Framework for Estimating Appropriate Construction Duration of CFRD in the Planning Phase

  • Kim, In Kyum (Dept. of Civil & Environmental Engineering Chung-Ang University) ;
  • Kim, Kyong Ju (Dept. of Civil & Environmental Engineering Chung-Ang University) ;
  • Yun, Won Gun (Dept. of Civil & Environmental Engineering Chung-Ang University)
  • Published : 2015.10.11

Abstract

To secure quality of dam construction needs appropriate construction duration. Tight construction schedule may have negative influence on infrastructure quality, work safety and maintenance cost. It is necessary to reflect proper construction duration in the planning phase. There have been standards for estimating construction duration of building and industrial complex development but dam construction have not. In order to estimate construction duration of CFRD, feasible study reports and design reports were analyzed to acquire available information. After that, considering on construction duration methods such as comparison with similar cases, approximate estimating formula, approximate quantity assumption were adapted to Critical Path items. Hence, this study present framework for construction duration estimating of CFRD in the planning phase. This framework can be applied other types of dam along the same line.

Keywords

Acknowledgement

This research was supported by Basic Science Research Program through the National Research Foundation of Korea (NRF) funded by the Ministry of Education (No. NRF-2013R1A1A2009803)