A Study on Proto-type Development of BIM based Stochastic Duration Estimation Module

BIM기반 추계학적 공기 예측 모듈 프로토 타입 개발에 관한 연구

  • Published : 2009.05.23

Abstract

Today's construction is more various and more complex. Because of that, a lot of uncertain factors are occurred and they related uncertain construction duration. For management complex architecture project, importance of construction schedule management also increased. In previous studies, one of solutions to overcome those problems is suggested. It was BIM based construction simulation process which focused on construction schedule and construction schedule management. But latest process had limited point which has no duration estimation function. So this paper suggested duration estimation method and developed duration estimation module. Duration estimation module developed with current scheduling tool MS Project and their macro function. However, this module has just developed Reinforced Concrete Structure and has to do more development and research.