Case Studies: Schedule Delay Factors and Delay Prevention Program for Concrete Frame Works in Apartment Construction Project  

Cho, Tae-Jea (Department of Architectural Engineering, Dongguk University)
Choi, Jong-Soo (Department of Architectural Engineering, Dongguk University)
Publication Information
Journal of the Korea Institute of Building Construction / v.11, no.1, 2011 , pp. 9-17 More about this Journal
Abstract
Project delay is one of the most crucial impact factors in the construction process from a schedule and cost management perspective. This study focused on analyzing the causes of concrete frame work delay in the apartment construction project. According to the analysis of project cost composition, the direct cost of concrete works was highest in most samples. Actual delays of concrete works were analyzed for the six different construction components. Causes of delay were grouped into two categories; preconstruction and construction phases and these two groups were further divided into sub-groups. Analysis results revealed that the most significant delay was occurred in the 1st. floor concrete skeleton work. For each delay factor, implications of delay as well as suggestion(s) for reducing the possibility of schedule delay are provided.
Keywords
Schedule Delay Factors; Concrete Frame Works; Delay Prevention Program;
Citations & Related Records
Times Cited By KSCI : 12  (Citation Analysis)
연도 인용수 순위
1 Kim YJ, Lee WC, Hong JS, Kim KR, Shin DW. A case study on delay analysis methods in the construction project. Korea journal of construction engineering and management 2004;15(6):129-137.
2 Kwon JM, Lee JS. Construction delay analysis method; hierarchical planning process approach, Journal of the architectural institute of Korea(structure & construction). 2003;19(8):121-128.   과학기술학회마을
3 Lee SB, Lee YM. Improvement for liquidated damages according to the delay of domestic construction project. Journal of the architectural institute of Korea(structure & construction). 2003;19(5):145-152.   과학기술학회마을
4 Han JK, Chin SY, Kim YS. An analysis on delay factors of major trades in apartment housing projects. Journal of the architectural institute of Korea(structure & construction). 2003;19(3):163-170.   과학기술학회마을
5 Lyu HG, Yu JH, Lee HS. A method of calculating schedule delay considering lost productivity. Journal of the architectural institute of Korea(structure & construction). 2002;18(10):117-125   과학기술학회마을
6 Elinwa AU, Joshua M. Time-overrun factors in Nigerian construction industry. Journal of construction engineering and management. 2001;127(5):419-425.   DOI   ScienceOn
7 Majid MZ, Mccaffe R. Factors of non-excusable delays that influence contractors' performance. Journal of management in engineering. 1998;14(3):42-49.
8 Jung JH, Lee K, Hong KH, Lee CH. An analysis on difficulties and delay factors for the development and application of technologies for reduction of construction duration. Journal of the architectural institute of Korea(structure & construction). 2010;26(10):121-128.   과학기술학회마을
9 Lee JS. Delay analysis using learning effect and linear scheduling in construction. Journal of the architectural institute of Korea(structure & construction). 2008;24(5):185-192.   과학기술학회마을
10 Kim KH, Kim KH, Lee YS, Kim JJ. A study about influence of risk factors in relation to construction cost increase and schedule delay on the reinforced concrete construction. Journal of the architectural institute of Korea(structure & construction). 2008;24(5):165-172.   과학기술학회마을
11 Lee JS. Delay analysis using linear schedule in construction. Journal of the architectural institute of Korea(structure & construction). 2007;23(8):213-220.   과학기술학회마을
12 Lee JS. Modified delay analysis considering production rates. Journal of the architectural institute of Korea(structure & construction). 2006;22(5);203-210.   과학기술학회마을
13 Koo JM, Lee JS. Construction delay analysis method considering productivity. Journal of the architectural institute of Korea(structure & construction). 2004;20(4);153-160.   과학기술학회마을
14 Kim YJ, Hong JS, Kim KR, Shin DW. An analysis method for the concurrent delay using delay section concept. Journal of the architectural institute of Korea(structure & construction). 2004;20(6):141-148.
15 Kim TW, Lee JS. Construction delay analysis utilizing system thinking approach. Journal of the architectural institute of Korea(structure & construction). 2006;22(9):131-138.   과학기술학회마을
16 Korean commercial arbitration board. Case book of arbitration precedents Vol. 13. KR, Seoul:Korean commercial arbitration board editors; 2003.
17 AURIC(Architecture & Urban Research Information Center) [Internet]. The dictionary constructional terms. Available from; http://www.auric.or.kr/User/Dict/DictMain.aspx
18 Callahan MT, Quackenbush DG, Rowings JE. Construction project scheduling. NY. McGraw-Hill; 1992
19 Kartman S. Generic methodology for analyzing delay claims. Journal of construction engineering and management. 1999;125(6):409-419.   DOI
20 Han SH, Yun SM, Lee SH. Exploring delays of the mega construction project : the case of korea high speed railway. The KSCE journal of civil engineering 2006;26(5):839-848.   과학기술학회마을
21 Chan DWM, Kumaraswamy MM. A comparative study of causes of time overruns in Hong Kong construction projects. International journal of project management. 1997;15(1):55-63.   DOI   ScienceOn
22 Assaf SA, Al-Khalil M, Al-Hazmi M. Cause of delay in large building construction projects. Journal of construction engineering and management. 1995;11(2):45-50.
23 Nasir D, Mccabe B, Hartono L. Evaluating risk in construction-schedule model(eric-s):construction schedule risk model. Journal of construction engineering and management, 2003;129(5):518-527.   DOI   ScienceOn