A Real Time Integrated Dispatching Logic for Semiconductor Material Flow Control Considering Multi-load Automated Material Handling System

반도체 물류 제어 시스템을 위한 반송장비의 다중적재를 고려한 실시간 통합 디스패칭 로직

  • Suh, Jungdae (Department of Industrial Engineering, Kyungwon University) ;
  • Faaland, Bruce (School of Business, University of Washington)
  • 서정대 (경원대학교 산업정보시스템공학과) ;
  • Received : 2007.06.20
  • Accepted : 2008.04.18
  • Published : 2008.09.30

Abstract

A semiconductor production system has sophisticated manufacturing operations and needs high capital investment for its expensive equipment, which warrants efficient real-time flow control for wafers. In the bay, we consider material handling equipment that can handle multiple carriers of wafers. The dispatching logic first determines the transportation time of each carrier to its destination by each unit of transportation equipment and uses this information to determine the destination machine and target carrier. When there is no available buffer space at the machine tool, the logic allows carriers to stay at the buffer of a machine tool and determine the delay time, which is used to determine the destination of carriers in URL. A simulation study shows this dispatching logic performs better than the procedure currently in use to reduce the mean flow time and average WIP of wafers and increase efficiency of material handling equipment.

Keywords

Acknowledgement

Supported by : LG연암문화재단

References

  1. Bahri, N., Reiss, J., Doherty, B. (2001), A comparison of unified vs. segregated automated material handling systems for 300mm fabs, IEEE International Symposium on Semiconductor Manufacturing Conference, 3-6
  2. Chand, S., Traub, R., and Uzsoy, R. (1997), Rolling Horizon Procedures for the Single Machine Deterministic Total Completion Time Scheduling Problem with Release Dates, Annals of Operations Research, 70, 115-125 https://doi.org/10.1023/A:1018961818782
  3. Engell, S., Kuhn, T., and Moser, M. (1990), On Decentralized On-line Scheduling of FMS, Proceedings of the 29th IEEE Conference on Decision and Control, Honolulu, Hawaii, 125-127
  4. Ferland, A., Fortin, L., (1989), Vehicle scheduling with sliding time windows, European Journal of Operational Research, 38, 213-226 https://doi.org/10.1016/0377-2217(89)90106-9
  5. Gartland, K., Godding, G., Hodges, B., Muzumbar, N., Hohkibara, S., Kono, S., Honma, M., Inoue, G. (2000), Scheduler/dispatcher user requirements. International SEMATECH, Technology Transfer # 00063966A-TR
  6. Glassey, C. R. and Resende, M. G. C. (1988), Closed-loop job release control for VLSI circuit manufacturing, IEEE Transactions on semiconductor manufacturing, 1(1), 36-46 https://doi.org/10.1109/66.4371
  7. Jang, J., Suh, J., and Ferreira, P. (2001a), An AGV routing policy reflecting the current and future state of semiconductor and LCD production lines, International Journal of Production Research, 39(17), 3901-3921 https://doi.org/10.1080/00207540110056261
  8. Jang, J., Suh, J., and Liu, C. R. (2001b), A Look-Ahead Routing Procedure for Machine Selection in a Highly Informative Manufacturing System, International Journal of Flexible Manufacturing Systems, 13(3), 287-308 https://doi.org/10.1023/A:1011199619582
  9. Koo, P.-H, Jang, J. and Suh, J. (2005), Vehicle dispatching for highly loaded semiconductor production considering bottleneck machines first, International Journal of Flexible Manufacturing Systems, 17 (1), 23-38 https://doi.org/10.1007/s10696-005-5992-6
  10. Koskosidis, Y. A., Powell, W. B., Solomon, M. M., (1992), An optimization- based heuristic for vehicle routing and scheduling with soft time window constraints, Transportation Science, 26(2), 69-85 https://doi.org/10.1287/trsc.26.2.69
  11. Lou, S. X. C. and Kager, P. W. (1989), A Robust production control policy for VLSI wafer fabrication, IEEE Transactions on semiconductor manufacturing, 2(4), 159-164 https://doi.org/10.1109/66.44620
  12. Lu, S. C. H., Ramaswamy, D., and Kumar, P. R. (1994), Efficient scheduling policies to reduce mean and variance of cycle-time in semiconductor manufacturing plants, IEEE Transactions on Semiconductor Manufacturing, 7(3), 374-388 https://doi.org/10.1109/66.311341
  13. Sexton, T.R. and Choi, Y., (1986), Pickup and delivery of partial loads with soft time windows, American Journal of Mathematical and Management Science, 6, 369-398
  14. Smith, T. M. and Stecke, K. E. (1996), On the Robustness of Using Balanced Part Mix Ratios to Determine Cycle Part Input Sequences into Flexible Flow Systems, International Journal of Production Research, 34(10), 2925-2942 https://doi.org/10.1080/00207549608905066
  15. Suh, J., Jang, J., and Koo, P. H. (2003), Development of a Look-ahead AGV controller for a clean bay operation, International Journal of Industrial Engineering, 10(4), 547-554
  16. Taillard, E., Badeau, P., Gendreau, M., Guertin, F., Potvin, J.-Y., (1997), A tabu search heuristic for the vehicle routing problem with soft time windows, Transportation Science, 31(2), 170-186 https://doi.org/10.1287/trsc.31.2.170
  17. Uzsoy, R., Lee, C. Y. and Martin-vega, A. L. (1992), A review of production planning and scheduling models in the semiconductor industry part1 : system characteristics, performance evaluation and production planning, IIE Transactions, 24(4), 47-60 https://doi.org/10.1080/07408179208964233
  18. Vargas-Vilamil, F. D., Rivera, D. E. and Kempf, K. G. (2003), A hierarchical approach to production control of reentrant semiconductor manufacturing lines, IEEE Transactions on control systems technology, 11(4), 578-87 https://doi.org/10.1109/TCST.2003.813368
  19. Wein, L. M. (1988), Scheduling semiconductor wafer fabrication, IEEE Transactions on Semiconductor Manufacturing, 1(3), 115-130 https://doi.org/10.1109/66.4384