Abstract

Since its adoption by the transportation sector in the early 1990s, partnering has been broadly used with the traditional delivery method by many agencies with significant reported benefits. During the same era, a number of transportation agencies (DOTs) started experimenting with a wide variety of alternative project delivery methods (APDMs) aimed at improving the delivery of highway construction projects. The effect of collaborative working strategies such as partnering, together with the APDMs have become somehow interrelated posing a potential challenge on how to effectively integrate partnering as a concept in the APDMs. The salient question has been if the collaborative nature of these APDMs has affected how partnering is being used by state DOTs. Through an extensive literature review, analysis of 32 CMGC RFPs/RFQs and review of three CMGC case studies, the study found that there is limited information in state DOT documents that show procedures on the usage of partnering with CMGC projects. Majority of DOTs are relying on the inherent nature of the CMGC contract to promote healthy collaborative practices and there is the need to consider partnering during preconstruction and construction separately to cater for any personnel change over. The study also revealed that partnering may become less important at the construction phase due to overlap between partnering and CMGC practices. In support of this finding, a CMGC partnering model was developed that can be adopted by DOTs. This paper contributes to both research and practice by expanding the existing knowledge on partnering on APDMs.

Keywords

References

  1. AASHTO, AASHTO Partnering Handbook 2nd edition. Washington, DC: American Association of State Highway and Transportation Officials (AASHTO), 2018.
  2. Abudayyeh, O., Partnering: A Team Building Approach to Quality Construction Management. Journal of Management in Engineering, doi:10.1061/(ASCE)9742-597X(1994), vol. 10, no. 6(26), pp. 50-62, 1994
  3. Bayliss, R., Cheung, S.-O., Suen, H., and Wong, S.-P., Effective Partnering Tools in Construction: A Case Study on MTRC TKE Contract 604 in Hong Kong. International Journal of Project Management, doi:10.1016/S0263-7863(03)00069-3, vol. 22, pp. 253-263, 2004.
  4. Brown, D. K., ODOT Partnering Handbook. Grand Rapids, OH: Ohio Department of Transportation. Retrieved from 2000, http://www.dot.state.oh.us/Divisions/ConstructionMgt/Admin/Partnering/handbook.pdf, (May 4, 2019).
  5. Ellicott, M. and Grajek, K., Best Value Contracting Criteria. Cost Engineering, AACE, pp. 31-34, 1997.
  6. Ernzen, J., Murdough, G., and Drecksel, D., Partnering on a design-build project: Making the three-way love affair work. Ransportation Research Record: Journal of the Transportation Research Board, 1712, pp. 202-211, 2000. https://doi.org/10.3141/1712-24
  7. Federal Highway Adminstration, Federal Highway Adminstration. Retrieved from Special experimental projects no.14 - Alternative contracting (formerly innovative contracting): https://www.fhwa.dot.gov/programadmin/contracts/sep_a.cfm (May 14, 2019).
  8. FHWA. Design-Build Effectiveness Study. Retrieved from USDOT - Federal Highway Authority: January, 2006, https://www.fhwa.dot.gov/reports/designbuild/designbuild.htm, (July 21, 2018)
  9. FHWA. Construction Manager/ General Contractor, Retrieved from USDOT-Federal Highway Administration: 2017, https://www.fhwa.dot.gov/innovation/everydaycounts/edc-2/pdfs/edc_cm_gm.pdf, (July 20, 2018).
  10. FHWA. Construction Manager/General Contractor (CM/GC), Retrieved from USDOT-Federal Highway Administration: (June 6, 2017), https://www.fhwa.dot.gov/construction/contracts/acm/cmgc.cfm, (July 20, 2018).
  11. FHWA. Construction Program Guide: Construction Manager/General Contractor Project Delivery. Retrieved from U.S. Department of Transportation: Federal Highway Administration: https://www.fhwa.dot.gov/construction/cqit/cm.cfm, (June 27, 2017).
  12. Gransberg, D. and Shane, J., Construction Manager-at-Risk Project Delivery for Highway Programs. Washington, D.C.: National Cooperative Highway Research Program, 2010.
  13. Gransberg, D. and Shane, J., Defining Best Value for Construction Manager/General Contractor Projects: The CMGC Learning Curve. Journal of Management in Engineering, doi:10.1061/(ASCE)ME.1943-5479.0000275, vol. 31, no. 4, 2015.
  14. Gransberg, D., Dillion, W., Reynolds, L., and Boyd, J., Quantitative Analysis of Partnered Project Performance. Journal of Construction Engineering and Management, pp. 161-166, 1999.
  15. Hancher, D. and Haggard, R., In Search of Partnering Excellence. Austin, Tx: Construction Industry Institute, 1991.
  16. Hannon, J. and Zhang, F., A New Methodology for Partnering Transportation Projects. Advances in Human Factors, Sustainable Urban Planning and Infrastructure. AHFE 2017. Advances in Intelligent Systems and Computing. Springer, Cham, pp. 318-325, 2017.
  17. Kereri, J. O., A comparison of project party relationships in design-bid-build and design-build project delivery methods. Journal of Architecture, Engineering and Construction, vol. 6, no. 4, pp. 26-32, 2017.
  18. Kereri, J. O. and Harper, C. M., Intangible attaributes of partnering: A case study analysis . Annual meeting of the Transportation Research Board (TRB). Washington, DC: Transportation Research Board, 2019.
  19. Minnesota Department of Transportation. Minnesota Department of Ttansportation. Retrieved from Hwy 43 Bridge: www.dot.state.mn.us/winonabridge/work-package5-costs.html, (July 19, 2019).
  20. Murdough, G., Drecksel, D., Sharp, G., and Ernzen, J., Performance in the Project Trailer: A Partnering Evaluation Tool. Transportation Research Record: Journal of the Transportation Research Board, 1994, pp. 26-34, 2007. https://doi.org/10.3141/1994-04
  21. Opie, B., Webb, L., and Dudzik, D., Partnering Process Survey Report 2016. Phoenix: Arizona Department of Transportation. Retrieved , from 2016, https://www.azdot.gov/docs/default-source/partnering/partnering-processsurvey-report-2016.pdf?sfvrsn=2, (July 28, 2018).
  22. Rogge, D., Griffith, D., and Hutchins, W., Improving the Effectiveness of Partnering. Salem, Oregon: Oregon Department of Transportation, 2002.
  23. Schierholz, J., Gransberg, D., and McMinimee, J., enefits and Challenges of Implementing Construction Manager/General Contractor Project Delivery: The View from the Field. Transportation Research Board 91st Annual Meeting. Washibgton, DC: The National Academics of Sciences, Engineering and Medicine, pp. 50-62, 2012.
  24. Warne, T., Partnering for Success. New York, NY: American Society of Civil Engineers, 1994.
  25. West, N., Gransberg, D., and McMinimee, J., Effective Tools for Projects Delivered by Construction Manager-General Contractor Method. Journal of the Transportation Research Board, 2268, 2015.