Numerical simulation by the finite element method of the constructive steps of a precast prestressed segmental bridge

  • Gabriela G., Machado;Americo Campos, Filho;Paula M., Lazzari;Bruna M., Lazzari;Alexandre R., Pacheco
    • Structural Engineering and Mechanics
    • /
    • v.85 no.2
    • /
    • pp.163-177
    • /
    • 2023
  • The design of segmental bridges, a structure that typically employs precast prestressed concrete elements and the balanced cantilever construction method for the deck, may demand a highly complex structural analysis for increased precision of the results. This work presents a comprehensive numerical analysis of a 3D finite element model using the software ANSYS, version 21.2, to simulate the constructive deck stages of the New Guaiba Bridge, a structure located in Porto Alegre city, southern Brazil. The materials concrete and steel were considered viscoelastic. The concrete used a Generalized Kelvin model, with subroutines written in FORTRAN and added to the main model through the customization tool UPF (User Programmable Features). The steel prestressing tendons used a Generalized Maxwell model available in ANSYS. The balanced cantilever constructive steps of a span of the New Guaiba Bridge were then numerically simulated to follow the actual constructive sequence of the bridge. A comparison between the results obtained with the numerical model and the actual vertical displacement data monitored during the bridge's construction was carried out, showing a good correlation.

Precast Concrete Guideway of Automated Guideway Transit with Rubber Tire. (경량전철 고무차륜용 PC슬레브 궤도)

  • 조능호;정원기;이규정;윤태양;이안호
    • Proceedings of the KSR Conference
    • /
    • 2000.11a
    • /
    • pp.295-302
    • /
    • 2000
  • Slab guideway, surface treatment, heat line installation, and joint connection for Automated Guideway Transit with rubber tire are researched. While the AGT with rubber tire is constructed in city, the precast slab guideway must be considered a reduction of the construction period and the noise under construction. which related with environment. To do that, a basic design and the structural analysis for the precast slab guideway with rubber tire are studied. The surface treatment and the heat line installation of that are also compared with currently used methods. Tining method is applied to the surface treatment adopted from the concrete pavement application currently in use. The connection method between the slab of bridge and precast guideway are suggested with a bolt type and a bond type. To minimize noise and vibration of the connection while the AGT is in driving, the slop connection method can be enhanced the serviceability.

  • PDF

Analytical Studies on Shape of Shear Pocket of Full-Depth Precast Slab (프리캐스트 바닥판의 전단포켓 형상에 관한 해석 연구)

  • Han Sang-Yun;Lee Man-Sup;Lee Seong-Rok;Song Jae-Joon;Kang Young-Jong
    • Proceedings of the KSR Conference
    • /
    • 2004.10a
    • /
    • pp.1119-1124
    • /
    • 2004
  • Full depth precast concrete bridge deck system can be advantageously to reduce construction time, hence lowering the cost. This system has several significant design and construction component. To connect between the concrete slab and steel girder, precast deck has shear pocket. Post-tensioning tightens the joints and prevents any leakage though the joint. When post-tensioning is applied, stress concentration occurs in the edge of shear pocket. In this study, precast decks using four types of shear pocket is analyzed by F.E.M.

  • PDF

Development of Hybrid Panel with C-shaped Steel Beam at Top and Bottom of Precast Concrete Wall (프리캐스트 콘크리트 벽체의 상하부에 C형강 보가 결합된 복합 패널의 개발)

  • Lee, Sang Sup;Park, Keum Sung
    • Journal of Korean Society of Steel Construction
    • /
    • v.29 no.6
    • /
    • pp.435-442
    • /
    • 2017
  • A lateral load resisting system is a necessary structural element for the mid- to high-rise modular buildings and concrete cores are known as the most typical lateral load resisting systems in 10- to 20-story modular buildings. It is difficult to construct a concrete core simultaneously with the installation and finishing work of modular units because concrete placed using wet methods might contaminate or destroy the modular unit. Therefore, we have developed a hybrid PC (precast concrete) panel construction method that can construct a concrete core together with the installation of modular units. The hybrid PC panel is a load-bearing element in which a pair of C-shaped beams are combined at the top and bottom of a concrete wall. Concrete cores can be constructed by dry method to connect the hybrid PC panels with bolts. In this study, the details and connection of hybrid PC panels are improved to have the lateral performance comparable to reinforced concrete structural walls and are verified through FE analysis.

A method for evaluation of longitudinal joint connections of decked precast concrete girder bridges

  • Smith, Matthew Z.;Li, Yue;Bulleit, William M.
    • Structural Engineering and Mechanics
    • /
    • v.40 no.3
    • /
    • pp.297-313
    • /
    • 2011
  • As bridge conditions in the United States continue to deteriorate, rapid bridge replacement procedures are needed. Decked precast prestressed concrete (DPPC) girders are used for rapid bridge construction because the bridge deck is precast with the girders eliminating the need for a cast-in-place slab. One of the concerns with using DPPC girders as a bridge construction option is the durability of the longitudinal joints between girders. The objectives of this paper were to propose a method to use a spring element modeling procedure for representing welded steel connector assemblies between adjacent girders in DPPC girder bridges, perform a preliminary study of bridge performance under multiple loading scenarios and bridge configurations, and discuss model flexibility for accommodating future field data for model verification. The spring elements have potential to represent the contribution of joint grout materials by altering the spring stiffness.

