This is a case history on design and cnostruction of tunnel for under passing an underground transformer substation. The original construction plan was cut & cover method to avoid blasting vibrations and displacements of facilities during the construction stages. But this plan was changed to tunnel because of the difficulties from construction period, cost and the required relocation site. As a results of tunnel construction, the relocation of transformer substation and replacements of transmission cables were not necessary. Therefore about 10 months of construction period and 3.5 billion wonts of construction cost were saved. Additionally, quantitative criterion for blasting was provided through the results of blasting vibration analysis.
Proceedings of the Korean Institute of Building Construction Conference
/
2020.06a
/
pp.169-170
/
2020
Occupational Safety and Health Management Cost, used to protect workers in Korean construction worksites and to create safe working environments, is a legally managed expense item. As this cost item is grounded on the Occupational Safety and Health Act, it is always implemented. However, because there is a ceiling on its rates, insufficient amounts of Safety Management Costs are often allocated to worksites, with the money not being used to areas essential to worker safety. As such, the current study raises the need to develop a set of standards to enable some items under the Occupational Safety and Health Management Costs-appropriated under the rate of indirect costs-to be appropriated as direct construction costs. As a preliminary step in this effort, the current study will provide basic data that can be used to create construction cost calculation standards for items that can be calculated as direct construction costs.
Kyung-Bae Jin;Young-Ho Kim;Eul-Bum Lee;Suk-Hwan Seo
International conference on construction engineering and project management
/
2013.01a
/
pp.145-150
/
2013
As a recent global trend, the majority of mega-size plant projects are delivered through EPC (Engineering, Procurement and Construction) contracts, where a single contract is awarded for engineering, procurement, and construction. Under this contracting mechanism, it is challenging for contractors to carry out the projects under traditional project management processes used in design-bid-build projects. A new EPC Plant, the POSCO Special Steel Plant in Changwon, was built successfully at the beginning of 2012 and it is currently in full-scale production. The project has encountered a number of major difficulties however, with some technical and managerial issues through its development process. As summarized in this paper, the authors (as project participants with the contractor) investigated it as a post construction analysis and recorded the Lessons-learned for future project management improvement.
This document presents the JES(Joint Element Structure) method that has been adopted for the firs time in our country for the construction of the structure crossing under the railroad without open excavation. Front Jacking Method, Tubular Roof Construction Method, New Tubular Roof Method and Joint Element Structure Method are commonly used for the construction of structures crossing under the railroad. JES Method, frequently used in Japan recently, is a new method to construct the structures crossing under the railroad in a safe manner and in a relatively short period of time by utilizing the steel elements with the joints through which the load in the vertical angle to the axial direction is transferred to the next element. The elements are tied to each other through the joints to form the permanent walls of a Rahmen structure under the road without open excavation and without limitation to the length in a convenient way. Through the case study in the project of a Subway Box Culvert Improvement for the Gyeonguiseon Railroad in front of Yonsei University using the JES Method, the cost and period of construction in various types of soil is investigated compared to the Front Jacking Method. Furthermore, by analyzing the results of instrumentation measurements carried out throughout the construction, comparison between the actual displacement in the ground and the predicted displacement in the design is made to provide the considerations to be counted for the design. In conclusion, comparison in the field of economic feasibility, constructability and safety between the JES Method and Front Jacking Method, which is most frequently adopted in our country at present, is made to present the JES Method as a new alternative for the non-open excavation construction method for the structures crossing under the railway.
Proceedings of the Korea Concrete Institute Conference
/
2008.04a
/
pp.117-120
/
2008
Recently, according to the increasement of high-rise building construction and domestic situation, requirements of rapid cycle construction are increasing. For more economical and rapid cycle construction, it is required to reduce formwork cost. So formwork have to be stripped as soon as possible. But as fresh concrete is loaded with construction load, it is likely that the structure will have problems with safety and serviceability. To reduce construction cycle economically, safety and serviceability of structure against construction load have to be considered. But as behavior of structure under construction is so complicated, behavior of structure has to be investigated according to construction stage. Therefore, through field instrumentation of apartment, behavior of structure under construction was analyzed.
The effect of a partially earth anchored cable system on the structural safety of a long span cable-stayed bridge under seismic and wind loads are examined during construction process. By assuming the FCM (free cantilever method) construction stages with structural vulnerability, a multi-mode spectral analysis and a multi-mode buffeting analysis are performed for specific seismic load and wind load, respectively. Results show that the wind load dominates the structural safety of a cable-stayed bridge during construction. And, the application of a partially earth anchored cable system can enhance structural safety under wind load since the maximum pylon moment in the model with partially earth anchored cable system is reduced by 49% under wind load. In contrast, the maximum pylon moment occurred by seismic load is only decreased by 8%.
