Systematic Improvement for Effective Operation of Long-Term Continuous Construction Contracts

장기계속공사계약의 효율적 운영을 위한 제도 개선

  • Cho, Youngjun (School of Architect and Civil Engineer, Joongbu University)
  • 조영준 (중부대학교 건축토목공학부)
  • Received : 2019.01.21
  • Accepted : 2019.02.15
  • Published : 2019.11.30

Abstract

The entire duration of the long-term continuous construction contract project cannot be expected when calculating the initial budget as the construction of the contract is carried out annually according to the budget composition. In addition, the statutes related to the defect liability and execution of contracts have not been established systematically in relation to the contract. Therefore, there are many problems at the actual construction site with regard to the defect liability or the performance of the contract in relation to the contract. In this study, the following improvement directions were presented for the efficient operation of the contracts: First, the defect liability is legal and should be specified in an Act rather than an enforcement decree. Second, if the parties to the contract vary in the following order in the contract, the special agreement should be specified in the enforcement decree. Third, in the event of an indirect cost due to the extension of the period of the long-term continuous work, the contingency items of the total project cost management policy should be utilized. Fourth, in the case of general construction contract conditions, clauses related to the purchase of the premium of the CAR, inspection, taking over, defect repair, and defect inspection shall be supplemented.

수년에 걸쳐 장기적으로 사업을 추진해야 하는 대형건설공사를 위해서는 단년도에 편성된 예산의 한도내에서 공사를 차수별로 계약체결하는 장기계속공사계약과 전체공사에 대한 예산을 편성해 두고 연차적으로 집행해 나가는 계속비사업계약이 있다. 장기계속공사계약의 경우 매년도 예산편성에 따라 공사를 진행하게 되므로 최초 예산을 산출할 때 전체 사업기간을 예상할 수 없다. 또한 장기계속공사계약과 관련해서는 하자책임과 관련된 법령, 계약이행과 관련된 법령이 체계적으로 정립되어 있지 못하고 있다. 그러므로 실제 건설현장에서는 장기계속공사계약과 관련하여 하자책임이나 계약의 이행과 관련하여 많은 문제점이 발생되고 있다. 이에 본 연구에서는 장기계속공사계약의 효율적인 운영을 위해 다음과 같은 개선방향을 제시하였다. 첫째, 하자담보책임은 법적책임이므로 시행령이 아닌 법에 명시하여야 한다. 둘째, 장기계속공사에서 차수별 계약당사자가 달라질 경우 시행령에서 특약을 정할 수 있도록 명시해야 한다. 셋째, 장기계속공사의 공기연장으로 인한 간접비가 발생될 경우 총사업비관리지침의 예비비항목을 활용할 수 있도록 해야 한다. 넷째, 공사계약일반조건의 경우 손해보험의 가입, 검사, 인수, 하자보수 및 하자검사와 관련된 조항을 보완해야 한다.

Keywords

References

  1. Cho, Y.J., and Hyun, C.T. (2001). "A Study on the Contractor's Liability for Defect in Public Construction Project." Korean Journal of Construction Engineering and Management, KICEM, 2(4), pp. 69-80.
  2. Cho, Y.J., and Hyun, C.T. (2003). "A Study on the Characteristics of Contractor's Defects Liability in Construction Works." Journal of the Architectural Institute of Korea Structure & Construction, AIK, 19(11), pp. 155-163.
  3. Cho, Y.J., and Lee, S.B. (2005). "A Study on the Reformation of the Contract Time Extension Process in the Public Construction projects." Korean Journal of Construction Engineering and Management, KICEM, 6(3), pp. 1-9.
  4. Database of Decision against Payment of Construction Cost (2014da235189) [Internet]. Seoul(Korea): Supreme Court; 2018[cited 2019 Jan. 19]. Available from:http://glaw.scourt.go.kr.
  5. Database of Decision against Defect Liability of Long Term Continuing Contracts (2003da19275). [Internet]. Seoul(Korea): Supreme Court; 2014[cited 2019 Jan. 19]. Available from:http://glaw.scourt.go.kr.
  6. Jeong, K.C., Lee, J.S., and Park, Y.H. (2005). "Study on introduction of 'Pre-Agreement system for Additional Incidental Cost' related to construction time extension." Korean Journal of Construction Engineering and Management, KICEM, 13(6), pp. 33-44. https://doi.org/10.6106/KJCEM.2012.13.6.033
  7. Jeong, K.C., and Lee, J.S. (2017). "Improvement of the Calculation Standard for Prolongation cost of Long-term Continuing Contracts Construction Project." Korean Journal of Construction Engineering and Management, KICEM, 18(2), pp. 30-37. https://doi.org/10.6106/KJCEM.2017.18.2.030
  8. Jeong, K.C., and Lee, J.S. (2018). "Application of Accrual Basis for Calculation of Prolongation Cost in Construction Projects." Korean Journal of Construction Engineering and Management, KICEM, 19(5), pp. 111-120. https://doi.org/10.6106/KJCEM.2018.19.5.111
  9. Kim, Y.J., Kim, T.K., Jo, D.S., and Lee, H.K. (2015). "A Study on Substantial Methodology for Extension of Time in International Mega-Project Claims." Korean Journal of Construction Engineering and Management, KICEM, 16(3), pp. 165-176. https://doi.org/10.6106/KJCEM.2015.16.3.165
  10. Lee, J.S. (1999). "Criteria and conditions of compensation claims for delay in construction period." Issue Focus (55), (Sep. 1999), pp. 9-13.