DOI QR코드

DOI QR Code

Structure and Construction Technology Analysis about Construction Sequence Change for Superstructure Construction Period Reduction in Top-down Method

역타공법 중심의 골조 공기단축을 위한 시공시퀀스 변경에 따른 구조해석 및 요소기술 분석

  • 박용현 (고려대 건축사회환경공학과 대학원) ;
  • 주영규 (고려대 건축사회환경공학과)
  • Received : 2019.03.19
  • Accepted : 2019.05.21
  • Published : 2019.06.30

Abstract

The purpose of this study is to improve a general Top-Down construction process for superstructure construction period reduction. In a general Top-Down construction sequence, the ground floor slab is set up first. Subsequently, 1st basement level construction including core walls is constructed. Initiation of the ground level superstructure gets waited until then. In this study, removable deck plate installation on the bottom of the core walls of ground level is preceding the concrete casting, therefore, ground level superstructure construction is able to get started earlier. Up to first typical floor concrete casting, total of seventy-two working(calendar) days will be resulted in a reduction from the total construction periods.

Keywords

Acknowledgement

Supported by : 한국연구재단

References

  1. Ock, J. H. (1998). Shortening Construction Duration : A Comparison of the Double-Up Construction Method to the Top-down and the Bottom-up Method, Journal of the Architectural Institute of Korea, Structure Section, 1998.12. v14(12), p.137-144
  2. Rhim, H. C., Song, J. Y., & Seo, J. H. (2008). Study on the Application of Top-Down Construction Method utilizing Opened Slab, Journal of the Architectural Institute of Korea, Structure Section, 2008.10. v24(10), p.179-186
  3. Kim, S. W. (2008). The birth and development of top down method, the Expert column of MIDASIT Co. Ltd., 1-10. Retrieved March 2, 2019, from http://www.newtechstructure.com
  4. Sho, K. H., & Yang, K. Y. (2009). Study on the Application of Double-up Method for Framework, Journal of the Architectural Institute of Korea, Structure Section, 2009.9. v25(9), p.191-198
  5. Kim, K. J., Lee, J. B., & Hwang, Y. H. (2013). A Case Study on RC Core Wall Supported Temporary by H-Shaped Steel Column for Top-Down Construction, Journal of the Korea Concrete Institute, 2013.3, Vol.25(2), p.45-48 https://doi.org/10.4334/JKCI.2013.25.1.045
  6. Lee, I. J., & Lee, W. H. (2014). Downward Method of Underground Structure, Journal of the Architectural Institute of Korea, Spring techanical Conference, 2014.4. v34(1), p.347-348
  7. Architectural Institute of Korea (2016). Korea Building Code and Commentary, kimoondang, p.108-186
  8. Kim, B. S., Kim, G. S., Kim, O. K., & Bang, H. S. (2017). Comparative Study Between S.P.S Top Down Method and UP-UP Method in be based on the Schedule Simulation, Journal of the Architectural Institute of Korea, Spring techanical Conference, 2017.4. v37(1), p.205-206
  9. Lee, J. B. (2018). Application of the Up-Up Method to a Site Using the Top-Down Method for Shortening Construction Period, [master's thesis], Daegu Univertsity; 2017.12. 94p
  10. Jeong, D. M., Lee, J. H., Lee, D. H., & Ju, Y. K. (2019). Rapid Structural Safety Evaluation Method of Buildings using Unmanned Aerial Vehicle (SMART SKY EYE), Journal of the Architectural Institute of Korea, Structure Section, 2019.2. v35(2), p.3-11