Analysis of Loss Costs and Risk Reserve due to Risk Events for Aircraft Runway Construction  

Kang, Hyun Wook (Department of Architectural Engineering, Gwangju University)
Publication Information
Korean Journal of Construction Engineering and Management / v.23, no.3, 2022 , pp. 25-35 More about this Journal
Abstract
The purpose of this study is to derive risk events that occurred during aircraft runway construction and analyze loss costs for project participants. For this purpose, design change data, contracted statement and completed statement were investigated. The results of this study are as follows: There were 12 risk events in the process of construction, 5 design errors and 7 construction errors. The increased construction costs due to such risk events were calculated as KRW 726 million. Of the KRW 726 million that was increased due to risk events, about 52.57% was spent by the ordering agency, and about 47.43% contractors. The increased construction costs due to such risk events are about 4.86% of the direct construction costs of KRW 14.9 billion. Based on the results derived from these case studies, a method for estimating reserve costs and construction costs considering risk events is presented.
Keywords
Aircraft Runway; Risk Events; Variation Costs; Loss Costs; Estimation Reserve;
Citations & Related Records
Times Cited By KSCI : 4  (Citation Analysis)
연도 인용수 순위
1 Ahn, S. (2015). "A Case Study of the Risk Identification in Construction Project." Korean Journal of Construction Engineering and Management, KICEM, 16(1), pp. 15-23.   DOI
2 California (2012). Project Risk Management Handbook, California Department of Transportation.
3 Han, S.H., Park, H.K., Yeom, S.M., Chae, M.J., and Kim, U.Y. (2014). "Risk-Integrated Cash Forecasting for Overseas Construction Projects." KSCE Journal of Civil Engineering, 18(4), pp. 875-886.   DOI
4 Kang, H.W., and Kim, Y.S. (2016). "Analysis of the Probabilistic Cost Variation Ranges According to the Effect of Core Quantitative Risk Factors for an Overseas Plant Project." KSCE Journal of Civil Engineering, 20(2), pp. 509-518.   DOI
5 Kim, J.H. (2010). "Plans for Reducing Risk through a Case Study of Risk Factors at a Construction Site." Journal of the Korea Institute of Building Construction, 10(4), pp. 83-93.   DOI
6 Ovidiu, C. (2014). Risk Management for Design and Construction, Wiley.
7 Texas. (2010). Risk-Based Construction Cost Estimating Reference Guide, Texas Department of Transportation.
8 Kang, H.W., Lee, W.B., Kim, M.J., Kim, Y.S. (2020). "A Case Study on the Risk Impact and Loss Cost of Temporary Aircraft Runway Construction." Korean Journal of Construction Engineering and Management, KICEM, 21(1), pp. 32-39.   DOI
9 Cha, H.S., and Shin, K.Y. (2011). "Predicting Project Cost Performance Level by Assessing Risk Factors of Building Construction in South Korea." Journal of Asian Architecture and Building Engineering, 10(2), pp. 437-444.   DOI
10 Kang, H.W., and Kim, Y.S. (2018). "A Model for Risk Cost and Bidding Price Prediction Based on Risk Information in Plant Construction Projects." KSCE Journal of Civil Engineering, 22(11), pp. 4215-4229.   DOI
11 Kim, Y.S., and Kang, H.W. (2017). "Development of a Model for Risk and Cost Analysis in Overseas Plant Construction Projects." KSCE Journal of Civil Engineering, 20(5), pp. 1549-1562.
12 Kim, K.K. (2007). "A Study for Major Cost Increaseing Factors in Skyscraper Construction using FMEA." Journal of Architectural Institute of Korea, 23(5), pp. 171-178.
13 Sousa, V. (2014). "Risk-Informed Time-Cost Relationship Models for Sanitation Projects." ASCE Journal of Construction and Engineering Management, 140(5).
14 Lee, M.J. (2016). "The Case Study on Performance Measurement Weighting for Efficient Value Engineering Study of Sewage Treatment Facility." Korea Journal of Construction Engineering and Management, 17(3), pp. 125-133.   DOI
15 Park, Y.M., Kim, S.Y., Kim, K.Y. (2005). "An Analysis of Risk Factors of a Construction Project Through Execution Plan." Korean Journal of Construction Engineering and Management, KICEM, 6(2), pp. 139-149.