A Study on the Reliability Evaluation of Start-up Power Supply in Fossil Power Plant by Minimal Cut-Set Method

최소 컷셋법에 의한 화력발전소 기동전원의 신뢰도 예측에 관한 연구

  • 최규식 (건양대 정보전자통신공학부)
  • Published : 1999.04.01

Abstract

The auxiliary transformers or start-up/stand-by transformer(s) are installed against the start-up and shut-down of generator and emergency status in fossil power plant. The on-site power supply configuration using these transformers must be determined, considering configuration requirements, site characteristics, reliability and availability severely because it is remarkably important for safety and ecfonomy of plant. The auxiliary or start-up/stand-by power supply configuration has been determined considering only safety requirements and construction cost until now in Korea. This paper presents general theorems for the reliability estimation and proposes 2-unit based 4 alternatives for the start-up power supply stystem of 500㎿ standardized fossil power plant. The reliability and unavailability of equipment, system and configuration are determined using minimal cut-set methodology. The optimized plan of 4 alternatives is determined based on this ultimate reliability and unavailability.

Keywords

References

  1. 보령화력 3, 4호기 용량 및 대수 검토 보고서 한국전력기술(주)
  2. 보령화력 5, 6호기 용량 및 대수 검토 보고서 한국전력기술(주)
  3. 삼천포화력 5, 6호기 용량 및 대수 검토 보고서 한국전력기술(주)
  4. 태안화력 1, 2호기 용량 및 대수 검토 보고서 한국전력기술(주)
  5. 당진화력 1, 2호기 용량 및 대수 검토 보고서 한국전력기술(주)
  6. 서인천화력 1, 2단계 용량 및 대수 검토 보고서 한국전력기술(주)
  7. Reliability-Based Design Singiresu S. Rao
  8. IEEE Recommended Practice for the Design of Reliable Industrial and Commercial Power Systems IEEE493
  9. IEEE Guide for General Principles of Reliability Analysis of Nuclear Power Generating Station Safety Systems ANSI/IEEE352
  10. 신뢰성공학 이치우;김선진;이성우;정상영
  11. 신뢰성공학 강인선;김진규
  12. 발전소 정전방지 검토 한국전력기술(주)
  13. 원자력발전소 표준화 설계를 위한 조사 용역 제 10권 한국전력기술(주)