KSCE Journal of Civil Engineering, 18(4), pp. 875-886. https://doi.org/10.1007/s12205-014-0464-8
  5. Kang, H.W., and Kim, Y.S. (2018). "A Model for Risk Cost and Bidding Price Prediction Based on Risk Information in Plant Construction Projects." KSCE Journal of Civil Engineering, 22(11), pp. 4215-4229. https://doi.org/10.1007/s12205-018-0587-4
  6. Kang, H.W., and Kim, Y.S. (2016). "Analysis of the Probabilistic Cost Variation Ranges According to the Effect of Core Quantitative Risk Factors for an Overseas Plant Project." KSCE Journal of Civil Engineering, 20(2), pp. 509-518. https://doi.org/10.1007/s12205-015-0497-7
  7. Kang, H.W., Lee, W.B., Kim, M.J., Kim, Y.S. (2020). "A Case Study on the Risk Impact and Loss Cost of Temporary Aircraft Runway Construction." Korean Journal of Construction Engineering and Management, KICEM, 21(1), pp. 32-39. https://doi.org/10.6106/KJCEM.2020.21.1.032
  8. Kim, Y.S., and Kang, H.W. (2017). "Development of a Model for Risk and Cost Analysis in Overseas Plant Construction Projects." KSCE Journal of Civil Engineering, 20(5), pp. 1549-1562.
  9. Kim, J.H. (2010). "Plans for Reducing Risk through a Case Study of Risk Factors at a Construction Site." Journal of the Korea Institute of Building Construction, 10(4), pp. 83-93. https://doi.org/10.5345/JKIC.2010.10.4.083
  10. Kim, K.K. (2007). "A Study for Major Cost Increaseing Factors in Skyscraper Construction using FMEA." Journal of Architectural Institute of Korea, 23(5), pp. 171-178.
  11. Lee, M.J. (2016). "The Case Study on Performance Measurement Weighting for Efficient Value Engineering Study of Sewage Treatment Facility." Korea Journal of Construction Engineering and Management, 17(3), pp. 125-133. https://doi.org/10.6106/KJCEM.2016.17.3.125
  12. Ovidiu, C. (2014). Risk Management for Design and Construction, Wiley.
  13. Park, Y.M., Kim, S.Y., Kim, K.Y. (2005). "An Analysis of Risk Factors of a Construction Project Through Execution Plan." Korean Journal of Construction Engineering and Management, KICEM, 6(2), pp. 139-149.
  14. Sousa, V. (2014). "Risk-Informed Time-Cost Relationship Models for Sanitation Projects." ASCE Journal of Construction and Engineering Management, 140(5).
  15. Texas. (2010). Risk-Based Construction Cost Estimating Reference Guide, Texas Department of Transportation.