Proceedings of the Korean Geotechical Society Conference
/
2008.03a
/
pp.1036-1041
/
2008
In order to analysis the reason of sliding failure in embankment slope under construction in soft soil area, a model section located in Gimhae Region in Gyeongsangnam-Do, where the sliding failure had been occurred during embankment works in soft soil area, had been selected. This area had been firstly treated with the Pack Drain Method, and additional embankment works of 9.7 meters out of total 14 meters in thickness had been under construction. The results of analysis showed that the reason of sliding failure were overspeed in embankment construction and the overestimation of design factors in calculating strength of each layer of embankment and poor management and inaccuracy reading of measurement devices.
International conference on construction engineering and project management
/
2011.02a
/
pp.201-208
/
2011
Today's highly competitive construction scenario forces all the major players in the field to take up multiple projects which have put an undue pressure on the resources available within the organization. Under such a situation, there are many instances where in the resource requirement exceeds its availability due to multiple activities (with same resource requirement) which are scheduled to start simultaneously and thus results in the constrained resource becoming a bottleneck of the project. As a consequence of sharing resources, this paper studies the impact on the completion date of two similar projects under two different conditions, the first one resulting in a postponed end date and the second without any postponement. The resource utilization, the possibility of substitution of a resource and its subsequent impact on the deadline of the project is analyzed under these two circumstances. The study is done on a Critical Chain Project Management (CCPM) platform instead of leaving the schedule with a traditional Critical Path Method (CPM) finish, which gives an added advantage of validating the robustness of the emerging CCPM trend in the field of resource management.
Nallathiga, Ramakrishna;Shaikh, Haris D;Shaikh, Tauseef F;Sheik, Farhan A
Journal of Construction Engineering and Project Management
/
v.7
no.4
/
pp.1-12
/
2017
India has accorded a high priority to road infrastructure development through Public-Private Partnership (PPP) and it has set a high target for investment inflows. Yet, it is widely held that road/highway infrastructure has not been developing at required pace and that the road infrastructure projects under PPP have been suffering from several hurdles and delays, thereby affecting project success/failure. This paper is an attempt to analyze the critical success/failure factors of road infrastructure projects under PPP in India. A questionnaire survey was conducted among a sample of the stakeholders of road infrastructure projects to identify the critical success/failure factors during all four major project stages using different approaches. Initially, the critical factors were identified through ranking based on the average/mean score. Later, the conventional RII score was used to identify the critical success/failure factors. Finally, the critical success/failure factors were also identified based on the stakeholder-wise ranking of the factors and their convergence. The assessment revealed that there was a greater convergence across the different methods and also that there was greater consensus among project stakeholder on the critical success/failure factors of road PPP projects.
Proceedings of the Korean Institute of Building Construction Conference
/
2010.05a
/
pp.115-118
/
2010
The concept of construction information systems (IS) is very comprehensive and subjective. Acronyms in relation to the construction IS may include BIM, CIC, IT, nD-CAD, ERP, CALS, KM and so on. These terminologies are used in a somewhat mixed way causing possible misunderstandings in research and practice of construction information systems. Moreover, ever-changing construction business environment has widely affected the roles and methods of utilizing construction IS. Examples of these changes are dissemination of alternative project delivery systems, global standardization under highly competitive overseas market, and advancement of information and communication technologies. In this context, the purpose of this paper is to propose a high-level framework for information systems in the construction industry. Several different concepts in the area of construction IS were investigated first in order to identify the major variables of the framework. Trends of research and real-world implementations were then analyzed to support the rationale of the variables. Finally, a framework was proposed by re-arranging the relevant issues. Findings of this paper indicate that different acronyms commonly share many similar concepts in their definitions, however, in each acronym, the motivations and approaches to implementing construction IS are very different. Different approach can provide maximum effectiveness, while overlaps may happen causing practical inefficiency.
본 웹사이트에 게시된 이메일 주소가 전자우편 수집 프로그램이나
그 밖의 기술적 장치를 이용하여 무단으로 수집되는 것을 거부하며,
이를 위반시 정보통신망법에 의해 형사 처벌됨을 유념하시기 바랍니다.
[게시일 2004년 10월 1일]
이용약관
제 1 장 총칙
제 1 조 (목적)
이 이용약관은 KoreaScience 홈페이지(이하 “당 사이트”)에서 제공하는 인터넷 서비스(이하 '서비스')의 가입조건 및 이용에 관한 제반 사항과 기타 필요한 사항을 구체적으로 규정함을 목적으로 합니다.
