Experimental study on the ground arching depending on the deformation type of the crown in the shallow tunnel (얕은터널에서 천단의 변형형태에 따른 그라운드 아칭에 관한 실험적 연구)

  • Yim, Il Jae;Lee, Sang Duk
    • Journal of Korean Tunnelling and Underground Space Association
    • /
    • v.19 no.5
    • /
    • pp.733-747
    • /
    • 2017
  • In the shallow tunnel, the surrounding ground could be loosened and deformed, which could be the cause of stress change in the ground. Terzaghi has clarified the development of a ground arching induced by the deformation of a tunnel crown in the trap door tests. However, he considered only the case in which that the tunnel crown deformed uniformly. He did not consider the effect of deformation shapes. Therefore, the relation between the shape of the ground relaxation above the tunnel crown and the deformation shape of the tunnel crown is not clear yet. In this study, model tests were performed for the three types of the tunnel crown, such as uniform, concave and convex shapes. As results, it was found that the vertical load would be transferred in various types depending on the deformation shapes of the tunnel crown.

The Pre-Evaluation of Stability during Tunnel Excavation using Unconfined Compression Strength of Intact Rock or Rock Mass and Crown Settlement Data (터널천단변위와 암석 또는 암반의 일축압축강도를 이용한 시공 중인 터널의 예비 안정성 평가)

  • Park, Young Hwa;Moon, Hong Duk;Ha, Man Bok
    • International Journal of Highway Engineering
    • /
    • v.17 no.6
    • /
    • pp.27-32
    • /
    • 2015
  • PURPOSES : It is difficult to estimate tunnel stability because of lack of timely information during tunnel excavation. Tunnel deformability refers to the capacity of rock to strain under applied loads or unloads during tunnel excavation. This study was conducted to analyze a methods of pre-evaluation of stability during tunnel construction using the critical strain concept, which is applied to the results of tunnel settlement data and unconfined compression strength of intact rock or rock mass at the tunnel construction site. METHODS : Based on the critical strain concept, the pre-evaluation of stability of a tunnel was performed in the Daegu region, at a tunnel through andesite and granite rock. The critical strain concept is a method of predicting tunnel behavior from tunnel crown settlement data using the critical strain chart that is obtained from the relationship between strain and the unconfined compression strength of intact rock in a laboratory. RESULTS : In a pre-evaluation of stability of a tunnel, only actually measured crown settlement data is plotted on the lower position of the critical strain chart, to be compared with the total displacement of crown settlement, including precedent settlement and displacement data from before the settlement measurement. However, both cases show almost the same tunnel behavior. In an evaluation using rock mass instead of intact rock, the data for the rock mass strength is plotted on the lower portion of the critical strain chart, as a way to compare to the data for intact rock strength. CONCLUSIONS : From the results of the pre-evaluation of stability of the tunnel using the critical strain chart, we reaffirmed that it is possible to promptly evaluate the stability of a tunnel under construction. Moreover, this research shows that a safety evaluation using the actual instrumented crown settlement data with the unconfined compression strength of intact rock, rather than with the unconfined compression strength of a rock mass in the tunnel working face, is more conservative.

Behaviour Analysis of Crown Collapse under Tunnel Construction After Completing Reinforcement (보강완료 후 시공 중 터널 천단부 붕락 거동 분석)

  • Kim, Nagyoung;Baek, Seungchol;Min, Kyungjun;Kim, Bongsu;Heo, Yol
    • Journal of the Korean GEO-environmental Society
    • /
    • v.17 no.4
    • /
    • pp.39-46
    • /
    • 2016
  • The final stability analysis of the tunnel structure is generally evaluated by performing site monitoring to determine whether or not the measured value through the convergence after the completion of excavation in the face. When the ground conditions are so poor, the reinforcement around the tunnel was applied for enhancing the stability of tunnels. For the additional tunnel crown collapse or excessive displacement have occurred under construction, correlation analysis were performed for the comparison construction and numeric analyses. In this paper, we investigated the collapse types, tunnel collapse were mostly occurs at the crown and they were analyzed because of the geological conditions in the collapse zone. And also, it was analyzed as being correlated in the crown of tunnel exists a fault fracture zone which extends to the surface part. Thus, in case of ground conditions such as fault fracture zone with a tunnel extending from the crown to the surface, the behavior is larger than the behavior predicted by numerical method.

