DOI QR코드

DOI QR Code

A Study on Normal Project Period for Parking Lot of Aged Apartment Housing

노후 공동주택 주차장 리모델링 공사 표준공기 설정에 관한 연구

  • Bang, Seongbae (Department of Architectural Engineering, Graduate School, Incheon National University) ;
  • Jang, JunYoung (Department of Architectural Engineering, Graduate School, Incheon National University) ;
  • Koo, Choongwan (Division of Architecture and Urban Design, Incheon National University) ;
  • Kim, Taewan (Division of Architecture and Urban Design, Incheon National University) ;
  • Lee, Chansik (Division of Architecture and Urban Design, Incheon National University)
  • Received : 2021.09.29
  • Accepted : 2021.10.27
  • Published : 2021.11.30

Abstract

Recently, interest in remodeling apartment houses has been increasing due to problems such as a lack of parking spaces for old apartment houses. However, no method was suggested to predict the construction period of the apartment remodeling project. Unlike general apartment new construction, apartment remodeling construction involves demolition or reinforcement work, so a realistic remodeling construction period calculation plan differentiated from the existing construction period should be proposed. Therefore, this study intends to present a model for deriving the construction period of the underground parking lot of the apartment remodeling construction. Each construction period was calculated based on 19 activities of underground parking lot remodeling work through review of previous studies and expert advice. Activity's workload data and productivity data were derived to calculate the construction period, and the number of inputs and equipment inputs by Activity were determined to correct the productivity data. The construction period of Activity was calculated using the derived data, and the criteria for calculating the overlapping period for each Activity were presented to enable realistic construction period and scheduled schedule. As a result of predicting the accuracy of the construction period through the verification of the case complex, it is expected that it will be possible to predict the approximate construction period of the underground parking lot of the apartment remodeling construction in the future.

최근 노후 공동주택의 주차면수 부족 등의 문제로 공동주택 리모델링에 대한 관심이 높아지고 있다. 하지만 공동주택 리모델링 사업의 공사기간을 예측하기 위한 방법은 제시되지 않았다. 공동주택 리모델링 공사는 일반적인 공동주택 신축공사와 달리 철거공사나 보강공사가 수반되기 때문에 기존 공사기간 산정방안과 차별화된 현실성있는 리모델링 공사기간 산정방안이 제시되어야 한다. 따라서 이 연구에서는 공동주택 리모델링 공사의 지하주차장 공사기간을 도출하기 위한 모델을 제시하고자 한다. 선행 연구 고찰 및 전문가 자문을 통해 지하주차장 리모델링 공사의 19가지의 액티비티를 기준으로 각각의 공사기간을 산정하였다. 공사기간 산정을 위해 액티비티의 작업량데이터와 생산성데이터를 도출하였고, 생산성데이터의 보정을 위해 액티비티별 투입인원 및 장비투입대수를 결정하였다. 도출된 데이터를 활용하여 액티비티의 공사기간을 산출하였고, 액티비티 별 중첩기간 산정기준을 제시해 현실적인 공사기간과 예정공정표 작성이 가능하도록 하였다. 사례단지 검증을 통해 공사기간 정확도 예측 결과 정확도는 90%이상 일치하는 것으로 나타나 향후 공동주택 리모델링 공사의 지하주차장 개략 공사기간 예측과 공정표 작성이 가능할 것으로 기대된다.

Keywords

Acknowledgement

이 연구는 국토교통부 주거환경연구사업 중 "저비용·고효율의 노후 공동주택 수직증축 리모델링 기술개발 및 실증" 과제(21RERP-B099826-07)의 지원으로 수행되었습니다.

