역타공법 중심의 골조 공기단축을 위한 시공시퀀스 변경에 따른 구조해석 및 요소기술 분석 (Structure and Construction Technology Analysis about Construction Sequence Change for Superstructure Construction Period Reduction in Top-down Method)

  • 박용현;주영규
    • 대한건축학회논문집:구조계
    • /
    • 제35권6호
    • /
    • pp.101-109
    • /
    • 2019
  • The purpose of this study is to improve a general Top-Down construction process for superstructure construction period reduction. In a general Top-Down construction sequence, the ground floor slab is set up first. Subsequently, 1st basement level construction including core walls is constructed. Initiation of the ground level superstructure gets waited until then. In this study, removable deck plate installation on the bottom of the core walls of ground level is preceding the concrete casting, therefore, ground level superstructure construction is able to get started earlier. Up to first typical floor concrete casting, total of seventy-two working(calendar) days will be resulted in a reduction from the total construction periods.