A Study on the Mechanical Characteristics of Tunnel Structures and Ground Behavior by Synthetic Analysis Method with Tunnel Monitoring Results used (터널의 계측결과 종합분석에 의한 지반의 거동 및 터널 구조체의 역학적 특성 연구)

  • Woo, Jong-Tae
    • Journal of the Korea institute for structural maintenance and inspection
    • /
    • v.7 no.3
    • /
    • pp.115-124
    • /
    • 2003
  • In this study, the relationships between the displacement and stress of the tunnel using various analysis methods were compared with monitoring results carried out during construction and maintenance monitoring. The behavior of tunnel were measured in the subway tunnel passing comparative soft the weathering and analyzed both security and mechanical characteristics of the tunnel lining. With the results of simplified monitoring observed in top heading and bench excavation tunnel, it is confirmed that the crown settlement is larger than the surface settlement. it is interesting to note that the crown settlement and the crown shotcrete lining stress are widely used monitoring items for the back analysis. It is analyzed that the residual water pressure applied in the drainage type tunnel is reasonable.

Tunnel Convergence and Crown Observation using Industrial Photogrammetry (산업사진측량을 이용한 터널의 천단 및 내공 변위 관측)

  • Jung Sung Hyuk;Lee Jae Kee
    • Journal of the Korean Society of Surveying, Geodesy, Photogrammetry and Cartography
    • /
    • v.22 no.3
    • /
    • pp.209-215
    • /
    • 2004
  • Together with the requirements of tunnels, its construction methods and technologies have been pretty much developed, but frequent accidents happened under the constructions are just one of important problems which should be improved. To detect the potential hazardous factors in or ahead of time, speedy and accurate observation are absolutely required, but currently surveying method using tapes, level and total station, has been generally taken in measuring of tunnel convergence and crown. The purpose of this study is, as using of industrial photogrammetry system which is supplying more accuracy and speedy in the measure of tunnel convergence and crown. From the result of this study, we have got up to 1/20,000 accuracy and totally 6 minutes, from picturing 5 sections by one person to data edition, has been taken except setting targets.

Major causes of failure and recent measurements of tunnel construction (터널시공 중 붕락발생 원인과 최신 보강기술)

  • Park, Bong-Ki;Hwang, Je-Don;Park, Chi-Myeon;Kim, Sang-Su
    • Proceedings of the Korean Geotechical Society Conference
    • /
    • 2005.10a
    • /
    • pp.140-153
    • /
    • 2005
  • During the tunnel construction the major failure mode can be categorized as: tunnel failure just after the tunnel excavation without support, failure after application of shotcrete and finally failure after setting the concrete lining. The failure mode just after the tunnel excavation without support, can be further classified as : bench failure, crown failure, face failure, full face failure, failure due to weak strata and failure due to overburden. Moreover the failure after application of shotcrete is classified as heading face failure, settlement of shotcrete support, local failure of shotcrete lining and invert shotcrete. To find out the major causes of tunnel collapse, the investigation was done in case of the second phase of Seoul subway construction. The investigation results depicted that the major causes of tunnel collapse were due to the weak layer of rock/fault and sudden influx of ground water from the tunnel crown. While the investigation results of the mountain road tunnels construction have shown that the major causes of tunnel failure were inadequate analysis of tunnel face mapping results, intersection of faults and limestone cavities. In this paper some recent measurement in order to mitigate such tunnel collapse are presented

  • PDF

Analysis of the Structural Behaviors of Tunnel Linings in Joomunjin Standard Sand by Centrifugal Model Tests (원심모형실험에 의한 사질토 지반내 터널 복공의 역학적 거동에 관한 연구)

  • 김택곤;김영근;박중배;이희근
    • Proceedings of the Korean Geotechical Society Conference
    • /
    • 1999.10a
    • /
    • pp.161-168
    • /
    • 1999
  • A series of centrifuge model tests were performed in order to investigate the behaviors of various tunnel linings. A 1/100-scaled aluminum and hydrostone horseshoe tunnel linings with a radius km, height km were buried in a depth of C/D=3 with dry Joomunjin standard sand, the relative density of which was 86%. Bending moments and thrusts along the tunnel circumference were measured by 12 strain gages. Earth pressures in soil and on lining were estimated by pressure transducers, ground surface settlements at center and edges by using LVDTs. Average Ko(coefficient of earth pressure at rest) was 0.39 for the model sand. The structural behaviors of lining depended on its damaged conditions. But, as a rule, on the crown, the tensile circumferential strain of lining occurred at the inner surface, and the compressive at the outer surface, then positive bending moment was created at the crown. The circumferential strain of the inner surface on the springline was tensile, and the outer compressive, so negative bending moment was measured at the springline. For hydrostone linings, cracks initiated at the inner surface on the crown, and the outer on the springline over average 40g.

