A Comparative Analysis of Risk Impacts on Cost Overrun between Actual Cases and Managers' Perception on Overseas Construction Projects  

Lee, Kyung-Tae (Department of Architectural Engineering, Hanyang University)
Ann, Hannah (Department of Civil and Environmental Engineering, University of Illinois at Urbana-Champaign)
Kim, Jae-Won (Department of Architectural Engineering, Hanyang University)
Kim, Ju-Hyung (Department of Architectural Engineering, Hanyang University)
Publication Information
Korean Journal of Construction Engineering and Management / v.22, no.3, 2021 , pp. 52-60 More about this Journal
Abstract
Due to the significant size of overseas construction projects, the cost overrun has enormous impacts on the financial status of construction companies. The managers' appropriate perception and identification of key risk factors in the construction phase notably affect the performance of projects. However, the actual impacts of risk factors and local manager' s perception of them could be deviated. For this reason, we aim to compare the performance of actual cases and general opinions of responsible practitioners in terms of risk factors relevant to cost overruns in order to present a practical strategy for risk management. Firstly, factors classified from literature review were used to simulate 290 cost overruns data sets from 20 cases by introducing Monte-Carlo Simulation and were ranked by standardized coefficients through multiple regression analysis. Secondly, a survey was conducted against 42 local managers to rank their perception of impact on cost overrun with identical factors by using Stepwise Weight Assessment Ratio Analysis (SWARA). Comparison results show that conflicts such as 'conflict with subcontractors' and 'conflict with the local community' have caused excessive cost overrun. However, managers' perception of these as less significant than the actual influences and consider other risks such as 'material price fluctuation' and 'construction quality errors', as relatively serious. Therefore, education for local managers on conflict risks needs to be presented.
Keywords
Risk Perception; Cost Overrun; Standardized Coefficient; Monte-Carlo Simulation; SWARA;
Citations & Related Records
연도 인용수 순위
  • Reference
1 Baek, S, Han, S.H., and Jung, W. (2019). "A Comparative Analysis of Risk Assessment Depending on International Project Types." Construction Engineering and Management, 20(5), pp. 125-136.
2 Balali, A., Moehler, R.C., and Valipour, A. (2020). "Ranking Cost Overrun Factors in the Mega Hospital Construction Projects using Delphi-SWARA Method: An Iranian Case Study." International Journal of Construction Management, pp. 1-9.
3 Choi, J.W. (2017). "A Study on Relation between Construction Quality and Transaction Price of Apartment, Mh.D. Thesis, Hanyang University.
4 Chun, Y.J., and Cho, J.H. (2017). "Financial Feasibility Study by Considering Risk Factors for High-Rise Development Project." Construction Engineering and Management, 18(4), pp. 3-16.
5 Gupta, V.K., and Thakkar, J.J. (2018). "A Quantitative Risk Assessment Methodology for Construction Project." Sadhana, 43(7), pp. 1-16.   DOI
6 Jang, H.S. (2018). "Domestic Companies' Plan to Enter the ASEAN Construction Market: focusing on PPP projects." Construction Engineering and Management, 19(5), pp. 16-18.
7 Jung, W., and Han, S.H. (2017). "Successful Winning Award Factors in Early Stage of International Public Private Partnership Projects." Construction Engineering and Management, 18(3), pp. 84-94.
8 Kang, S., and Kim, S.C. (2016). "A Study on Composition and Application of Risk Management Planning and Procedure for Successful Overseas Construction Projects -Based on the PRINCE2 Methodology in the UK-." Construction Engineering and Management, 17(1), pp. 48-55.
9 Di Maddaloni, F., and Davis, K. (2018). "Project Manager' s Perception of the Local Communities' Stakeholder in Mega Projects." An Empirical Investigation in the UK, International Journal of Project Management, 36(3), pp. 542-565.   DOI
10 Valipour, A., Yahaya, N., Md Noor, N., Antucheviciene, J., and Tamosaitiene, J. (2017). "Hybrid SWARA-COPRAS Method for Risk Assessment in Deep Foundation Excavation Project: An Iranian Case Study." Journal of Civil Engineering and Management, 23(4), pp. 524-532.   DOI
11 Kang, S.W., Kim, D.H., and Kim, K.T. (2018). "Cost Overrun in Construction of Railway Infrastructure: Causes & Implications." Journal of the Korean Society for Railway, 22(11), pp. 905-912.   DOI
12 Van der Linden, S. (2014). "On the Relationship between Personal Experience, Affect and Risk Perception: The Case of Climate Change." European Journal of Social Psychology, 44(5), pp. 430-440.   DOI
13 Sinesilassie, E.G., Tabish, S.Z.S., and Jha, K.N. (2018). "Critical Factors Affecting Cost Performance: A Case of Ethiopian Public Construction Projects." International Journal of Construction Management, 18(2), pp. 108-119.   DOI
14 Kersuliene, V., Zavadskas, E.K., and Turskis, Z. (2010). "Selection of Rational Dispute Resolution Method by Applying New Stepwise Weight Assessment Ratio Analysis (SWARA)." Journal of business economics and management, 11(2), pp. 243-258.   DOI
15 Kim, D. Kim, H., and Jang, H. (2018). "An Analysis of the Casual Relations on Construction Project Managers Level Competency." Journal of the Architectural Institute of Korea Structure & Construction, 34(3), pp. 77-86.   DOI
16 NezihTayyar, M.D. (2017). Comparison of Max100, SWARA and Pairwise Weight Elicitation Methods.
17 Rathi, A.S., and Khandve, P.V. (2014). "Study of Factors Influencing Cost Overruns: An Overview." International Journal of Science and Research, 5, p. 334.
18 Safapour, E., Kermanshachi, S., Kamalirad, S., and Tran, D. (2019). "Identifying Effective Project-based Communication Indicators within Primary and Secondary Stakeholders in Construction Projects." Journal of Legal Affairs and Dispute Resolution in Engineering and Construction, 11(4), 04519028.   DOI
19 Radovic, D., and Stevic, Z. (2018). "Evaluation and Selection of KPI in Transport Using SWARA Method." Transport & Logistics: The International Journal, 8(44), pp. 60-68.
20 Ullah, K., Abdullah, A.H., and Nagapan, S. (2016). "A Framework for Avoiding Cost Overruns in Malaysian Construction Projects." International Journal of Advanced and Applied Sciences, 3(3), pp. 28-31.
21 AlGeelani, A., Dabous, S.A., and Venkatachalam, S. (2020). "Investigation of Project Delivery Risks in Public-Private-Partnership (PPP) Infrastructure Projects in UAE-A Stakeholder's Perspective." In 2020 Advances in Science and Engineering Technology International Conferences (ASET), IEEE, pp. 1-5.
22 Wang, C.M., Xu, B.B., Zhang, S.J., and Chen, Y.Q. (2016). "Influence of Personality and Risk Propensity on Risk Perception of Chinese Construction Project Managers." International Journal of Project Management, 34(7), pp. 1294-1304.   DOI
23 Yu, W.S. (2014). "Enhancement of Domestic Construction Companies' Risk Management Capabilities for Overseas Projects." Construction Engineering and Management, 15(5), pp. 27-30.
24 Zolfani, S.H., Yazdani, M., and Zavadskas, E.K. (2018). "An Extended Stepwise Weight Assessment Ratio Analysis (SWARA) Method for Improving Criteria Prioritization Process." Soft Computing, 22(22), pp. 7399-7405.   DOI