보-기둥구조 PC공동주택 골조공사 작업관계 분석 (Relationship Analysis of Field Work in Beam-Column System Frame Work of the Precast Concrete Public Apartment Building)

  • 김기호;김진원;김민준;이동건;손정락;이범식
    • 한국건축시공학회:학술대회논문집
    • /
    • 한국건축시공학회 2022년도 가을 학술논문 발표대회
    • /
    • pp.41-42
    • /
    • 2022
  • This study analyzed the process related to the linkage between on-site work targeting the middle size Precast Concrete(PC) public apartment building with beam-column system and prepared on-site works flow relationship diagram in which the wet process consists of core Critical Path(CP) to prepare a network diagram of the Precedence Diagram Method(PDM). Through this study, it is expected that it will be possible to maximize the project management capability by suggesting a method to minimize risk factors and the optimized process management of the beam-column system PC public apartment building.