Barriers of CM Performance during Pre-Construction Stages in Private CM Projects

민간 CM사업 시공이전단계 CM성과 저해요인 분석

  • Han, Jae Hoon (Department of Architecture, Graduate School of Engineering, Sejong University) ;
  • Kim, Han Soo (Department of Architecture, Sejong University)
  • Received : 2017.03.02
  • Accepted : 2017.06.02
  • Published : 2017.07.31

Abstract

The sustainable growth of Construction Management(CM) market depends on clients'acceptance from positive project outcomes of CM services. Achieving the positive outcomes requires CM firms'competency and efforts. Equally, it is critical to understand and overcome barriers of CM performance, which cause inefficiencies and under-performance of CM services. The objective of the study is to identify and discuss the barriers of CM performance during pre-construction stages in private CM projects based on the FMEA technique. Major findings basically suggest that clients and CM firms have roles to play, individually and collaboratively, in order to improve CM performance by eliminating performance barriers.

CM시장의 지속적인 발전은 CM성과에 대한 발주자의 수용을 전제로 하고 있으며, 이는 CM성과 향상을 위한 CM기업의 역량과 노력을 요구한다. 이를 위해서는 CM성과 향상을 저해하는 요인을 이해하고 이를 극복하기 위한 노력이 전제되어야 한다. 본 연구의 목적은 FMEA(Failure Mode and Effect Analysis)기법을 활용하여 민간 CM사업의 시공이전단계를 중심으로 CM성과 저해요인을 발굴하여 주요 특징을 분석하고 시사점을 제시하는데 있다. 본 연구를 통해 도출된 주요 결과는 CM성과 저해요인 해소를 통한 CM성과 향상을 위해서는 발주자와 CM사업자의 개별적인 노력과 협력적인 노력이 함께 경주되어야 한다는 것을 시사하고 있다.

