Gradational Risk Management in Procurement Phase for Plant Projects

플랜트 프로젝트의 구매조달 단계별 리스크 분석에 관한 연구

  • Received : 2009.07.07
  • Accepted : 2009.09.24
  • Published : 2009.09.30

Abstract

In the plant EPC project, the procurement work can be considered as the most important part that affects the success or failure of project as it has the closest mutual influence in every execution process of the project. Procurement takes up generally 60% ~ 70% of the entire project budget and the current trend of plant EPC project becoming larger in scale and a variety of process technology being applied. So, it is needed to identify the risks that are expected to occur according to the stages of procurement work, namely, proposal stage, manufacturer selection and purchasing agreement stage, expediting the process management of manufacturer stage, inspection stage and logistics & transportation stage. The management of observation and control of the risks should be performed with the response techniques which are 'avoid',' transfer'and' mitigate'.