References

  1. An, S.H., and Kang, K.I. (2005). "A Study on the Cost Model of Underground Parking Lot of Apartment Housing Projects in the Early Stage." Journal of the Architectural Institute of Korea Structure & Construction, JAIK-SC, 21(5), pp. 135-142.
  2. Choi, J.P., Park, Y.S., Ryu, J.W., and Choi, Y.J. (2008). "Case Study of Apartment Remodeling by Occupant's Questionnaire Survey." Journal of the Architectural Institute of Korea Planning & Design, JAIK-PD, 24(5), pp. 31-40.
  3. Choi, J.W., Jeong, E.B., Park, S.P., Kim, T.W., and Lee, C.S. (2019). "Development of Expansion Work Breakdown Structure for Underground Parking Lots in Aged Apartment Housing." Proceedings of the 2019 AIK Conference, Daejeon, KOREA.
  4. Customized Remodeling Item for Aged Apartment (2013). Korea Land and Housing Corporation, LH Research Report, 2013-10.
  5. Han, T.H. (2015). "Evaluating the efficiency and feasibility of parking lot expansion types for remodeling of deteriorated apartment." MS thesis, Seoul National Univ., Seoul.
  6. Han, T.H., and Choi, M.J. (2014). "A Study on the Types and Performance of Parking Space Expansion through Remodeling of Deteriorated Apartment." Proceedings of the 2014 KAHPS Conference, Seoul, KOREA.
  7. Jung, S.J., Kim, J.H., Lee, B.H., Hwang, K.S., and Seo, S.Y. (2018). "Establishment of a Technology for Earthwork Safety at New Construction/Extension of Underground Parking Lot in Building." Proceedings of the 2018 KCI Conference, Pyeongchang, KOREA.
  8. Kim, D.J., Park, C.K., and Kim, H.J. (2012). "A Study on the Expansion for the Parking Lots in Deteriorated Apartments." Journal of the Architectural Institute of Korea Planning & Design, JAIK-PD, 28(2), pp. 159-167. https://doi.org/10.5659/JAIK_PD.2012.28.2.159
  9. Kim, I.G., Kim, H.I., and Lee, S.H. (2009). "A Study on the Factors and Elements Effecting Parking Area Expansion Plans in Apartment Complexes Remodeling." Journal of the Architectural Institute of Korea Structure & Construction, JAIK-SC, 25(6), pp. 51-58.
  10. Kim, J. (2018). "Development of Estimation System for Housing Remodeling Cost through Influence Analysis by Design Elements." MS thesis, Ajou Univ., Kyonggi.
  11. Kim, J., and Cha, H.S. (2018). "Development of Estimation System for Housing Remodeling Cost through Influence Analysis by Design Elements." Korean Journal of Construction Engineering and Management, KICEM, 19(6), pp. 65-78. https://doi.org/10.6106/KJCEM.2018.19.6.065
  12. Kim, K.R. (2002). Modern Architecture Process Management Studies; Gimundang, Korea, pp. 1-256.
  13. Korea Land & Housing Corporation. (2007).
  14. Lee, E.J., Hyun, C.H., and Hyun, C.G. (2010). "A Case Study on the Safety Diagnosis of Daechi hyundai Apartment Remodeling." Journal of the Korea Institute for Structural Maintenance and Inspection, KSMI, 14(5), pp. 35-41.
  15. Lee, J.S., and Bing, C.M. (2012). "Cheongdam Cheonggu Apartment Remodeling Construction." Journal of the Korea Institute of Building Construction, JKIBC, 12(6), pp. 42-51. https://doi.org/10.5345/JKIBC.2012.12.1.042
  16. Lee, K. (2016). "Remodeling and cost." Korea Remodeling Association, pp. 49-51.
  17. Park, J.G. (2009). "Development of Checklist for Expansion of Parking Lot in Aged Apartment." MS thesis, Incheon National Univ., Incheon.
  18. Park, J.G., and Lee, C.S. (2008). "Preliminary Checklist For Vertical Extension of Elevator in Apartment Buildings." Proceedings of the 2008 KICEM Conference, Seoul, KOREA.
  19. Park, S.P., Youn, B.H., Choi, J.W., Kim, T.W., and Lee, C.S. (2018). "Development of Technology Tree for Method of Entry to Expand the Underground Parking Lot of the Apartment." Proceedings of the 2018 KICEM Conference, Seoul, KOREA.
  20. Shin, M.H. (2017). "Selection of the Aged Apartment Parking Lot Expansion Types Considering Economic Feasibility." MS thesis, Incheon National Univ., Incheon.
  21. Song, N.H. (2009). "The Selecting Method of Entry for Apartment in Remodeling an Underground Parking Lot." MS thesis, Incheon National Univ., Incheon.
  22. Song, N.H., Jung, I.S., and Lee, C.S. (2009). "The Development of a Model for Selecting Method of Entry for Apartment in Remodeling an Underground Parking Lot." Korean Journal of Construction Engineering and Management, KICEM, 10(2), pp. 65-74.
  23. Whang, K.J. (2008). "A Decision Making Model for Selection Method of Parking Lot Expansion for the Aged Apartment Complex." Ph-D thesis, Incheon National Univ., Incheon.
  24. Whang, K.J., and Lee, C.S. (2007). "The Development of Procedure Model for Selecting the Method of Parking Lot Expansion in Apartment Complex." Journal of the Architectural Institute of Korea Structure & Construction, JAIK-SC, 23(2), pp. 151-160.
  25. Xing Su, Abdul rahman Andoh, Hubo Cai, Jing Pan, Amr Kandil, and Hisham M. Said. (2012). "Gis-based dynamic construction site material layout evaluation for building renovation projects." Automation in construction, 27, pp. 40-49. https://doi.org/10.1016/j.autcon.2012.04.007
  26. Yoon, B.H. (2019). "Development of the Planning Procedure Model for the Remodeling of the Parking Lot in the Aged Apartment Complex." MS thesis, Incheon National Univ., Incheon.
  27. Yoon, B.H., Choi, J.W., Park, S.P., Kim, T.W., and Lee, C.S. (2019). "A Study on the Functional Analysis of Parking Lot Expansion Technology using Technology-Tree." Korean Journal of Construction Engineering and Management, KICEM, 120(3), pp. 64-76.
  28. Yu, Y.S., and Lee, C.S. (2017). "The Development of Assessment Method for Parking Lot Remodeling Alternative Adopted Asset Management Technique." Korean Journal of Construction Engineering and Management, KICEM, 18(3), pp. 52-62. https://doi.org/10.6106/KJCEM.2017.18.3.052