제 2 조 (용어의 정의)
① "이용자"라 함은 당 사이트에 접속하여 이 약관에 따라 당 사이트가 제공하는 서비스를 받는 회원 및 비회원을
말합니다.
② "회원"이라 함은 서비스를 이용하기 위하여 당 사이트에 개인정보를 제공하여 아이디(ID)와 비밀번호를 부여
받은 자를 말합니다.
③ "회원 아이디(ID)"라 함은 회원의 식별 및 서비스 이용을 위하여 자신이 선정한 문자 및 숫자의 조합을
말합니다.
④ "비밀번호(패스워드)"라 함은 회원이 자신의 비밀보호를 위하여 선정한 문자 및 숫자의 조합을 말합니다.
제 3 조 (이용약관의 효력 및 변경)
① 이 약관은 당 사이트에 게시하거나 기타의 방법으로 회원에게 공지함으로써 효력이 발생합니다.
② 당 사이트는 이 약관을 개정할 경우에 적용일자 및 개정사유를 명시하여 현행 약관과 함께 당 사이트의
초기화면에 그 적용일자 7일 이전부터 적용일자 전일까지 공지합니다. 다만, 회원에게 불리하게 약관내용을
변경하는 경우에는 최소한 30일 이상의 사전 유예기간을 두고 공지합니다. 이 경우 당 사이트는 개정 전
내용과 개정 후 내용을 명확하게 비교하여 이용자가 알기 쉽도록 표시합니다.
제 4 조(약관 외 준칙)
① 이 약관은 당 사이트가 제공하는 서비스에 관한 이용안내와 함께 적용됩니다.
② 이 약관에 명시되지 아니한 사항은 관계법령의 규정이 적용됩니다.
제 2 장 이용계약의 체결
제 5 조 (이용계약의 성립 등)
① 이용계약은 이용고객이 당 사이트가 정한 약관에 「동의합니다」를 선택하고, 당 사이트가 정한
온라인신청양식을 작성하여 서비스 이용을 신청한 후, 당 사이트가 이를 승낙함으로써 성립합니다.
② 제1항의 승낙은 당 사이트가 제공하는 과학기술정보검색, 맞춤정보, 서지정보 등 다른 서비스의 이용승낙을
포함합니다.
제 6 조 (회원가입)
서비스를 이용하고자 하는 고객은 당 사이트에서 정한 회원가입양식에 개인정보를 기재하여 가입을 하여야 합니다.
제 7 조 (개인정보의 보호 및 사용)
당 사이트는 관계법령이 정하는 바에 따라 회원 등록정보를 포함한 회원의 개인정보를 보호하기 위해 노력합니다. 회원 개인정보의 보호 및 사용에 대해서는 관련법령 및 당 사이트의 개인정보 보호정책이 적용됩니다.
제 8 조 (이용 신청의 승낙과 제한)
① 당 사이트는 제6조의 규정에 의한 이용신청고객에 대하여 서비스 이용을 승낙합니다.
② 당 사이트는 아래사항에 해당하는 경우에 대해서 승낙하지 아니 합니다.
- 이용계약 신청서의 내용을 허위로 기재한 경우
- 기타 규정한 제반사항을 위반하며 신청하는 경우
제 9 조 (회원 ID 부여 및 변경 등)
① 당 사이트는 이용고객에 대하여 약관에 정하는 바에 따라 자신이 선정한 회원 ID를 부여합니다.
② 회원 ID는 원칙적으로 변경이 불가하며 부득이한 사유로 인하여 변경 하고자 하는 경우에는 해당 ID를
해지하고 재가입해야 합니다.
③ 기타 회원 개인정보 관리 및 변경 등에 관한 사항은 서비스별 안내에 정하는 바에 의합니다.
제 3 장 계약 당사자의 의무
제 10 조 (KISTI의 의무)
① 당 사이트는 이용고객이 희망한 서비스 제공 개시일에 특별한 사정이 없는 한 서비스를 이용할 수 있도록
하여야 합니다.
② 당 사이트는 개인정보 보호를 위해 보안시스템을 구축하며 개인정보 보호정책을 공시하고 준수합니다.
③ 당 사이트는 회원으로부터 제기되는 의견이나 불만이 정당하다고 객관적으로 인정될 경우에는 적절한 절차를
거쳐 즉시 처리하여야 합니다. 다만, 즉시 처리가 곤란한 경우는 회원에게 그 사유와 처리일정을 통보하여야
합니다.
