• Title/Summary/Keyword: concrete tunnel

Search Result 594, Processing Time 0.024 seconds

Thermal Crack Control Using Optimized Steps of Concrete Placement in Massive Concrete Foundation (대형 기초 콘크리트의 분할타설 방법을 고려한 수화열에 의한 온도균열 제어 대책)

  • 김동규;조선규;김은겸
    • Proceedings of the Korea Concrete Institute Conference
    • /
    • 2000.10b
    • /
    • pp.1169-1174
    • /
    • 2000
  • Since the cement-water reaction in exothermic by nature, the temperature rise within a large concrete mass. Significant tensile stresses may develop from the volume change associated with the increase and decrease of the temperature with the mass concrete. There thermal stresses will cause temperature-related cracking in mass concrete structure. These typical type of mass concrete include mat foundation, bridge piers, thick wall, box type walls, tunnel linings, etc. Crack control methods can be considered at such stages as designing, selecting the materials, and detailing the construction method. Temperature and analysis was performed by taking into consideration of the cement type and content, boundary and environment conditions including the variations of atmospheric temperature and wind velocity. This is paper, the effect of separate placement of thermal crack control footing was analysed by a three dimensional finite element method. As a result, using this method, thermal crack control can be easily performed for structures such as mat structures.

  • PDF

Estimation of the Mechanical Properties of the Concrete Tunnel Lining by Drilling Resistance Test (천공저항시험에 의한 콘크리트 터널라이닝의 역학적 특성 추정)

  • Choi, Soon-Wook;Sung, Yun-Chang;Cheong, Ho-Seop;Chang, Soo-Ho
    • Journal of the Korean Geotechnical Society
    • /
    • v.23 no.11
    • /
    • pp.87-98
    • /
    • 2007
  • For the quick rehabilitation of a fire-damaged tunnel structure, it is the most important procedure to investigate the fire-induced damaged zone rapidly. This study aims to propose a new drilling resistance testing method by which mechanical properties of tunnel concrete lining altered by high temperature can be estimated easily and continuously. Especially, it alms to derive the relationships to estimate mechanical properties of mortar and concrete materials from drilling parameters. To obtain the optimum testing condition, a series of drilling resistance tests were carried out for mortar specimens. When the rotation per minute of drill bit, tile penetration rate and the bit diameter were 1,300 rpm, 1.40 mm/sec, and 10 mm respectively, the deviation of measured drilling resistance forces was minimal. Under the optimum testing condition, the relationships between drilling resistance and mechanical properties of mortar specimens were shown to be very favorable. The concept of replacing a mean value of resistance farces measured during drilling with the resistance energy was proposed to consider the effects of randomly distributed aggregates inside a concrete material on drilling resistance. When the concept was applied to concrete materials, a favorable relationship between actual compressive strength and drilling resistance energy was also successfully derived.

Wind tunnel investigation on flutter and buffeting of a three-tower suspension bridge

  • Zhang, Wen-ming;Ge, Yao-jun
    • Wind and Structures
    • /
    • v.24 no.4
    • /
    • pp.367-384
    • /
    • 2017
  • The Maanshan Bridge over Yangtze River in China is a new long-span suspension bridge with double main spans of $2{\times}1080m$ and a closed streamline cross-section of single box deck. The flutter and buffeting performances were investigated via wind tunnel tests of a full bridge aeroelastic model at a geometric scale of 1:211. The tests were conducted in both smooth wind and simulated boundary layer wind fields. Emphasis is placed on studying the interference effect of adjacent span via installing a wind deflector and a wind separating board to shelter one span of the bridge model from incoming flow. Issues related to effects of mid-tower stiffness and deck supporting conditions are also discussed. The testing results show that flutter critical wind velocities in smooth flow, with a wind deflector, are remarkably lower than those without. In turbulent wind, torsional and vertical standard deviations for the deck responses at midspan in testing cases without wind deflector are generally less than those at the midspan exposed to wind in testing cases with wind deflector, respectively. When double main spans are exposed to turbulent wind, the existence of either span is a mass damper to the other. Furthermore, both effects of mid-tower stiffness and deck supporting conditions at the middle tower on the flutter and buffeting performances of the Maanshan Bridge are unremarkable.

Laboratory and Field Model Study on the Optimum Mix of Shotcrete in Tunnel Construction (터널의 SHOTCRETE 최적배합에 관한 실내 및 현장 모형 실험 연구)

  • 오병환;박칠림;백신원;장성욱
    • Magazine of the Korea Concrete Institute
    • /
    • v.6 no.4
    • /
    • pp.131-140
    • /
    • 1994
  • Recently, tunnels are increasingly constructed in this country with the increased construction of highways, high-speed railways and subways. Shotcreting is one of the major processes in the tunnel construction. Many problems, however, exist in the current shotcreting practice. The purpose of the present study is, therefore, to explore the problems in the current shotcreting practice, to derive an optimum mix for efficient shotcreting, To this end, extensive experimental study has been conducted. Optimum mixes with high quality and economy were derived. The present study provides a firm bast: in our country to apply high-quality shotcrete in tunnel construction.

A Basic Study for Single Shell Support System of Railway Tunnel (철도 터널의 싱글쉘 지보시스템 적용에 관한 기초 연구)

  • Jung, Daeho;Jeong, Cahnmook
    • Journal of the Korean GEO-environmental Society
    • /
    • v.17 no.1
    • /
    • pp.39-48
    • /
    • 2016
  • In this study, it can be shortened tunnel construction work period by introducing a single-shell tunnel does not placing the secondary concrete lining, a global research trend, reduction of the cost of the lining placement and number of benefits that can ensure the safety of long-term tunnel with a single shell it was to study the tunnel method. First, we analyze the design and construction practices relating to delete lining of the domestic design and construction practices and a comprehensive analysis of the stability study found a rock in good condition interval (1~3 grades), we propose that the lining uninstalled. In the case of domestic changes on the ground floor is very heavy underfoot conditions many so tunneling method by single shell as ground conditions are good and one preferred the water points that apply in less soil, the soil health and poor sections (4~5 grades) reflecting with respect to the concrete lining that is expected reasonable.