Keywords

References

  1. Ahn, E. J. (2008). "A suggest on the need of measuring the performance of a construction management project integrated viewpoints of project participants: focusing on owner, construction manager, designer and constructor" MS thesis, Hanyang University, Korea.
  2. Ahn, E. J., Yoo, B. G., Lee, Y. S. and Kim, J. J. (2008). "Measuring of the Performance of a Construction Management Project from Viewpoints of Project Participants -Focusing on Owner, Construction Manager, Designer and Constructor-" Korean Journal of Construction Engineering and Management, KICEM, 9(3), pp. 194-205.
  3. Cho, H. K. and Kim, H. S. (2010). "Level of Use of Construction Management Services in Private Building Projects during Pre-construction Stages" Korean Journal of Construction Engineering and Management, KICEM, 11(5), pp. 15-23. https://doi.org/10.6106/KJCEM.2010.11.5.15
  4. Go, Y, J. (2011). "Selecting Optimum Management Methods in Pre-Construction Phase considering Project Characteristics -Focused on Improving Project Performance-" Master's Thesis, Ajou University, Korea.
  5. Ha, J. S. (2015). "Strengthen CM capabilities for overseas markets" (Apr, 03, 2015).
  6. Hong, C. U., Park D. Y. and Kim J. J. (2010). "A Study on the Check-List of the Performance of the Construction Management" Journal of the Architectural Institute of Korea Planning & Design, AIK, 30(1), pp. 181-182. https://doi.org/10.5659/JAIK_PD.2014.30.1.181
  7. Hong, S. S., Kim, K. R., Shin, D. W. and Cha, H. S. (2006) "Development of Web-Based Performance Measurement System for Construction Companies" Journal of the Architectural Institute of Korea Structure & Construction, AIK, 30(8), pp. 63-70. https://doi.org/10.5659/JAIK_SC.2014.30.8.63
  8. Hong, Y. T., Yu, J. H., Lim, G. H. and Lee, H. S. (2004 ). "Evaluation of Time-Affecting Factors in High- Rise Building Construction Using FMEA" Journal of the Architectural Institute of Korea Structure & Construction, AIK, 20(10), pp. 183-192.
  9. Kim, J. H. and Kim, H. S. (2001). "A preliminary study on barriers to the application of the CM delivery system to public works: from CM service provider's perspectives" Journal of the Architectural Institute of Korea Structure & Construction, AIK, 21(1), pp. 533-536.
  10. Kim, Y. S. and Cho W. C. (2002). "A Study on Development of Failure Mode and Effect Analysis for Construction Business" Journal of the Korean Society of Civil Engineers, KSCE, (3-6), pp. 1954-1957.
  11. Kim, K. K. (2006). "A Study for Major Cost-Increasing Factors in Skyscraper Construction Using FMEA" MS thesis, Sejong University, Korea.
  12. Kim, D. H. and Kim, H. S. (2011). "Characteristics of Construction Managers' Roles from the Perspective of Leader's Roles. -Focused on Design Stages-" Korean Journal of Construction Engineering and Management, KICEM, 12(1), pp. 125-132. https://doi.org/10.6106/KJCEM.2011.12.1.125
  13. Kim, J. Y., Choi J. H. and Lee S. H. (2011). "Factors Affecting the Losses of Domestic Construction Productivity and Strategies for Avoiding Them" Journal of the Architectural Institute of Korea Structure & Construction, AIK, 27(2), pp. 113-124.
  14. Kim, B. and Kim, Y. (2012). "The Analysis of the Major Cost-increasing Risk Factors from the Perspective of Construction Management. -Focusing on Pre-construction Phases-" Korean Journal of Construction Engineering and Management, KICEM, 13(2), pp. 147-155. https://doi.org/10.6106/KJCEM.2012.13.2.147
  15. Kim, N. G. (2013). "An Analysis of the Critical Risk Factors in Failure Cases of Lifting Equipment Plans in High-rise Construction Project" MS thesis, Sungkyunkwan University, Korea.
  16. Kim, M. J. (2014). "Barriers of CM Performance during Construction Stage in CM Projects" MS thesis, Sejong University, Korea.
  17. Kim, Y. S., Kim, H. S., Lee, Y. S., Kang, T. K., Cho, H. H. and Baek, S. H. (2014). "Study on the Critical Success Factors to the Construction Projects Using Construction Management Delivery System" Journal of the Architectural Institute of Korea Structure & Construction, AIK, 17(12), pp. 207-215.
  18. Knowledge Information System of Construction Industry (KISCON) (2011-2015). CM ability evaluation.published press releases, KISCON report, 2011-2015.
  19. Korea Institute of Construction & Transportation Technology Evaluation and Planning (KICTEP) (2003). Development of promotion plan and business procedures by CM type, KICTEP Research Report, 2003.
  20. Lee, J. E. (2002). "Needs and opportunities Analysis of CM Services during Pre-Construction Stages" MS thesis, Sejong University, Korea.
  21. Lee, S. G. (2003). "Integrative performance management of local government based on the implementation of performance-based budgeting system - Focused on Seoul city case" The Korean Journal of Local Finance, KALF, 8(1), pp. 135-162.
  22. Lee, T. S. (2004). "Checklist of Critical Success Factors Classified by Best Practice for Measurement of Construction Management Performance" Journal of the Korean Society of Civil Engineers, KSCE, pp. 5093-5098.
  23. Lee, T. S., Park, K. S., Seo J. W. and Lee, S. Y. (2006). "A Development Of Web-based System for evaluating CM Case" Journal of the Korean Society of Civil Engineers, KSCE, (10), pp. 3721-3724.
  24. Lee, H. C., Lee, J. H. and Go, S. S. (2009). "A Study on the Priority Analysis of Work Delay Factors in Steal-frame Work using FMEA" Korean Journal of Construction Engineering and Management, KICEM, 10(1), pp. 91-101.
  25. Lee, S. H. (2011). "An exploratory study on communication disability factors focused on organizational performance indicators." Journal of Local Government Studies, KALGS, 23(4), pp. 97- 124.
  26. Lee, Y. M. and Kim, Y. S. (2011). "A Study for Major Delay Risk Factors in Curtain Wall Work of High-rise Building using FMEA." Journal of the Architectural Institute of Korea Structure & Construction, AIK, 27(1), pp. 189-196.
  27. Lee, K. M. and Son, C. B. (2014). "An Analysis on the Job Performance of Construction Manager and Its Improvement Measures" Journal of the Architectural Institute of Korea Structure & Construction, AIK, 30(10), pp. 69-76. https://doi.org/10.5659/JAIK_SC.2014.30.10.69
  28. Lim, W. S. (2014). "Extraction of the Core Result Index of Construction Management Control Using Balanced Score Car" MS thesis, Dong-A University, Korea.
  29. Oh, C. D. and Park, C. S. (2012). "An Analysis of Critical Management Factors for Construction Failure on the Apartment Structural Framework using FMEA" Korean Journal of Construction Engineering and Management, KICEM, 13(3), pp. 78-88. https://doi.org/10.6106/KJCEM.2012.13.3.078
  30. Park, K. W. (2010). "The effects of Design and Use of Performance Management Systems on Organizational Performance" Korean Journal of Business Administration, KAABA, 23(2), pp. 769- 789.
  31. Raymond J. Mikulak, Robin McDermott, Michael Beauregard. (2008). The Basics of FMEA, 2nd ed, CRC Press.
  32. Sai X. Zeng, Chun M. Tam and Vivian W. Y. Tam. (2010). "Integrating Safety, Environmental and Quality Risks for Project Management Using a FMEA Method" Economic of Engineering Decisions, 21(1), pp. 44-52.
  33. Seo, S. W. and Jung, I. H. (2016). "Application and Analysis of FMEA for identifying Risk Factors" Journal of Security Engineering, JSE, 13(3), pp. 239-248. https://doi.org/10.14257/jse.2016.06.05
  34. Shin, Y. I. and Kim H. S. (2004). "Performance Measurement Techniques and Best Practice in Construction Projects" Journal of the Architectural Institute of Korea Structure & Construction, AIK, 20(3), pp. 105-112.
  35. Yoo, B. G., Ahn, B. J. and Kim, J.J. (2008). "A Performance Evaluation of Public Construction Management Projects Using Questionnaire Methodology in Korea" Journal of the Architectural Institute of Korea Structure & Construction, AIK, 24(10), pp. 143-150.
  36. Yu, J. H., Song, J. W. and Kim, C. D. (2008). "Construction Safety Management Using FMEA Technique for Selecting Priority order" Korean Journal of Construction Engineering and Management, KICEM, 9(6), pp. 185-193.
  37. Yun, S. and Lee, Y. (2012). "CM work status of HaeUndae tourist resort development project in design management stage" Korean Journal of Construction Engineering and Management, KICEM, 13(4), pp. 25-29. https://doi.org/10.6106/KJCEM.2012.13.4.025