Process Interference Management for Finish Works using Mobile Technology
모바일 기술을 이용한 마감공사의 작업간섭 관리
Abstract
The finish works of construction projects comprises approximately 40% of the total construction duration. Thus, the management of finish works have as big as impacts on total project duration as the earthworks, foundation and structure works. Process interference management is considered one of the most important issues dealt during finish works. However, it was investigated that effective management systems have yet not been applied for practical use. Accordingly, this paper suggests a mobile technology based finish works management system that mainly focuses on preventing process interference occurred due to ineffective communication between general and sub-contractors.