Analysis of effect of hydrogen jet fire on tunnel structure (수소 제트화염이 터널 구조체에 미치는 영향 분석)

  • Park, Jinouk;Yoo, Yongho;Kim, Whiseong
    • Journal of Korean Tunnelling and Underground Space Association
    • /
    • v.23 no.6
    • /
    • pp.535-547
    • /
    • 2021
  • A policy to expand the hydrogen economy has been established in Korea and the supply of FCEV is being expanded to realize a hydrogen society. Therefore, the supply of FCEV is expected to increase rapidly, and a solution to respond to accidents of FCEV is required. In this study, an experimental study was conducted to analyze the effect of the hydrogen jet flame generated by a FCEV on the inner wall of the tunnel and the characteristics of the internal radiant heat. For the experiment, the initial pressure of hydrogen tank was set to 700 bar, and the injection nozzle diameter was set to 1.8 mm in order to make the same as the conditions generated in the FCEV. In addition, a tunnel fire resistance test specimen having the same strength as the compressive strength of concrete applied to general tunnels of 40 MPa was manufactured and used in the experiment. The results were analyzed for the separation distance (2 m and 4 m) between the hydrogen release nozzle and the tunnel fire resistance test concrete. As the result, the maximum internal temperature of the test concrete was measured to 1,349.9℃ (2 m separation distance), and the radiant heat around the jet flame was up to 39.16 kW/m2.

Assessment of long-term behaviour of a shallow tunnel in clay till

  • Wang, Z.;Wong, R.C.K.;Heinz, H.
    • Geomechanics and Engineering
    • /
    • v.2 no.2
    • /
    • pp.107-123
    • /
    • 2010
  • Ground settlements and pore pressure changes were monitored around a shallow tunnel constructed in clay till during the excavation and primary lining installation. The settlements above the tunnel continued to develop for up to 100 days after the primary lining installation. Triaxial compression tests were carried out to estimate the short-term and long-term deformation characteristics of the till. Numerical simulation was conducted to history match the field measurements, and thus, to quantify the settlements induced by ground stress relief, consolidation and creep. It was found that the surface settlements due to ground stress relief, consolidation and creep are 17, 12 and 71% of total settlement (about 44 mm), respectively. In addition, early installation of rigid concrete lining could be an effective means to reduce the settlement due to creep.

Development of Vision-Based Inspection System for Detecting Crack on the Lining of Concrete Tunnel (비젼센서를 이용한 콘크리트 터널 라이닝 균열검사 시스템의 개발)

  • 고봉수;조남규
    • Journal of the Korean Society for Precision Engineering
    • /
    • v.20 no.12
    • /
    • pp.96-104
    • /
    • 2003
  • To assess tunnel safety, cracks in tunnel lining are measured by inspectors who observe cracks with their eyes. A manual inspection is, however, slow and subjective. This paper, therefore, proposes vision-based inspection system for measuring cracks in the tunnel lining that inspects cracks fast and objective. The system is consisted of an on-vehicle system and a lab system. An on-vehicle system acquires image data with line CCD camera. A lab system extracts crack then inform their thickness, length and orientation by using image processing. To improve accuracy of crack recognition the geometric properties of a crack was applied to image processing. The proposed system were verified with experiments in both laboratory and field environment.

The ultimate bearing capacity of rectangular tunnel lining assembled by composite segments: An experimental investigation

  • Liu, Xian;Hu, Xinyu;Guan, Linxing;Sun, Wei
    • Steel and Composite Structures
    • /
    • v.24 no.4
    • /
    • pp.481-497
    • /
    • 2017
  • In this paper, full-scale loading tests were performed on a rectangular segmental tunnel lining, which was assembled by steel composite segments, to investigate its load-bearing structural behavior and failure mechanism. The tests were also used to confirm the composite effect by adding concrete inside to satisfy the required performance under severe loading conditions. The design of the tested rectangular segmental lining and the loading scheme are also described to better understand the bearing capacity of this composite lining structure. It is found that the structural ultimate bearing capacity is governed by the bond capacity between steel plates and the tunnel segment. The failure of the strengthened lining is the consequence of local failure of the bond at waist joints. This led to a fast decrease of the overall stiffness and eventually a loss of the structural integrity.

Influence of TBM operational parameters on optimized penetration rate in schistose rocks, a case study: Golab tunnel Lot-1, Iran

  • Eftekhari, A.;Aalianvari, A.;Rostami, J.
    • Computers and Concrete
    • /
    • v.22 no.2
    • /
    • pp.239-248
    • /
    • 2018
  • TBM penetration rate is a function of intact rock properties, rock mass conditions and TBM operational parameters. Machine rate of penetrationcan be predicted by knowledge of the ground conditions and its effects on machine performance. The variation of TBM operational parameters such as penetration rate and thrust plays an important role in its performance. This study presents the results of the analysis on the TBM penetration rates in schistose rock types present along the alignment of Golab tunnel based on the analysis of a TBM performance database established for every stroke through different schistose rock types. The results of the analysis are compared to the results of some empirical and theoretical predictive models such as NTH and QTBM. Additional analysis was performed to find the optimum thrust and revolution per minute values for different schistose rock types.