A Comparative Analysis of Risk Impacts on Cost Overrun between Actual Cases and Managers' Perception on Overseas Construction Projects

해외 프로젝트 시공단계 리스크 요인의 실제 비용 초과 영향과 현장관리자 인식 차이 분석

  • Lee, Kyung-Tae (Department of Architectural Engineering, Hanyang University) ;
  • Ann, Hannah (Department of Civil and Environmental Engineering, University of Illinois at Urbana-Champaign) ;
  • Kim, Jae-Won (Department of Architectural Engineering, Hanyang University) ;
  • Kim, Ju-Hyung (Department of Architectural Engineering, Hanyang University)
  • Received : 2021.02.26
  • Accepted : 2021.03.22
  • Published : 2021.05.31

Abstract

Due to the significant size of overseas construction projects, the cost overrun has enormous impacts on the financial status of construction companies. The managers' appropriate perception and identification of key risk factors in the construction phase notably affect the performance of projects. However, the actual impacts of risk factors and local manager' s perception of them could be deviated. For this reason, we aim to compare the performance of actual cases and general opinions of responsible practitioners in terms of risk factors relevant to cost overruns in order to present a practical strategy for risk management. Firstly, factors classified from literature review were used to simulate 290 cost overruns data sets from 20 cases by introducing Monte-Carlo Simulation and were ranked by standardized coefficients through multiple regression analysis. Secondly, a survey was conducted against 42 local managers to rank their perception of impact on cost overrun with identical factors by using Stepwise Weight Assessment Ratio Analysis (SWARA). Comparison results show that conflicts such as 'conflict with subcontractors' and 'conflict with the local community' have caused excessive cost overrun. However, managers' perception of these as less significant than the actual influences and consider other risks such as 'material price fluctuation' and 'construction quality errors', as relatively serious. Therefore, education for local managers on conflict risks needs to be presented.

국내 시공사의 해외 건설 비중이 증가하면서, 발생하는 리스크로 인한 비용초과는 시공사의 재정 상황에 막대한 영향을 끼친다. 특히, 현지 관리자의 올바른 시공단계의 리스크 인식은 실질적인 관리에 영향을 끼친다. 그러나 실제 사례에서 발생한 리스크 요인의 비용초과 영향도와 현장 관리자의 인식도에는 차이가 있다. 따라서 이 연구는 리스크 관리를 위한 비용초과 대응전략 구축 이전에 해외 건설 시공단계 리스크 요인을 기반으로 실제 사례와 현지관리자의 인식도 비교를 목표로 한다. 우선, 이론고찰을 통해 선별된 리스크 요인을 기반으로 20개 사례에서 발생한 290개의 비용초과 데이터 기반으로 몬테카를로 시뮬레이션을 통해 추가 데이터를 획득한 후, 다중회귀분석으로 얻을 수 있는 표준화계수를 통해 요인별 비용초과 영향도를 구하였다. 또한, 42명의 현지관리자를 대상으로 동일 요인에 대한 인식도 파악을 위해 설문조사 진행 후, SWARA를 활용하여 분석하였다. 두 데이터 비교 결과, '하청업체와의 갈등', '현지 커뮤니티와의 갈등' 등의 갈등 관련 리스크들이 높은 비용초과를 보인다. 그러나 현지관리자들은 이를 낮은 순위로 인식하며, '자재 가격의 변동', '시공 품질 오류' 등에 대해 높은 순위로 인식하고 있었다. 따라서 현지관리자들의 갈등 리스크에 대한 교육과 관심이 필요하다.