Requirement analysis for Development of the Bolt-type Rebar Coupler (볼트 접합형 철근 이음장치 개발을 위한 요구조건 분석)

  • Lim, Chae-Yeon;Joo, Jin-Kyu;Lee, Goon-Jae;Kim, Sun-Kuk
    • Proceedings of the Korean Institute of Building Construction Conference
    • /
    • 2011.11a
    • /
    • pp.169-170
    • /
    • 2011
  • In the connection of green frame, the bottom rebar of the precast concrete beam needs joint or anchorage to ensure structural integrity. However, given the characteristics of composite precast concrete joint, enough length over which rebar can be anchored or lap-spliced is not secured. In addition, due to issues with constructability, cost or quality, it is difficult to apply welding or mechanical connection techniques. Therefore, this study analyze the requirement for a bolt-type rebar coupler as a solution for the coupling issue between the lower rebars of green frame beam. The requirement for bolt-type rebar coupler proposed herein will provide basic data for development studies of the rebar coupler.

  • PDF

An Analysis of Influence Factors on Insitu-production and Installation Schedule of Composite Precast Concrete Members (합성 PC 부재의 현장생산 및 설치 공정계획의 영향요소 분석)

  • Lim, Chaeyeon;Kim, Sun Kuk
    • Proceedings of the Korean Institute of Building Construction Conference
    • /
    • 2013.05a
    • /
    • pp.176-177
    • /
    • 2013
  • The composite PC rahmen structure, called Green Frame, allows the main structural members such as PC column and beam to be produced on the site, resulting in a reduction of PC member transportation cost and the margin of PC plant (operation cost and profit), making it more economic than the bearing wall structure. To apply the Green Frame to practice, not only installation but also insitu-production process should be considered. Therefore, this study analyse the influence factors on insitu-production and installation schedule of composite precast concrete members. The results shall be used as basic criteria on the planning of insitu-production and installation of Green Frame.

  • PDF

Connection Method of Composite Precast Concrete Columns Using Thread Rebar (나사형 철근을 사용한 합성 PC기둥의 접합방법)

  • Kim, Tae-Koo;Lee, Sung-Ho;Kim, Sun-Kuk
    • Proceedings of the Korean Institute of Building Construction Conference
    • /
    • 2013.05a
    • /
    • pp.14-15
    • /
    • 2013
  • Green Frame is precast concrete column-beam structure. There are three types on column connection. The coupler type which is one of the three, need to be improved because of unstability caused by pre-installation of column before casting the slab, and quality deterioration caused by lack of workspace. Therefore, in this study, new coupler connection type with thread rebar is suggested. The result of this study shall be used for the efficiency analysis of the new coupler connection.

  • PDF

Relationship Analysis of Field Work in Beam-Column System Frame Work of the Precast Concrete Public Apartment Building (보-기둥구조 PC공동주택 골조공사 작업관계 분석)

  • Kim, Ki-Ho;Kim, Jin-Won;Kim, MIn-Jun;Lee, Dong-Gun;Sohn, Jeong-Rak;Lee, Bum-Sik
    • Proceedings of the Korean Institute of Building Construction Conference
    • /
    • 2022.11a
    • /
    • pp.41-42
    • /
    • 2022
  • This study analyzed the process related to the linkage between on-site work targeting the middle size Precast Concrete(PC) public apartment building with beam-column system and prepared on-site works flow relationship diagram in which the wet process consists of core Critical Path(CP) to prepare a network diagram of the Precedence Diagram Method(PDM). Through this study, it is expected that it will be possible to maximize the project management capability by suggesting a method to minimize risk factors and the optimized process management of the beam-column system PC public apartment building.

  • PDF

Study on Safety Evaluation of the Half-Depth Precast Deck with RC Rib Pannel for the Flexural Behavior (리브 형상을 갖는 반단면 프리캐스트 판넬의 휨 안전성 평가 연구)

  • Hwang, Hoon Hee
    • Journal of the Korean Society of Safety
    • /
    • v.34 no.4
    • /
    • pp.76-84
    • /
    • 2019
  • The precast pannels are used as formwork in Half-depth precast deck systems. Therefore, it has many advantages, including safe and convenient construction and reduced construction period compared to cast-in-place construction method. In half-depth precast deck systems, the bonding of precast pannels to cast-in place concrete is very important. To enhance the performance of half-depth precast deck system, it is necessary to improve the composite efficiency of the interface or increase the stiffness of the precast pannel to reduce deformation or stress on the interface. In this study, a flexural test of half-depth precast deck system was performed, in which the shear connecting reinforcement was applied to increase the bonding performance at the interface, and the rib shape precast panels were applied to improve stiffness. In addition, the safety and serviceability of these systems were evaluated. Test results show that all of specimens have the required flexural strength under the ultimate strength limit design. It was also evaluated to have sufficient safety for the serviceability of deflection and crack under the serviceability limit design.