An Enhanced TACT Technique for Finish Work of High-rise Residential Buildings

  • Kim, Sun-Kuk (Department of Architectural Engineering, KyungHee University) ;
  • Son, Ki-Young (Department of Construction Science, Texas A&M University) ;
  • Joo, Jin-Kyu (Shindongah Engineering & Construction) ;
  • Lee, Dong-Hoon (Department of Architectural Engineering, KyungHee University) ;
  • Lee, Sung-Ho (Department of Architectural Engineering, KyungHee University)
  • Received : 2011.04.07
  • Accepted : 2011.07.01
  • Published : 2011.08.20

Abstract

Execution of the finish work for high-rise residential construction occurs when a mixture of work progresses simultaneously at each floor or sector and is carried on by highly-specialized subcontractor teams. Therefore, the finish work plan requires an effective scheduling method that interfaces between the work and the teams. In order to address these issues, the TACT technique is utilized in Korea. This technique is based on Line-of-Balance and Lean construction. However, according to recent case studies, finish work using TACT technique was frequently delayed with cost overruns because the work was performed without a detailed schedule control plan outlining the relationship between architecture and mechanical, electrical, and plumbing work. This paper describes the enhanced-TACT technique which provides a detailed work flow chart and TACT work template. With improved TACT technique, this paper will contribute to improved cash flow and reduced cycle time and provide quality improvement through work continuity.

Keywords

References

  1. United States Census. 2004 economic census industry series reports construction. [On-line]. [Retrieved Aug 11, 2011] Available at www.census.gov/econ/census02/ guide/INDRPT23. HTM.
  2. Sacks R, Goldin M. Lean management model for construction of high-rise apartment buildings. ASCE Journal of Construction Engineering and Management. 2007 May;133 (5):374-84. https://doi.org/10.1061/(ASCE)0733-9364(2007)133:5(374)
  3. Kim JH, Yoon YS, Jang MH, Suh SW. Work flow-based TACT Planning & Scheduling Process: Focused on the Finish Work of Apartment Building. Journal of the Architectural Institute of Korea. 2007 Dec; 23(6):153-63.
  4. Kim YS, Hwang MH, Park CS. A Study on the Present Status and Problem Analysis of Construction Process Management in Domestic Building Construction Sites. Journal of the Architectural Institute of Korea. 1996 Dec;12(12):253-65.
  5. Hwang HS, Kim KR, Suh SW, Kim CD, Shin DW. Analysis of Actual Duration by Effecting Elements to Duration Estimate: Focused on Standard Duration of the Office Building Construction. Korean Journal of Construction Engineering and Management. 2002 June; 3(3):84-93.
  6. Yoon YS, Suh SW. The application of tact time at finish work for building construction: Focused on Office Building. Korean Journal of Construction Engineering and Management. 2005 Dec;6(6):90-7.
  7. Rahbar FF, Rowing JE, Repetitive Activity Scheduling process. Proceedings of the 36st Annual Meeting of the Transactions of the American Association of Cost Engineers; Orlando; [date unknown]. Orlando (PL): Transactions of the American Association of Cost Engineers; 1992. p. 51-58.
  8. Selinger S. Construction planning for linear projects. ASCE Journal of Construction Engineering and Management. 1980 Feb;106(2):195-205.
  9. Carr RI, Meyer W.L. Planning construction of repetitive building units. Journal of the Construction Division 1974 Sep;100(3):403-12.
  10. Arditi D, Albulak MZ. Line-of-balance scheduling in pavement construction. ASCE Journal of Construction Engineering and Management. 1986 Dec;112(3): 411-24. https://doi.org/10.1061/(ASCE)0733-9364(1986)112:3(411)
  11. Arditi D, Tokdemir OB, Suh K. Challenges in Line-of-Balance Scheduling. ASCE Journal of Construction Engineering and Management. 2002 Dec;128(6): 545-56. https://doi.org/10.1061/(ASCE)0733-9364(2002)128:6(545)
  12. Neale RH, Neale DE. Construction Planning. London (UK): Thomas Telford Ltd.; 1989. 165 p.
  13. Kim YJ, Han JY, Shin DW, Kim KR, Kim CD, Seo SW. A Tact Planning and Scheduling Process Model for Reduction of Finishing Work Duration in Building Construction Projects. Journal of the Architectural Institute of Korea. 2003 Sep;19(1):161-168.

Cited by

  1. TACT Productivity Management for Finish Works of Residential Buildings using Productivity Achievement Ratio (PAR) vol.16, pp.3, 2015, https://doi.org/10.6106/KJCEM.2015.16.3.036
  2. Time reduction effect of the enhanced TACT method for high-rise residential buildings vol.22, pp.7, 2016, https://doi.org/10.3846/13923730.2014.945949