Construction Plan by Large Diameter Shield TBM Method and Analysis of Deformation on Site Under Soo-Young River

대구경 Shield TBM공법에 의한 수영강 하저터널 시공계획 및 시공중 발생되는 거동의 공학적 분석

  • 윤현돈 (두산건설㈜ Shield TBM Project팀) ;
  • 황규호 (두산건설㈜ 기술연구소) ;
  • 최기훈 (두산건설㈜ 기술연구소)
  • Published : 2001.03.01

Abstract

Doosan Construction & Engineering Co., Ltd is building a railway tunnel beneath the Soo-Young River connecting MinLak Station and Centum City Station, a section 230, subway line 2, Pusan City, Korea. When completed the tunnel will have a finished inner diameter of 6.5m(21.311) throughout its total length of 840m(420m = 0.52 miles, Two Single Track Tunnel : 420m+420m). The ground profile of the face toward shield machine is composed of multi layers, silty clay, clayey gravel, soft rock etc. This research paper is to predict ground deformation and variation of stresses around tunnel using Hyperbolic model, and to reflect the works on the next shield tunneling project. And this research paper is analyzed data of measuring instrument (such as settlement gauge, inclinometer, Multiple extensometer, etc.) which is installed along tunnel line for safety of tunnel. For calculations, the finite difference Method is applied. Backfill grouting material is supposed to have instantly strength of 10kg/$\textrm{cm}^2$ above, although its strength is available after 24 hours passed.

Keywords