Abstract
The emergency restoration scenarios for efficient railway accident management and restoration were developed. The emergency restoration procedures defined by the worst case of emergency restoration and the important events was proposed based on questionnaires from specialists and the result of survey. Via these studies, the railway accident in the tunnel could be the worst case among all railway accident types. Therefore, educations for a restoration team in confined area condition should be planned and performed to recover the worst case accident. In order for the emergency restoration, when a railway accident is occurred, the restoration should be performed in orders of handing collapse of facilities, burying track, and derailment of vehicle in tunnel based on the statistical analysis. The result of priorities were established by the period of restoration. The standard operation system for efficient railway accident management was developed by synthesizing the worst case for rapid emergency restoration, and important events for the standard operation procedures according to each emergency restoration type. Through this study, the restoration operation system of railway accident are recommended. This paper suggests to develop emergency restoration scenarios for the efficient railway accident management and recovery system. The study results will contribute not only for insuring punctuality, but also for minimizing delays from accidents. Therefore, emergency restoration scenarios will play a major role in the SOP for the damage limitation and the prevention of accident spread.
본 연구에서는 효율적인 철도사고관리 및 복구작업을 위한 임시복구 시나리오를 개발하였다. 문헌조사 및 전문가 설문조사 결과를 통하여 임시복구 Worst Case 선정시기준이 되는 고려항목과 임시복구 시나리오 수립에 필요한 중요항목(event)을 도출하였으며, 임시복구가 가장 힘든 Worst Case로는 터널구간에서 발생하는 철도사고가 선정되었다. 이는 신속한 임시복구를 위해 좁은 공간에서 체계적이고 효율적인 복구절차를 갖추고 숙련된 복구요원 양성이 필요한 것으로 분석되었다. 또한, 본 연구에서는 통계학적 분석기법을 이용하여 임시복구 시나리오 수립 시 중요항목(event)간 중요도(우선순위)를 선정한 결과 임시복구유형중 시설물 붕괴를 가장 우선적으로 복구하고 선로매몰, 차량탈선 순으로 처리함이 복구시간을 단축할 수 있는 것으로 분석되었다. 이는 복구에 많은 시간이 소요되는 순으로 임시복구가 이루어져야 함을 나타낸다. 임시복구 시나리오는 임시복구 Worst Case, 임시복구유형별 중요항목(event)을 종합하여 표준운영절차(안) 11개를 제안하였다. 이를 활용하여 철도사고 DB관리 및 신속한 사고복구를 통해 정시성을 확보하여 열차지연시간을 최소화하는데 크게 기여할 것이다.