A Validation on Estimate at Completion Evaluation Methods of EVMS

EVMS에서 최종예상공사비(EAC) 평가방법에 관한 검증

  • 박은진 (부경대학교 대학원 건설사업관리공학협동과정) ;
  • 김수용 (부경대학교 산업공학과) ;
  • 황효수 (성일건설(주))
  • Published : 2002.11.01

Abstract

Earned Value Management System(EVMS) has been institutionalized as an advanced management technique of construction project lately. And its research has been in the active progress in order to utilize the earned value concept as a project management tool for construction project ordered by both government and private sector. However it is necessary to test and prove the EVMS's adaptability to our construction environment by EVMS's several of operations before its introduction. Project forecasting phase of EVMS is the Estimate at Completion by utilizing earned value data. So, the purpose of this study is to propose EAC evaluation method for evaluation the accuracy of the EAC and encouraging cost realism, and to test for proving the validity of the evaluation methods through hypothesis testing.

EVMS(Earned Value Management System)는 건설프로젝트의 선진관리기법으로서 최근 국내건설공사의 공공부분 공사에 도입되어 제도화되었으며, 정부발주뿐만 아니라 민간발주 건설프로젝트에서도 EVMS를 관리기법의 도구로 활용하기 위하여 많은 연구가 진행되고 있다. 그러나 선진관리기법인 EVMS를 도입하기 이전에 EVMS의 여러 업무들이 국내건설사업 환경에 대한 적합성에 대하여 검정할 필요성이 있다. 이에 본 연구에서는 EVMS에서 프로젝트 예측단계로서 최종예상공사비(Estimate At Completion)를 정확하게 평가하고 실질적인 비용을 측정하는데 유용하게 사용하기 위하여 최종예상공사비 평가방법을 제안하고 그 방법들에 대하여 통계적 방법인 가설검정(Hypothesis testing)을 이용하여 타당성을 검증하고자 한다.

Keywords