  • PDF

Prediction of fault zone ahead of tunnel face using x-Rs control chart analysis for crown settlement (천단변위의 x-Rs 관리도 분석을 이용한 터널 막장 전방 단층대 예측)

  • Yun, Hyun-Seok;Seo, Yong-Seok;Kim, Kwang-Yeom
    • Journal of Korean Tunnelling and Underground Space Association
    • /
    • v.16 no.4
    • /
    • pp.361-372
    • /
    • 2014
  • A measurement of tunnel displacement plays an important role for stability analysis and prediction of possible fault zone ahead of tunnel face. In this study, we evaluated characteristics of tunnel behaviour due to the existence and orientation of fault zone based on 3-dimensional finite element numerical analysis. The crown settlement representing tunnel behaviour is acquired at 5 m away from tunnel face in combination with x-Rs control chart analysis based on statistics for trend line and L/C (longitudinal/crown displacement) ratio in order to propose risk management method for fault zone. As a result, x-Rs control chart analysis can enable to predict fault zone in terms of existence and orientation in tunnelling.

A numerical study on the behavior of existing and enlarged tunnels when widened by applying the pre-cutting method (Pre-cutting 공법을 적용한 터널 확폭 시 기존 및 확폭터널의 거동에 관한 수치해석적 연구)

  • Kim, Han-Eol;Nam, Kyoung-Min;Ha, Sang-Gui;Yoo, Han-Kyu
    • Journal of Korean Tunnelling and Underground Space Association
    • /
    • v.22 no.4
    • /
    • pp.451-468
    • /
    • 2020
  • Aging tunnels with small cross-sections can cause chronic traffic jams. This problem can be solved by widening the tunnel. In general, when the tunnel is expanded, the outer portion of the existing tunnel is excavated through a mechanical or blasting method. Such excavation affects not only the surrounding ground but also the existing tunnel. The application of the pre-cutting method can be a solution to these problems effectively. Therefore, if the widening of tunnel is performed by applying pre-cutting method, analysis of the impact of this method must be performed. In this study, in order to analyze the effect of applying pre-cutting in tunnel widening, numerical analysis is performed at six ground grades, from grade I to weathered rock. The analysis is performed with the expanding lane and the excavation length of pre-cutting as variables. In addition, the analysis is focused on the displacement of crown of the existing tunnel and the enlarged tunnel. As a result, the crown displacement of the enlarged tunnel is confirmed to converge at the same value regardless of the excavation length of the pre-cutting when the tunnel widening is completed. In the case of existing tunnels, uplift of crown occurs within 5 m of the front of the tunnel surface, and the shorter the excavation length of pre-cutting is found to be effective in preventing the occurrence of uplift.

Field Measurements with the Construction of Cut and Cover Tunnel (복개 터널구조물의 현장 시공에 따른 계측 분석 사례)

  • 박시현;이석원;이규필;배규진;전오성;이종성
    • Proceedings of the Korean Geotechical Society Conference
    • /
    • 2002.03a
    • /
    • pp.149-156
    • /
    • 2002
  • Field measurements were carried out in this study to investigate the behavior of cut and cover tunnel such as the distribution and the magnitude of the earth pressure during back fill process of the ground material. Three kinds of measuring instruments, such as the earth pressure load cell, the concrete strain gauge and the reinforcing bar meter of embedded type in concrete structure were installed and measured. Earth pressure load cells, installed after construction of the tunnel lining, measure the outside forces acting on the tunnel lining with radial directions. Three load cells were installed at the crown, the right and the left shoulder of the tunnel, respectively. Three sets of reinforcing bar meter were installed in the double reinforcements of the tunnel lining and their locations were the same with the position of the earth pressure load cells. Concrete strain gauge was installed only one site of the upper compressive part at the tunnel crown. Based on the measuring results in the field, the deformation and the earth pressure acting on the tunnel lining were investigated with the back fill process of the ground material. Considerations on the validity of the measuring results were paid. For the analysis of measurements, after dividing back fill process into three steps, various factors which affect on the behavior of tunnel lining were investigated at each step.