Masonry work interference factor deduction based on daily report data analysis

작업일보 데이터를 활용한 조적공사 작업간섭 요소 도출

  • 박민하 (인하대학교 건축공학과) ;
  • 이혜린 (인하대학교 건축공학과) ;
  • 고용호 (인하대학교 건축공학과) ;
  • 한승우 (인하대학교 건축공학과)
  • Published : 2015.11.14

Abstract

Construction project involves numerous repetitive operations. Especially in high-rise and apartment houses projects, the amount of repetitive operations increase and a preceding operations delay causes serious damage to the total duration of the project. This study deducts work delay factors by site engineer interview and survey. The study analyzes daily report data to deduct crucial processes affecting masonry work which has been investigated to be one of preliminary processes conducted at the beginning of finish work.