Reinforced-Concrete Works Productivity Analysis on Nuclear-Power-Plant Project

  • 발행 : 2015.10.11

초록

Both the importance and process of estimating Nuclear-power plant construction time and cost have increased in significance as energy user costs themselves have become more significant. In estimating construction time, few parameters are more significant than work item production rates and factors significantly affecting the rates. A standardized data collection tool was used to acquire a total of 401 data points from a S Nuclear-power plant project, for selected critical works: form-work, rebar-work, and concrete-pouring. With the data, several hypothesized drivers of the man-hour production rates and crew-day production rates were also analyzed. Findings from this study will enable industry professionals to enhance accuracy of time and cost estimation for nuclear power plant construction.