An Enhanced TACT Technique for Finish Work of High-rise Residential Buildings  

Kim, Sun-Kuk (Department of Architectural Engineering, KyungHee University)
Son, Ki-Young (Department of Construction Science, Texas A&M University)
Joo, Jin-Kyu (Shindongah Engineering & Construction)
Lee, Dong-Hoon (Department of Architectural Engineering, KyungHee University)
Lee, Sung-Ho (Department of Architectural Engineering, KyungHee University)
Publication Information
Journal of the Korea Institute of Building Construction / v.11, no.4, 2011 , pp. 396-406 More about this Journal
Abstract
Execution of the finish work for high-rise residential construction occurs when a mixture of work progresses simultaneously at each floor or sector and is carried on by highly-specialized subcontractor teams. Therefore, the finish work plan requires an effective scheduling method that interfaces between the work and the teams. In order to address these issues, the TACT technique is utilized in Korea. This technique is based on Line-of-Balance and Lean construction. However, according to recent case studies, finish work using TACT technique was frequently delayed with cost overruns because the work was performed without a detailed schedule control plan outlining the relationship between architecture and mechanical, electrical, and plumbing work. This paper describes the enhanced-TACT technique which provides a detailed work flow chart and TACT work template. With improved TACT technique, this paper will contribute to improved cash flow and reduced cycle time and provide quality improvement through work continuity.
Keywords
scheduling; lean construction; high-rise buildings;
Citations & Related Records
Times Cited By KSCI : 5  (Citation Analysis)
연도 인용수 순위
1 Selinger S. Construction planning for linear projects. ASCE Journal of Construction Engineering and Management. 1980 Feb;106(2):195-205.
2 Carr RI, Meyer W.L. Planning construction of repetitive building units. Journal of the Construction Division 1974 Sep;100(3):403-12.
3 Arditi D, Albulak MZ. Line-of-balance scheduling in pavement construction. ASCE Journal of Construction Engineering and Management. 1986 Dec;112(3): 411-24.   DOI   ScienceOn
4 Arditi D, Tokdemir OB, Suh K. Challenges in Line-of-Balance Scheduling. ASCE Journal of Construction Engineering and Management. 2002 Dec;128(6): 545-56.   DOI   ScienceOn
5 Neale RH, Neale DE. Construction Planning. London (UK): Thomas Telford Ltd.; 1989. 165 p.
6 Kim YJ, Han JY, Shin DW, Kim KR, Kim CD, Seo SW. A Tact Planning and Scheduling Process Model for Reduction of Finishing Work Duration in Building Construction Projects. Journal of the Architectural Institute of Korea. 2003 Sep;19(1):161-168.   과학기술학회마을
7 United States Census. 2004 economic census industry series reports construction. [On-line]. [Retrieved Aug 11, 2011] Available at www.census.gov/econ/census02/ guide/INDRPT23. HTM.
8 Sacks R, Goldin M. Lean management model for construction of high-rise apartment buildings. ASCE Journal of Construction Engineering and Management. 2007 May;133 (5):374-84.   DOI   ScienceOn
9 Kim JH, Yoon YS, Jang MH, Suh SW. Work flow-based TACT Planning & Scheduling Process: Focused on the Finish Work of Apartment Building. Journal of the Architectural Institute of Korea. 2007 Dec; 23(6):153-63.   과학기술학회마을
10 Kim YS, Hwang MH, Park CS. A Study on the Present Status and Problem Analysis of Construction Process Management in Domestic Building Construction Sites. Journal of the Architectural Institute of Korea. 1996 Dec;12(12):253-65.   과학기술학회마을
11 Hwang HS, Kim KR, Suh SW, Kim CD, Shin DW. Analysis of Actual Duration by Effecting Elements to Duration Estimate: Focused on Standard Duration of the Office Building Construction. Korean Journal of Construction Engineering and Management. 2002 June; 3(3):84-93.   과학기술학회마을
12 Yoon YS, Suh SW. The application of tact time at finish work for building construction: Focused on Office Building. Korean Journal of Construction Engineering and Management. 2005 Dec;6(6):90-7.   과학기술학회마을
13 Rahbar FF, Rowing JE, Repetitive Activity Scheduling process. Proceedings of the 36st Annual Meeting of the Transactions of the American Association of Cost Engineers; Orlando; [date unknown]. Orlando (PL): Transactions of the American Association of Cost Engineers; 1992. p. 51-58.