Keywords

References

  1. AlGeelani, A., Dabous, S.A., and Venkatachalam, S. (2020). "Investigation of Project Delivery Risks in Public-Private-Partnership (PPP) Infrastructure Projects in UAE-A Stakeholder's Perspective." In 2020 Advances in Science and Engineering Technology International Conferences (ASET), IEEE, pp. 1-5.
  2. Baek, S, Han, S.H., and Jung, W. (2019). "A Comparative Analysis of Risk Assessment Depending on International Project Types." Construction Engineering and Management, 20(5), pp. 125-136.
  3. Balali, A., Moehler, R.C., and Valipour, A. (2020). "Ranking Cost Overrun Factors in the Mega Hospital Construction Projects using Delphi-SWARA Method: An Iranian Case Study." International Journal of Construction Management, pp. 1-9.
  4. Choi, J.W. (2017). "A Study on Relation between Construction Quality and Transaction Price of Apartment, Mh.D. Thesis, Hanyang University.
  5. Chun, Y.J., and Cho, J.H. (2017). "Financial Feasibility Study by Considering Risk Factors for High-Rise Development Project." Construction Engineering and Management, 18(4), pp. 3-16.
  6. Di Maddaloni, F., and Davis, K. (2018). "Project Manager' s Perception of the Local Communities' Stakeholder in Mega Projects." An Empirical Investigation in the UK, International Journal of Project Management, 36(3), pp. 542-565. https://doi.org/10.1016/j.ijproman.2017.11.003
  7. Gupta, V.K., and Thakkar, J.J. (2018). "A Quantitative Risk Assessment Methodology for Construction Project." Sadhana, 43(7), pp. 1-16. https://doi.org/10.1007/s12046-017-0766-x
  8. Jang, H.S. (2018). "Domestic Companies' Plan to Enter the ASEAN Construction Market: focusing on PPP projects." Construction Engineering and Management, 19(5), pp. 16-18.
  9. Jung, W., and Han, S.H. (2017). "Successful Winning Award Factors in Early Stage of International Public Private Partnership Projects." Construction Engineering and Management, 18(3), pp. 84-94.
  10. Kang, S., and Kim, S.C. (2016). "A Study on Composition and Application of Risk Management Planning and Procedure for Successful Overseas Construction Projects -Based on the PRINCE2 Methodology in the UK-." Construction Engineering and Management, 17(1), pp. 48-55.
  11. Kang, S.W., Kim, D.H., and Kim, K.T. (2018). "Cost Overrun in Construction of Railway Infrastructure: Causes & Implications." Journal of the Korean Society for Railway, 22(11), pp. 905-912. https://doi.org/10.7782/JKSR.2019.22.11.905
  12. Kersuliene, V., Zavadskas, E.K., and Turskis, Z. (2010). "Selection of Rational Dispute Resolution Method by Applying New Stepwise Weight Assessment Ratio Analysis (SWARA)." Journal of business economics and management, 11(2), pp. 243-258. https://doi.org/10.3846/jbem.2010.12
  13. Kim, D. Kim, H., and Jang, H. (2018). "An Analysis of the Casual Relations on Construction Project Managers Level Competency." Journal of the Architectural Institute of Korea Structure & Construction, 34(3), pp. 77-86. https://doi.org/10.5659/JAIK_SC.2018.34.3.77
  14. NezihTayyar, M.D. (2017). Comparison of Max100, SWARA and Pairwise Weight Elicitation Methods.
  15. Radovic, D., and Stevic, Z. (2018). "Evaluation and Selection of KPI in Transport Using SWARA Method." Transport & Logistics: The International Journal, 8(44), pp. 60-68.
  16. Rathi, A.S., and Khandve, P.V. (2014). "Study of Factors Influencing Cost Overruns: An Overview." International Journal of Science and Research, 5, p. 334.
  17. Safapour, E., Kermanshachi, S., Kamalirad, S., and Tran, D. (2019). "Identifying Effective Project-based Communication Indicators within Primary and Secondary Stakeholders in Construction Projects." Journal of Legal Affairs and Dispute Resolution in Engineering and Construction, 11(4), 04519028. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000332
  18. Sinesilassie, E.G., Tabish, S.Z.S., and Jha, K.N. (2018). "Critical Factors Affecting Cost Performance: A Case of Ethiopian Public Construction Projects." International Journal of Construction Management, 18(2), pp. 108-119. https://doi.org/10.1080/15623599.2016.1277058
  19. Ullah, K., Abdullah, A.H., and Nagapan, S. (2016). "A Framework for Avoiding Cost Overruns in Malaysian Construction Projects." International Journal of Advanced and Applied Sciences, 3(3), pp. 28-31.
  20. Valipour, A., Yahaya, N., Md Noor, N., Antucheviciene, J., and Tamosaitiene, J. (2017). "Hybrid SWARA-COPRAS Method for Risk Assessment in Deep Foundation Excavation Project: An Iranian Case Study." Journal of Civil Engineering and Management, 23(4), pp. 524-532. https://doi.org/10.3846/13923730.2017.1281842
  21. Van der Linden, S. (2014). "On the Relationship between Personal Experience, Affect and Risk Perception: The Case of Climate Change." European Journal of Social Psychology, 44(5), pp. 430-440. https://doi.org/10.1002/ejsp.2008
  22. Wang, C.M., Xu, B.B., Zhang, S.J., and Chen, Y.Q. (2016). "Influence of Personality and Risk Propensity on Risk Perception of Chinese Construction Project Managers." International Journal of Project Management, 34(7), pp. 1294-1304. https://doi.org/10.1016/j.ijproman.2016.07.004
  23. Yu, W.S. (2014). "Enhancement of Domestic Construction Companies' Risk Management Capabilities for Overseas Projects." Construction Engineering and Management, 15(5), pp. 27-30.
  24. Zolfani, S.H., Yazdani, M., and Zavadskas, E.K. (2018). "An Extended Stepwise Weight Assessment Ratio Analysis (SWARA) Method for Improving Criteria Prioritization Process." Soft Computing, 22(22), pp. 7399-7405. https://doi.org/10.1007/s00500-018-3092-2