제 11 조 (회원의 의무)
① 이용자는 회원가입 신청 또는 회원정보 변경 시 실명으로 모든 사항을 사실에 근거하여 작성하여야 하며,
허위 또는 타인의 정보를 등록할 경우 일체의 권리를 주장할 수 없습니다.
② 당 사이트가 관계법령 및 개인정보 보호정책에 의거하여 그 책임을 지는 경우를 제외하고 회원에게 부여된
ID의 비밀번호 관리소홀, 부정사용에 의하여 발생하는 모든 결과에 대한 책임은 회원에게 있습니다.
③ 회원은 당 사이트 및 제 3자의 지적 재산권을 침해해서는 안 됩니다.
제 4 장 서비스의 이용
제 12 조 (서비스 이용 시간)
① 서비스 이용은 당 사이트의 업무상 또는 기술상 특별한 지장이 없는 한 연중무휴, 1일 24시간 운영을
원칙으로 합니다. 단, 당 사이트는 시스템 정기점검, 증설 및 교체를 위해 당 사이트가 정한 날이나 시간에
서비스를 일시 중단할 수 있으며, 예정되어 있는 작업으로 인한 서비스 일시중단은 당 사이트 홈페이지를
통해 사전에 공지합니다.
② 당 사이트는 서비스를 특정범위로 분할하여 각 범위별로 이용가능시간을 별도로 지정할 수 있습니다. 다만
이 경우 그 내용을 공지합니다.
제 13 조 (홈페이지 저작권)
① NDSL에서 제공하는 모든 저작물의 저작권은 원저작자에게 있으며, KISTI는 복제/배포/전송권을 확보하고
있습니다.
② NDSL에서 제공하는 콘텐츠를 상업적 및 기타 영리목적으로 복제/배포/전송할 경우 사전에 KISTI의 허락을
받아야 합니다.
③ NDSL에서 제공하는 콘텐츠를 보도, 비평, 교육, 연구 등을 위하여 정당한 범위 안에서 공정한 관행에
합치되게 인용할 수 있습니다.
④ NDSL에서 제공하는 콘텐츠를 무단 복제, 전송, 배포 기타 저작권법에 위반되는 방법으로 이용할 경우
저작권법 제136조에 따라 5년 이하의 징역 또는 5천만 원 이하의 벌금에 처해질 수 있습니다.
제 14 조 (유료서비스)
① 당 사이트 및 협력기관이 정한 유료서비스(원문복사 등)는 별도로 정해진 바에 따르며, 변경사항은 시행 전에
당 사이트 홈페이지를 통하여 회원에게 공지합니다.
② 유료서비스를 이용하려는 회원은 정해진 요금체계에 따라 요금을 납부해야 합니다.
제 5 장 계약 해지 및 이용 제한
제 15 조 (계약 해지)
회원이 이용계약을 해지하고자 하는 때에는 [가입해지] 메뉴를 이용해 직접 해지해야 합니다.
제 16 조 (서비스 이용제한)
① 당 사이트는 회원이 서비스 이용내용에 있어서 본 약관 제 11조 내용을 위반하거나, 다음 각 호에 해당하는
경우 서비스 이용을 제한할 수 있습니다.
- 2년 이상 서비스를 이용한 적이 없는 경우
- 기타 정상적인 서비스 운영에 방해가 될 경우
② 상기 이용제한 규정에 따라 서비스를 이용하는 회원에게 서비스 이용에 대하여 별도 공지 없이 서비스 이용의
일시정지, 이용계약 해지 할 수 있습니다.
제 17 조 (전자우편주소 수집 금지)
회원은 전자우편주소 추출기 등을 이용하여 전자우편주소를 수집 또는 제3자에게 제공할 수 없습니다.
제 6 장 손해배상 및 기타사항
제 18 조 (손해배상)
당 사이트는 무료로 제공되는 서비스와 관련하여 회원에게 어떠한 손해가 발생하더라도 당 사이트가 고의 또는 과실로 인한 손해발생을 제외하고는 이에 대하여 책임을 부담하지 아니합니다.
제 19 조 (관할 법원)
서비스 이용으로 발생한 분쟁에 대해 소송이 제기되는 경우 민사 소송법상의 관할 법원에 제기합니다.
[부 칙]
1. (시행일) 이 약관은 2016년 9월 5일부터 적용되며, 종전 약관은 본 약관으로 대체되며, 개정된 약관의 적용일 이전 가입자도 개정된 약관의 적용을 받습니다.