Test Results Grid Connection of 120 kW Power Generation System

120 kW급 태양광 발전시스템 설치 및 실 계통연계 운전 결과 평가

  • 황정희 (한전전력연구원 신재생에너지그룹) ;
  • 안교상 (한전전력연구원 신재생에너지그룹) ;
  • 임희천 (한전전력연구원 신재생에너지그룹) ;
  • 김수창 (한국서부발전(주)) ;
  • 김신섭 (헥스파워시스템)
  • Published : 2006.09.15

Abstract

In this paper, the test results of medium-size(120 kW class) PV system which was installed in the Taeahn thermal power station of Korea Western Power Co., Ltd., were summarized for developing the practical technology to applicate high voltage grid connection PV system. The 120 kW photovoltaic system which was consisted of 1,300 modules, PCS, and 150 kVA transformer station has been operated since Aug. 05, 2005. For verifying the modeling results of PV system, the operation data was compared with modeling results which was executed commercial PSCAD/EMTD and Psim tools. An equivalent circuit model of a solar cell has been also used for solar array modeling. A series of parameters required for array modeling have been estimated from general specification data of a solar module. A PWM voltage source inverter(VIS) and its current control scheme have been analyzed by using P&O (perturbation and Observation) MPPT algorithms technique.

Keywords

References

  1. 산업자원부, '120 kW급 태양광 발전시스템의 실 계통 연계운전 적용 및 평가', 최종보고서, 2006
  2. 안교상, 김수창, 김신섭, 황언호, 박성연, 김영섭, 임희천, 오제명, ' 120 kW 태양광 발전시스템의 설계/제작', 대한전기학회 하계학술대회, July, 2005
  3. 김슬기, 김진홍, 김응상, 'PSCAD/EMTDC를 이용한 계통연계형 태양광발전시스템의 모델 링 및 모의 해석' 대한전기학회, Vol. 54A, No.3, Mar. 2005