Development of Construction Cost Estimation Model for Elementary, Middle and High School Facilities

초·중·고등학교 시설물별 추정공사비 산정모델 개발

  • Jung, Eui-Hyun (Department of Architectural Engineering, Inha University) ;
  • Yeom, Dong-Jun (Department of Construction Policy Research, Korea Institute of Civil Engineering and Building Technology) ;
  • Kim, Jun-Sang (Department of Architectural Engineering, Inha University) ;
  • Kim, Young Suk (Department of Architectural Engineering, Inha University)
  • 정의현 (인하대학교 건축공학과) ;
  • 염동준 (한국건설기술연구원 건설정책연구소) ;
  • 김준상 (인하대학교 건축공학과) ;
  • 김영석 (인하대학교 건축공학과)
  • Received : 2021.04.27
  • Accepted : 2021.05.04
  • Published : 2021.05.31

Abstract

Estimated construction cost is an important index to secure an optimal budget which needs to go into construction projects in the previous of basic design phase. In order for public institutions to calculate the estimated construction cost, the cost per unit area of public buildings is used. However, the current calculation method of the estimated construction cost in public buildings is impossible to reflect the characteristics of many facilities and combinations. The purpose of this study is to develop an estimation model in the previous of basic design phase for the elementary, middle and high school facilities. it is expected that it is possible to estimate the construction cost of the elementary, middle and high schools in a reasonable and reliable manner through the estimation model developed in this study.

추정공사비는 기본설계 이전단계에서 건설사업에 투입되어야 하는 적정 예산의 확보를 위해 산정되는 중요한 건설공사비 지표이다. 여러 공공기관에서는 추정공사비를 산정하기 위해 공공건축물 세부 유형별 단위면적당 공사비를 도출하고, 이를 해당 건축물의 연면적에 곱하는 방식을 사용하고 있다. 그러나 일부 공공건축물들은 그 시설물의 구성 및 조합이 다양하여 세부 유형별로 단위면적당 공사비를 산정하는 획일화된 현행 추정공사비 산정방법으로는 공공건축물 내 여러 시설물 조합에 따른 특성을 반영할 수 없어 신뢰성 있는 추정공사비를 산정하는데 한계성을 지니고 있는 것으로 조사 및 분석되었다. 본 연구의 목적은 발주 빈도수 및 누적사업비용의 규모가 크고 시설물의 구성 및 종류가 다양한 초·중·고등학교를 대상으로, 시설물 조합에 따른 추정공사비 산정방안을 제시하는 것이다. 본 연구에서 개발한 초·중·고등학교 시설물별 추정공사비 산정모델 및 분석 방법론을 실무에 적용할 경우 공공발주자는 보다 합리적이고도 신뢰성 있는 초·중·고등학교의 추정공사비 산정이 가능할 것으로 기대된다.

Keywords

Acknowledgement

This work was supported by the National Research Foundation of Korea (NRF) grant funded by the Korea government. (MSIT) (2020R1A2C2008616)

References

  1. Durbin, J., and Watson, G.S. (1950). "Testing for Serial Correlation in Least Squares Regression. 1." Biometrika, 37(3-4). pp. 409-428. https://doi.org/10.2307/2332391
  2. Hegazy, T., and Moselhi, O. (1994). "Analogy-Based Solution to Markup Estimation Problem." ASCE Journal of Computing Civil Engineering, 8(1). pp. 72-87. https://doi.org/10.1061/(ASCE)0887-3801(1994)8:1(72)
  3. Kang, S.D. (2003). "A Study on the Prediction of Construction Costs by Regression Analysis by Building Areas in the Early Planning Stage." Master's thesis, Yeungnam University.
  4. Kang, S.H. (2010). "A study on the estimation of the cost of the bridge construction." Doctoral dissertation, Korea Maritime University.
  5. Kim, K.H., An, S.H., and Cho, H.G. (2006). "Comparison of the Accuracy between Cost Prediction Models based on Neural Network and Genetic Algorithm." Journal of the Architectural Institute of Korea Structure & Construction, 22(3), pp. 111-118.
  6. Kim, S.K. (2008). "A study on the analysis and estimation of construction cost by using artificial neural network in the BTL project for educational facilities." Master's thesis, Hongik University.
  7. Kim, J.W. (2011). "A study on construction cost estimation model of educational facilities using regression analysis : for the BTL project in the Gyeonggi-do region." Master's thesis, Hanyang University.
  8. KICT (Korea Institute of Civil Engineering and Building Technology) (2019). Construction cost index in September 2019.
  9. Lee, K.H. (2014). Statistical Analysis using SPSS, Freeaca Press, Korea.
  10. Lim, S.Y. (2010). "A study on improving the estimation accuracy of apartment project cost." Master's thesis, Jeonnam university.
  11. MOLIT (Ministry of Land, Infrastructure and Transport) (2018). Standards for reviewing the management methods of construction projects and guidelines for performance of duties.
  12. MOEF (Ministry of Strategy and Finance) (2018). Guidelines for managing total business expenses.
  13. Park. S.H. (2011). "Judgement Model for Construction Cost Appropriateness of Multi-Family Housing Projects in Planning Phase." Master's thesis, Seoul City University.
  14. PPS (Public Procurement Service) (2017). Analysis of construction costs by type of public buildings in 2017.